03-Hire Charges



HIRE CHARGES FOR MACHINERY

Sl.
No.
Description Unit Hire Charges
for 2020-21
Remarks
Machine Activity ( Rupees)
1 2 3 4 6 7
1 Dozer( D 80 ) Spreading Per Hour   As per I&CAD S.No 8
Cutting
Cleaning
2 Dozer( D 50 ) Spreading Cutting
Cleaning
Per Hour 1758.40  
3 Mortor Grader Clearing Per Hour 3601.92  
Spreading
GSB
WMM
4 Hydraulic Excavator Soil Ordinary Per Hour   As per I&CAD S.No.52
Soil Marshy
Soil unsuitable
5 Front end loader Soil loading Per Hour 1843.52  
Aggregate loading Per Hour
6 Tipper- 5.5 Cum Transportation of soil, GSB,WMM, Hot mix etc Per Hour   As per
I&CAD S.No.54
Per tonne
Km
8.00  
7 Vibratory roller 8 tonne Earth/Soil, GSB, Per Hour   As per
I&CAD S.No.62
WMM
8 Smooth wheeled roller 8 tonne Soil compaction ,BM compaction Per Hour   As per I&CAD
S.No.50
9 Water tanker 8 Kilolitre Water transport Per Hour   As per I&CAD
S.No.64
10 Water tanker 6
Kilolitre
Water transport Per Hour 698.88  
11 Tractor Pulling Per Hour 464.80  
12 Tractor with
rotavator
Scarifying Per Hour 472.64  
13 Tractor with ripper
attachment
Scarifying Per Hour 568.23  
14 Air Compressor General purpose Per Hour   As per I&CAD
S.No.2
15 Wet mix plant 60 TPH Wet mix Per Hour 1843.52  
16 Mechanical broom
Hydraulic
Surface cleaning Per Hour 399.84  
17 Bitumen Pressure
Distributor
Applying bitumen tack
coat
Per Hour 1677.76  
18 Emulsion Pressure Applying emulsion Per Hour 963.20  
  Distributor tack coat      
19 Hot mix Plant – 120
TPH capacity
DBM/BM/SDC Per Hour 31556.00  
/Premix
20 Hot mix Plant – 100
TPH capacity
DBM/BM/SDC Per Hour 27071.52  
/Premix
21 Hot mix Plant – 60
TPH capacity
DBM/BM/SDC Per Hour 24268.16  
/Premix
22 Hot mix Plant – 40 to
60 TPH capacity
DBM/BM/SDC Per Hour 21414.40  
/Premix
23 Paver Finisher Hydrostatic with sensor control 100
TPH
DBM/BM/SDC Per Hour 3426.65  
/Premix
24 Paver finisher
Mechanical 100
Paving of WMM,
paving of DLC
Per Hour 2518.88  
25 Hydraulic Chip
Spreader
Surface dressing Per Hour 2875.04  
26 Tandem Road roller Rolling of Asphaltic
surface
Per Hour 1843.52  
27 Pneumatic Road roller Rolling of Asphaltic
surface
Per Hour 1436.96  
28 Pot-Hole repair
machine
Repair of pot-holes Per Hour 946.40  
29 Bitumen boiler oil
fired
Bitumen Spraying Per Hour 234.08  
30 GSB Plant 50 Cum Producing GSB Per Hour 1280.16  
31 Mastic Cooker Mastic wearing coat Per Hour 72.80  
32 Batching and Mixing
Plant (a) 30 Cum capacity
Concrete mixing Per Hour 1379.73 As per
I&CAD S.No.10
(b) 15 - 20 Cum
capacity
Concrete mixing Per Hour  
33 Transit mixer Transportation of concrete mix Per Hour   As per
I&CAD S.No.1
34 Concrete pump of 45
and 30 cum
Pumping of Concrete Per Hour 899.36  
35 Cranes        
(a) 80 tonnes Lifting purpose Per Hour 1311.52
(b) 35 tonnes 885.92
(c) 3 tonnes 394.24
(d)Crane with grab
bucket 0.75 cum
Well foundation Per Hour 2419.2
(e)Crane with grab bucket 1 cum Well foundation Per Hour 3955.84
36 Concrete bucket For pouring concrete Per Hour   As per
          I&CAD
S.No.14
37 Kerb casting machine Kerb making Per Hour 348.32  
38 Concrete mixer Concrete mixing Per Hour   As per I&CAD S.No.18
(a)0.28 cum
(b) 1.0 cum Concrete mixing Per Hour 726.88
39 Piling rig with
bantonite pump
0.75 m dia to 1.20 m
dia boring attachment
Per Hour 6132  
40 Concrete paver
finisher with 40 HP motor
Paving of concrete surface Per Hour 3248  
41 Integrated stone crusher Crushing of spalls 100
TPH
Per Hour 9757.44  
Crushing of spalls 200
TPH
Per Hour 20573.28
42 Pre stressing jack
with pump and access
Stressing of steel
wires/ stands
Per Hour 157.92  
43 Generator        
250 KVA Generation of electric energy per hour 2072.00  
125 KVA per hour 1478.40  
100 KVA per hour 1261.12  
30 KVA per hour   As per I&CAD
S.No.23
44 Pneumatic sinking of
Plants
Pneumatic sinking of
wells
Per K.m. 62.72  
45 Truck 5.5 cum per 10 tonnes Material transport Per Km.   As per
I&CAD S.No.58
46 Road marking
machine
Road marking Per Hour 124.32  
47 Mobile slurry seal
equipment
Mixing and laying
slurry seal
Per Hour 1261.12  
48 Plate compacter For compacting in
medians
Per Hour 53.76  
49 Drilling equipment For drilling Per Hour   As per
I&CAD S.No.22
Note: The above hire charges of machinery & plant includes crew, oils, conveyance of machinery to site and all other incidental charges.

*****