HIRE CHARGES FOR MACHINERY
Sl. No. |
Description | Unit | Hire Charges for 2020-21 |
Remarks | |
Machine | Activity | ( Rupees) | |||
1 | 2 | 3 | 4 | 6 | 7 |
1 | Dozer( D 80 ) | Spreading | Per Hour | As per I&CAD S.No 8 | |
Cutting | |||||
Cleaning | |||||
2 | Dozer( D 50 ) | Spreading Cutting Cleaning |
Per Hour | 1758.40 | |
3 | Mortor Grader | Clearing | Per Hour | 3601.92 | |
Spreading | |||||
GSB | |||||
WMM | |||||
4 | Hydraulic Excavator | Soil Ordinary | Per Hour | As per I&CAD S.No.52 | |
Soil Marshy | |||||
Soil unsuitable | |||||
5 | Front end loader | Soil loading | Per Hour | 1843.52 | |
Aggregate loading | Per Hour | ||||
6 | Tipper- 5.5 Cum | Transportation of soil, GSB,WMM, Hot mix etc | Per Hour | As per I&CAD S.No.54 |
|
Per tonne Km |
8.00 | ||||
7 | Vibratory roller 8 tonne | Earth/Soil, GSB, | Per Hour | As per I&CAD S.No.62 |
|
WMM | |||||
8 | Smooth wheeled roller 8 tonne | Soil compaction ,BM compaction | Per Hour | As per I&CAD S.No.50 |
|
9 | Water tanker 8 Kilolitre | Water transport | Per Hour | As per I&CAD S.No.64 |
|
10 | Water tanker 6 Kilolitre |
Water transport | Per Hour | 698.88 | |
11 | Tractor | Pulling | Per Hour | 464.80 | |
12 | Tractor with rotavator |
Scarifying | Per Hour | 472.64 | |
13 | Tractor with ripper attachment |
Scarifying | Per Hour | 568.23 | |
14 | Air Compressor | General purpose | Per Hour | As per I&CAD S.No.2 |
|
15 | Wet mix plant 60 TPH | Wet mix | Per Hour | 1843.52 | |
16 | Mechanical broom Hydraulic |
Surface cleaning | Per Hour | 399.84 | |
17 | Bitumen Pressure Distributor |
Applying bitumen tack coat |
Per Hour | 1677.76 | |
18 | Emulsion Pressure | Applying emulsion | Per Hour | 963.20 | |
Distributor | tack coat | ||||
19 | Hot mix Plant – 120 TPH capacity |
DBM/BM/SDC | Per Hour | 31556.00 | |
/Premix | |||||
20 | Hot mix Plant – 100 TPH capacity |
DBM/BM/SDC | Per Hour | 27071.52 | |
/Premix | |||||
21 | Hot mix Plant – 60 TPH capacity |
DBM/BM/SDC | Per Hour | 24268.16 | |
/Premix | |||||
22 | Hot mix Plant – 40 to 60 TPH capacity |
DBM/BM/SDC | Per Hour | 21414.40 | |
/Premix | |||||
23 | Paver Finisher Hydrostatic with sensor control 100 TPH |
DBM/BM/SDC | Per Hour | 3426.65 | |
/Premix | |||||
24 | Paver finisher Mechanical 100 |
Paving of WMM, paving of DLC |
Per Hour | 2518.88 | |
25 | Hydraulic Chip Spreader |
Surface dressing | Per Hour | 2875.04 | |
26 | Tandem Road roller | Rolling of Asphaltic surface |
Per Hour | 1843.52 | |
27 | Pneumatic Road roller | Rolling of Asphaltic surface |
Per Hour | 1436.96 | |
28 | Pot-Hole repair machine |
Repair of pot-holes | Per Hour | 946.40 | |
29 | Bitumen boiler oil fired |
Bitumen Spraying | Per Hour | 234.08 | |
30 | GSB Plant 50 Cum | Producing GSB | Per Hour | 1280.16 | |
31 | Mastic Cooker | Mastic wearing coat | Per Hour | 72.80 | |
32 | Batching and Mixing Plant (a) 30 Cum capacity |
Concrete mixing | Per Hour | 1379.73 | As per I&CAD S.No.10 |
(b) 15 - 20 Cum capacity |
Concrete mixing | Per Hour | |||
33 | Transit mixer | Transportation of concrete mix | Per Hour | As per I&CAD S.No.1 |
|
34 | Concrete pump of 45 and 30 cum |
Pumping of Concrete | Per Hour | 899.36 | |
35 | Cranes | ||||
(a) 80 tonnes | Lifting purpose | Per Hour | 1311.52 | ||
(b) 35 tonnes | 885.92 | ||||
(c) 3 tonnes | 394.24 | ||||
(d)Crane with grab bucket 0.75 cum |
Well foundation | Per Hour | 2419.2 | ||
(e)Crane with grab bucket 1 cum | Well foundation | Per Hour | 3955.84 | ||
36 | Concrete bucket | For pouring concrete | Per Hour | As per | |
I&CAD S.No.14 |
|||||
37 | Kerb casting machine | Kerb making | Per Hour | 348.32 | |
38 | Concrete mixer | Concrete mixing | Per Hour | As per I&CAD S.No.18 | |
(a)0.28 cum | |||||
(b) 1.0 cum | Concrete mixing | Per Hour | 726.88 | ||
39 | Piling rig with bantonite pump |
0.75 m dia to 1.20 m dia boring attachment |
Per Hour | 6132 | |
40 | Concrete paver finisher with 40 HP motor |
Paving of concrete surface | Per Hour | 3248 | |
41 | Integrated stone crusher | Crushing of spalls 100 TPH |
Per Hour | 9757.44 | |
Crushing of spalls 200 TPH |
Per Hour | 20573.28 | |||
42 | Pre stressing jack with pump and access |
Stressing of steel wires/ stands |
Per Hour | 157.92 | |
43 | Generator | ||||
250 KVA | Generation of electric energy | per hour | 2072.00 | ||
125 KVA | per hour | 1478.40 | |||
100 KVA | per hour | 1261.12 | |||
30 KVA | per hour | As per I&CAD S.No.23 |
|||
44 | Pneumatic sinking of Plants |
Pneumatic sinking of wells |
Per K.m. | 62.72 | |
45 | Truck 5.5 cum per 10 tonnes | Material transport | Per Km. | As per I&CAD S.No.58 |
|
46 | Road marking machine |
Road marking | Per Hour | 124.32 | |
47 | Mobile slurry seal equipment |
Mixing and laying slurry seal |
Per Hour | 1261.12 | |
48 | Plate compacter | For compacting in medians |
Per Hour | 53.76 | |
49 | Drilling equipment | For drilling | Per Hour | As per I&CAD S.No.22 |
|
Note: The above hire charges of machinery & plant includes crew, oils, conveyance of machinery to site and all other incidental charges. |
*****