04-Conveyance Charges



LEAD/LIFT/LOADING & UNLOADING CHARGES FOR THE YEAR 2020-21

LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS

1. For total lead up to 150 m (including initial lead) lead charges by head load only shall be adopted irrespective of mode of conveyance.

2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of mode of conveyance.

3. The rates for loading at quarry including idle hire charges of trucks and hire charges per for each kilometre and up to 5 km are cumulative and inclusive of total charges for preceding lead.

4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones are for loose volume and not for compacted or in-situ volume.

5. The rates for lift charges, lead charges, hire charges are cumulative and inclusive of rates for preceding lift, lead and hire charges

6. Lift charges are not payable where conveyance of materials is by mechanical means to final placing point.

7. Loading and unloading charges are not payable for conveyance by head load.

8. Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 50 m wherever specified.

9. Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 1 km wherever specified.

10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone are inclusive of stacking.

11. Hire charges are per 1KM for tippers and trucks for transport of materials from work site to dump yard and other places are cumulative& includes previous km up to 5 kms.

12. The lead & lift charges are inclusive of contractor's profit and overhead charges of 13.615%

13. During the BoCE meeting held on 26.05.2016, it is observed that the in some of the estimates, Lead charges are being added directly to the material basic rates for arriving the finished item rate. In view of that, the BoCE has instructed to see that while arriving the finished item rate the lead charges are to be added to the material basic rates only after deducting the provision of Contractor’s Profit and Overhead charges.

COM-LDLFT-1 A. (Lead) Conveyance Charges for materials by head load

  Total distance ( Total lead includes initial lead
)
Earth / Sand /Gravel / Murrum / Lime/ Surki/ Size stone / Cut stone Rubble / Coarse aggregate    Rs/ Cum Cement / Reinforcement steel Strutrural steel
Rs / tonne
PCC slab/ Shahbad slab / CC block/ BS slab / Late- rite / Wood
Rs / cum
1 2 3 4 5
1 Total lead upto 50 m
(covered by item rate)
Initial Lead Initial Lead Initial Lead
2 Total lead upto 100 m 75.50 44.00 96.10
3 Total lead upto 150 m 150.90 88.10 192.10

Notes: 1. No loading or unloading charges are admissible for conveyance by head load.

2. For total lead exceeding 150 m conveyance charges by mechanical means only shall be adopted irrespective of mode of conveyance.

3. The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

COM-LDLFT-2 B. (Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks excluding loading, unloading and idle hire charges of machinery. ( No loading and unloading charges allowed for machinery loading and unloading )

Sl. No Distance (Lead) charges for trucks and tippers for Earth / Sand /Gravel / Murrum/ Lime/ Surki/ per cu.meter (Lead) charges for trucks and tippers for Rubble/Size stones/ Cut Stones/ Coarse aggregate per cu.meter (Lead) charges for trucks and tippers for Cement/ Steel/ RCC poles/ AC & GI sheets/ Packed materials/ tonne (Lead) charges for trucks and tippers per cu.meter for PCC slabs/ Shahabad slabs/ CC & Laterite blocks/ Wood/ cum (Lead) charges for per cu.met er for water/ 1000 litres (Lead) charge s for trucks per 1000 Nos. of Bricks
1 2 3 4 5 6 7 8
1 Lead  up to 1 km 35.30 33.80 21.10 49.80 20.90 56.40
2 Lead  up to 2 km 49.40 47.40 29.60 69.70 29.30 79.00
3 Lead up to  3 km 65.90 65.90 41.20 96.90 39.00 105.30
4 Lead  up to 4 km 80.00 80.00 50.00 117.70 47.40 127.80
5 Lead  up to 5 km 94.10 94.10 58.80 138.40 55.80 150.40
6 for Every km beyond 5 km
upto 30 km
14.10 14.10 8.80 20.80 8.40 22.60
7 for Every km
beyond 30 km
11.80 11.80 7.40 17.30 7.00 18.80

Note:   The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

C   OM-LDLFT-3 
C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)

Sl No. Description of item Earth / Sand
/Gravel Murrum/ Surki/
Rs / cum
Rubble/ size stone/ cut stone/ Coarse aggregate,Lime
in Rs/cum
Cement in Rs/tonne Steel  in Rs./tonne Brick work Rs/1000
No
1 2 3 4 5 6 7
1 Loading 25.00 50.10 82.60 99.00 68.80
2 Unloading 12.50 25.05 82.60 99.00 68.80

Note:   The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

C   OM-LDLFT-4 
D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks)

Sl No. Description of item Earth / Sand
/Gravel Murrum/ / Surki/
Rs / cum
Rubble/ size stone/ cut stone/ Coarse aggregate,Lime in
Rs/cum
Cement in Rs/tonne Steel  in Rs./tonne Brick work Rs/1000
No
1 2 3 4 5 6 7
1 Loading 127.60 152.60 195.40 211.80 254.90
2 Unloading 46.60 76.30 195.40 211.80 254.90

COM-LDLFT-5

E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)

Sl No. Description of item Earth / Sand /Gravel Murrum/ Surki
Rs / cum
Rubble/ size stone/ cut stone/ Coarse aggregate,
Lime in Rs/cum
1 2 3 4
1 Loading 55.80 110.90
2 Unloading 17.80 17.80

Note:   The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

C   OM-LDLFT-6
F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

Sl No. Total lift
( Total lift includes initial lift )
Earth / Sand /Gravel Murrum/ Lime/ Surki/ Size stone / Cut stone Rubble / Coarse aggregate
Rs / cum
Cement / Reinforcement steel Structural steel
Rs / tonne
PCC slab/ Shahbad slab / CC block/ BS slab / Laterite
/ Wood
Rs / cum
1 2 3 4 5
1 Total lift upto 3 m (covered
by item rate)
Initial lift Initial lift Initial lift
2 For Every 1.00 Lift beyond
initial lift of 3 meters
8.80 6.40 11.70

*****