05-Head Loads& Conveyance



ANNEXURE-IV
RATES FOR CONVEYANCE  OF MATERIALS BY HEAD LOAD

sn no Description of Material Unit Basic Rate approved for the year 2020-2021 (w.e.f. 20.04.2020}
LEAD LIFT
Above 1Om and upto 1OOm Add extra for every additional 1OOm or part thereof Add extra for every 1m height or part thereof for more than 2m lift
1 Rough Stone, Broken Stone Jelly, Cut Stone, RCC   Slab,   Sand-Cement   Block,   Wooden Scantling, Wooden Plank cum. 101.20 42.00 10.95
2 Lime,   Lime    Stone,    Laterite,    Brick   Jelly, Earth,  Sand,  Gravel,  Surki,  Pond  Ash  (Wet / Dry), Crushed Stone Sand, Stone Dust cum. 53.80 42.00 8.20
3 a Mangalore Tiles 1000 Nos. 109.70 55.10 13.85
b Machine Pressed Tiles 2000 Nos. 109.70 55.10 13.85
c Hydraulic Pressed Nosaic Flooring Tiles 1500 Nos. 109.70 55.10 13.85
d Terrace Bricks, Flat Tiles and Pan Tiles 2500 Nos. 109.70 55.10 13.85
e Bricks 1000 Nos. 109.70 55.10 13.85
4 Cement, AC Sheet, Bitumen,  Asphalt, far MT 99.90 55. 10 10.95
5 Steel MT 167.90 67.50 13.85
Note:  
1 Fraction of 100 metres to be rounded ofT to the nearest 100 metres.
2 The rates indicated  in the table  shall  be applicable  only to inaccessible  places  (i.e.) the places  wherever  the Bullock  Carts cannot move [Chief Engineer (General}, Memo No. CTO (A) /  38153 / 89, dated 03.02.1989].
3 For an initial lead of 10 metre and initial lift of 2 metre, no charge towards head load is allowable.
4 The Basic Rate adopted under this Head, "Annexure-IV  — Rates of Conveyance of Materials by Head Load" is exclusive of all taxes and GST.

ANNEXURE-V
CONVEYANCE  TABLE
{A}. RATES FOR CONVEYANCE OF MATERIALS BY ROAD IN  PLAINS

s.
No.
Distance in kilometre Basic Rate approved for the year  2020-2021 w.e.f. 20.04.2020}
Cement,
S*tuee»l
Lime Stone, Lateriter    rick Jelly, Wood Work, Pond Ash (Wet /  Dry}, Stone Dust
{One cubic metre)
Rough Stone, Bond Stone, Cut Stone, Broken Stone Jelly, Sand, Gravel, Surki, Earth, Crushed Stone Sand
(One cubic metre)
Third Class Country Bricks (Kiln Burnt}
{1000 Nos.}
Mangalore Tiles
(1000 Nos.},
Machine Pressed Tiles (2000 Nos.), Hydraulically Pressed Mosaic Flooring Tiles (1500 Nos.}
Bricks II  Class Chamber Burnt Bricks (Table Moulded / Ground Moulded},
Fly Ash Bricks (1000 Nos.)
1 2 3 4 5 6 7 8
1 Co-efficient 1.00 1.10 1.60 1.35 1.80 2.25
2 Add for every extra 1 Km and   art thereof..................        
3 0 - 10 Km. 6.51 7.14 10.40 8.78 11.70 14.62
4 10 - 20 Km. 5.57 6.12 8.90 7.51 10.02 12.52
5 20 - 40 Km. 4.79 5.27 7.67 6.45 8.62 10.77
6 40 - 80 Km. 4.13 4.55 7.19 5.57 7.42 9.30
7 Above 80 Km. 3.77 4.15 6.03 5.09 6.78 8.48
8 Loading Charges 116.30 55.50 38.00 54.60 54.60 54.60
9 Unloading Charges 116.30 55.50 38.00 54.60 54.60 54.60
10 Add  above  extra  for  inter
state works
23.40 25.70 37.60 31.60 42.20 53.00
Note :
1 The above rates do not  include stacking  charges [as  per Circular Memo No.230  Wks. IV  (2)  /  62-3, dt.10.06.62 of Chief Engineer (General)].
2 For conveyance of materials on cart track, allow  20% extra over the above rates excluding loading and unloading charges.
3 For sandy and slusly soil tracks, add 50% extra over the above rates excluding loading and unloading charges.
4 The quantity for payment towards conveyance of earth in Column (5)  is for the pit  measured quantity  at the site of excavation only.
5 For conveyance  of laterite, broken stone jelly, etc., through lorries, the rates provided are for the volume with voids.
6 For  all  materials  which  finds  place  in  Column,  3,4,5,6,7  and  8  above,  necessary  incidental  charges,  loading  charges  and  unloading  charges  have been included already under their basic cost furnished  below the head "Rates of Materials" itself.  Hence, no separate incidental charges, loading and unloading charges shall be allowed for the above materials.
7 The Basic Rate adopted under this Head, "Annexure-V  — (A). Rates of Conveyance of Materials by Road in Plains" is exclusive of all taxes and GST.

ANNEXURE-V
CONVEYANCE TABLE
{B}. RATES FOR CONVEYANCE  OF MATERIALS BY ROAD IN  HILLS

SI.
No.
Distance in
kilometre
Basic Rate approved for the year 2020-2021 (w.e.f. 20.04.2020)
Cement,
Seel
{1   MT)
Lime Stone, Laterite, Brick 3eIIy, Wood Work, Pond Ash {Wet / Dry}, Stone Dust
{One cubic metre)
Rough Stone, Bond Stone, Cut Stone, Broken Stone 3elly, Sand, Gravel, Surki, Earth, Crushed Stone Sand
(One cubic metre)
Third Class Country Bricks {Kiln Burnt)
{1000 Nos.)
Mangalore Tiles
{1000 Nos.),
Machine Pressed Tiles (2000 Nos.},
Hydraulically Pressed Mosaic Flooring Tiles
(1500 Nos.}
Bricks II  Class Chamber Burnt Bricks
(Table Moulded / Ground Moulded), Fly Ash Bricks
{1000 Nos.)
1 2 3 4 5 6 7 8
  Co-efficient 1.00 1.10 1.so 1.as 1.so z.as
  Add for every ext ra 1 Km and part thereof...      
a 0 - 10 Km. 13.02 14.28 20.80 17.56 23.40 29.24
b 10 - 20 Km. 11. 14 12.24 17.80 15.02 20.04 25.04
C 20 - 40 Km. 9.58 10.54 15.34 12.90 17.24 21.54
d 40 - 80 Km. 8.26 9.10 14.38 11.14 14.84 18.60
e Above 80 Km. 7.54 8.30 12.06 10.18 13.56 16.96
Note  
1 The above rates do not include stacking  charges  [as per Circular Memo No.  230 Wks. IV (2} /  62-3, dated  10.06.1962  of Chief Engineer
(General)].
2 For conveyance  of materials on cart track, allow  20% extra over the  above rates excluding  loading and unloading charges.
3 For sandy and slusly soil tracks, add 50% extra over the above rates excluding  loading and unloading charges.
4 The quantity for payment towards conveyance of earth in Column (5) is for the pit measured quantity at the site of excavation only.
5 For conveyance  of laterite, broken stone jelly, etc., through lorries, the rates provided are for the volume with voids.
6 For all materials which finds place in Column, 3,4,5,6,7  and 8 above, necessary incidental charges, loading charges and unloading charges have  been  included  already  under  their  basic  cost  furnished  below  the  head  "Rates  of  Materials"  itself.   Hence,  no  separate  incidental charges, loading and unloading charges shall be allowed for the above materials.
7 The Basic Rate adopted under this Head, "Annexure-V  — (B). Rates of Conveyance  of I'dateriaIs by Road in Hills" is exclusive of all taxes
and GST.

*****