Abstract of Leads & Lifts



Abstract
LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS
FOR THE YEAR: 2019-20


COM-LDLFT:                     

1. For total lead upto 150 m (including initial lead) lead charges by head load only shall be adopted irrespective of mode of conveyance.
2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of mode of conveyance.
3. The rates for loading at quarry including idle hire charges of trucks and hire charges  per for  each kilometer  and upto 5 km  are cumulative and inclusive of total charges for preceding lead.
4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones are for loose volume and not for compacted or in-situ volume.
5. The rates for lift charges,lead charges hire cahrges are cumulative are cumulative and inclusive of  rates  for preceding lift,load and  hire charges
6. Lift charges are not payable where conveyance of materials is by mechanical means to final placing point.

7. Loading and unloading charges are not payable for conveyance by head load.
8. Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 50 m wherever specified.
9. Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 1 km wherever specified.
10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone are inclusive of stacking.
11. Hire charges are per 1KM  for tippers and trucks for tranport of materials from work site to dump  yard and other places are cumulative& includes previous km upto 5 kms
12. The lead & lift charges are exclusive of  contractor's profit and overhead charges of 13.615%
13. The loading & unloading charges are exclusive of  contractor's profit and overhead charges of 13.615%
14. During the BoCE meeting held on 24-05-2014, it is observed that in some of the estimates, Lead Charges are being added directly to the material basic rates for arriving the finished item rate. In view of that, the BoCE has instructed to see that while arriving the finished item rate, the lead charges are to be added to the material basic rates only after  deducting the provision of "Contractor's Profit and Overhead charges"
15. During the BoCE meeting held on  10.06.2015,the BoCEs has recommended to withdraw lead charges,loading
and unloading charges for Cement as per the minutes of meeting of Sub-Committee held on 29.06.2015.(The conveyance charges , loading & unloading charges for cement are displayed for information purpose only).

COM-LDLFT-1 A. (Lead) Conveyance Charges for materials by head load
FOR THE YEAR: 2019-20

Sl No. Total distance
( Total lead includes
initial lead )
Earth / Sand
/Gravel /
Murrum/ Lime/
Surki/ Size stone
/ Cut stone
Rubble / Coarse
aggregate
Rs/Cum
Cement/
Reinforce-ment
steel Str steel
Rs / tonne
PCC slab/
Shahbad
slab / CC
block/ BS
slab/ Laterite
/ Wood
Rs / cum
1 2 3 4 5
1 Total lead upto 50 m
(covered by item rate)
Initial lead Initial lead Initial lead
2 Total lead upto 100 m 60.00 35.00 76.40
3 Total lead upto 150 m 120.00 70.00 152.70

Notes: 1. No loading or unloading charges are admissible for conveyance by head load.
            2. For total lead exceeding 150 m conveyance charges by mechanical means only shall be adopted irrespective of mode of                        conveyance.

COM-LDLFT-2   B.( Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks excluding loading, unloading and idle hire charges of machinery
( No loading and unloading charges allowed for machinery loading and unloading )

Sl No. Distance (Lead) charges for trucks and tippers  for Earth
/ Sand /Gravel / Murrum/ Lime/ Surki/ per cu.meter
(Lead) charges for trucks and tippers for Rubble/Size stones/ Cut Stones/ Coarse aggregate per cu.meter (Lead) charges for trucks and tippers  for Cement/ Steel/ RCC poles/ AC & GI sheets/ Packed materials/tonn e (Lead) charges for trucks and tippers per cu.meter  for PCC slabs/ Shahabad slabs/ CC & Laterite blocks/ Wood/ cum (Lead) charges for trucks and tippers per cu.meter  for water/ 1000 litres (Lead) charges for trucks per 1000
Nos. of Bricks
1 2 3 4 5 6 7 8
1 Lead  upto 1 km 28.30 27.40 17.10 40.40 17.60 45.70
2 Lead  upto 2 km 39.50 38.40 24.00 56.50 24.60 64.00
3 Lead upto  3 km 52.70 52.70 33.00 77.50 32.80 85.40
4 Lead  upto 4 km 64.00 64.00 40.00 94.20 39.80 103.60
5 Lead  upto 5 km 75.30 75.30 47.10 110.80 46.90 121.90
6 for Every km beyond 5 km upto 30 km 11.30 11.30 7.10 16.60 7.00 18.30
7 for Every km beyond 30 km 9.40 9.40 5.90 13.90 5.90 15.20

COM-LDLFT-3   C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)

Sl No. Description of item Earth / Sand
/Gravel Murrum/ / Surki/
Rs / cum
Rubble/ size stone/ cut stone/ Coarse aggregate, Lime in Rs/cum Cement in Rs/tonne Steel  in Rs./tonne Brick work     Rs/ 1000 No
1 2 3 4 5 6 7
1 Loading 19.80 39.90 65.80 78.80 54.80
2 Unloading 9.90 19.95 65.80 78.80 54.80

COM-LDLFT-4   D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )

Sl No. Description of item Earth / Sand
/Gravel Murrum/ / Surki/
Rs / cum
Rubble/ size stone/ cut stone/ Coarse aggregate,Lime in Rs/cum Cement in Rs/tonne Steel  in Rs./tonne Brick work     Rs/ 1000 No
1 2 3 4 5 6 7
1 Loading 103.10 123.00 157.20 170.30 205.70
2 Unloading 37.60 61.50 157.20 170.30 205.70

COM-LDLFT-5   E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)

Sl No. Description of item Earth / Sand
/Gravel Murrum/ / Surki/
Rs / cum
Rubble/ size stone/ cut stone/ Coarse aggregate, Lime in Rs/cum
1 2 3 4
1 Loading 45.60 90.80
2 Unloading 14.30 14.30

COM-LDLFT-6 F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

Sl No. Total lift
( Total lift includes
initial lift )
Earth / Sand
/Gravel
Murrum/ Lime/
Surki/
Size stone / Cut
stone
Rubble / Coarse
aggregate
Rs / cum
Cement/
Reinforcement
steel
Str steel
Rs / tonne
PCC slab/
Shahbad
slab / CC
block/ BS
slab / Laterite
/ Wood
Rs / cum
1 2 3 4 5
1 Total lift upto 3 m
(covered by item rate)
Initial lift Initial lift Initial lift
2 For Every 1.00 Lift
beyond initial lift of 3
meters
7.00 5.10 9.30

* * *