CONVEYANCE CHARGES



ABSTRACT

LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS FOR THE YEAR: 2019-20

For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be adopted irrespective of mode of conveyance.

For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of mode of conveyance.

The rates for loading at quarry including idle hire charges of trucks and hire charges per for each kilometer and upto 5 km are cumulative and inclusive of total charges for preceding lead.

Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones are for loose volume and not for compacted or in-situ volume.

The rates for lift charges,lead charges hire cahrges are cumulative are cumulative and inclusive of rates for preceding lift,load and hire charges

Lift charges are not payable where conveyance of materials is by mechanical means to final placing point.

Loading and unloading charges are not payable for conveyance by head load.

Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 50 m wherever specified.

Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 1 km wherever specified.

The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone are inclusive of stacking.

Hire charges are per 1KM for tippers and trucks for tranport of materials from work site to dump yard and other places are cumulative& includes previous km upto 5 kms

The lead & lift charges are inclusive of contractor's profit and overhead charges of 13.615%

During the BoCE meeting held on 26-05-2016, it is observed that in some of the estimates, Lead Charges are being added directly to the material basic rates for arriving the finished item rate. In view of that, the BoCE has instructed to see that while arriving the finished item rate, the lead charges are to be added to the material basic rates only after deducting the provision of Contractor's Profit and Overheadcharges

A. (Lead) Conveyance Charges for materials by head load

FOR THE YEAR: 2019-20

 

 

Sl No.

 

Total distance

( Total lead includes initial lead )

 

Earth/Sand/Gravel/ Murrum/Lime/Surki/Size stone / Cut stone Rubble / Coarse aggregate        Rs/Cum

 

Cement / Reinforce- ment steel Str steel Rs / tonne

 

PCC slab/ Shahbad slab / CC block/ BS slab/ Late-rite / Wood

Rs / cum

1

2

3

4

5

 

1

Total lead upto 50 m (covered by item rate)

 

initial lead

 

initial lead

 

initial lead

2

Total lead upto 100 m

72.2

42.1

91.9

3

Total lead upto 150 m

144.5

84.3

183.8

 

Notes:

No loading or unloading charges are admissible for conveyance by headload.

For total lead exceeding 150 m conveyance charges by mechanical means only shall be adopted irrespective of mode ofconveyance.

The Lead & Lift Charges are inclusive of 13.615% Contractor's Profit and Over HeadCharges

by tippers and trucks excluding loading, unloading and idle hire charges of

( No loading and unloading charges allowed for machinery loading and unloading )

 

 

 

 

 

 

Sl No.

 

 

 

 

 

 

Distance

 

 

(Lead) chargesfor trucks and tippers for Earth / Sand

/Gravel / Murrum/ Lime/ Surki/ per cu.meter

 

(Lead) chargesfor trucks and tippersfor Rubble/Si ze stones/ Cut Stones/ Coarse aggregate per cu.meter

 

(Lead) chargesfor trucks and tippers for Cement/ Steel/ RCC poles/ AC & GI sheets/ Packed materials/t onne

 

(Lead) charges for trucks and tippers per cu.meter for PCC slabs/ Shahabad slabs/ CC & Laterite blocks/ Wood/ cum

 

 

 

(Lead) charges for trucks and tippers per cu.meter for water/ 1000 litres

 

 

 

(Lead) charges for trucks per 1000 Nos. of Bricks

1

2

3

4

5

6

7

8

1

Lead upto 1 km

34.70

33.60

21.00

49.50

20.80

56.10

2

Lead upto 2 km

48.60

47.10

29.40

69.30

29.10

78.50

3

Lead upto 3 km

64.80

64.80

40.50

95.30

38.80

104.70

4

Lead upto 4 km

78.70

78.70

49.20

115.70

47.20

127.10

5

Lead upto 5 km

92.50

92.50

57.80

136.10

55.50

149.50

6

For Every km beyond

5 km upto 30 km

13.90

13.90

8.70

20.40

8.30

22.40

7

For Every km beyond

30 km

11.60

11.60

7.20

17.00

6.90

18.70

Note:The Lead & Lift Charges are inclusive of 13.615% Contractor's Profit and Over Head Charges

COM-LDLFT- C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle  hire  charges  of  trucks are not added)

 

 

Sl No.

 

 

 

Description of item

Earth / Sand

/Gravel Murrum// Surki/

 

Rs / cum

Rubble/ size stone/ cut stone/ Coarse aggregate, Lime in Rs/cum

 

 

cement in Rs/tonne

 

 

steel in Rs./tonne

 

 

brick work Rs/1000

No

1

2

3

4

5

6

7

1

Loading

125.90

149.80

191.20

206.90

250.90

2

Unloading

45.80

74.90

191.20

206.90

250.90

Note:The Loading & Unloading Charges are inclusive of 13.615% Contractor's Profit and Over Head Charges

COM-LDLFT- E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire

charges of trucks)

Sl

No.

Description of item

Earth / Sand /Gravel

Murrum/ / Surki/

Rubble/ size stone/ cut

stone/ Coarse

1

2

3

4

1

Loading

56.00

111.70

2

Unloading

17.50

17.50

Note:The Loading & Unloading Charges are inclusive of 13.615% Contractor's Profit and Over Head Charges

COM-LDLFT- F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

 

 

Sl No.

 

 

Total lift

( Total lift includes initial lift )

 

Earth / Sand /Gravel Murrum/Lime/Surki/ Size stone / Cut stone Rubble / Coarse aggregate

Rs / cum

 

Cement / Reinforce- ment steel Str steel Rs / tonne

PCC slab/ Shahbad slab / CC block/ BS slab /Laterite

/ Wood Rs / cum

1

2

3

4

5

 

1

Total lift upto 3 m (covered by item rate)

 

Initial lift

 

Initial lift

 

Initial lift

 

2

For Every 1.00 Lift beyond initial lift of 3

meters

 

8.40

 

6.10

 

11.20

Note:The Lead & Lift Charges are inclusive of 13.615% Contractor's Profit and Over Head Charges

*****