CONVEYANCE IN PLAINS & HILLS



ANNEXURE - V
CONVEYANCE TABLE (PWD : SoR 2019-20)
(A). RATES FOR CONVEYANCE OF MATERIALS BY ROAD IN PLAINS

 

 

SI. No.

Distance in kilometre Basic Rate approved for the year 2019-2020 (w.e.f. 17.06.2019)
Cement, Steel
(1 MT)
Lime Stone, Laterite, Brick Jelly, Wood Work, Pond Ash (Wet / Dry), Stone Dust (One cubic metre) Rough Stone, Bond Broken Stone Jelly, Sand, Gravel, Surki, Earth, Crushed Stone Sand (One cubic metre) Stone, Cut Stone, , Third Class Country Bricks (Kiln Burnt) (1000 Nos.) Mangalore Tiles (1000 Nos) Machine Pressed Tiles (2000 Nos.), Hydraulically Pressed Mosaic Flooring Tiles (1500 Nos.) Bricks II Class Chamber Burnt Bricks (Table Moulded / Ground Moulded),Fly Ash Bricks (1000 Nos.)
1 2 3 4 5 6 7 8
1 Co-efficient 1 1.1 1.6 1.35 1.8 2.25
2 Add for every extra 1 Km and part thereof ………………….
a 0 - 10 Km. 6.38 7 10.2 8.61 11.47 14.33
b 10 - 20 Km. 5.46 6 8.72 7.37 9.83 12.27
c 20 - 40 Km. 4.7 5.16 7.52 6.33 8.45 10.56
d 40 - 80 Km. 4.05 4.46 7.05 5.46 7.27 9.12
e Above 80 Km. 3.7 4.07 5.91 4.99 6.65 8.31
4 Loading Charges 101.2 48.29 33.11 47.52 47.52 47.52
5 Unloading Charges 101.2 48.29 33.11 47.52 47.52 47.52
6 Add above extra for inter state works 20.4 22.4 32.7 27.5 36.7 46.1
Note:
1 The above rates do not include stacking charges [as per Circular Memo No.230 Wks. IV (2) / 62-3, dt.10.06.62 of Chief Engineer (General)].
2 For conveyance of materials on cart track, allow 20% extra over the above rates excluding loading and unloading charges.
3 For sandy and slusly soil tracks, add 50% extra over the above rates excluding loading and unloading charges.
4 The quantity for payment towards conveyance of earth in Column (5) is for the pit measured quantity at the site of excavation only.
5 For conveyance of laterite, broken stone jelly, etc., through lorries, the rates provided are for the volume with voids.
6 For all materials which finds place in Column, 3,4,5,6,7 and 8 above, necessary incidental charges, loading charges and unloading charges have been included already under their basic cost furnished below the head "Rates of Materials" itself. Hence, no separate incidental charges, loading and unloading charges shall be allowed for the above materials.
7 The Basic Rate adopted under this Head, "Annexure-V - (A). Rates of Conveyance of Materials by Road in Plains" is exclusive of all taxes and GST.
ANNEXURE - V
CONVEYANCE TABLE (PWD : SoR 2019-20)
(B). RATES FOR CONVEYANCE OF MATERIALS BY ROAD IN HILLS
1 Co-efficient 1 1.1 1.6 1.35 1.8 2.25
2 Add for every extra 1 Km and part thereof
a 0 - 10 Km. 12.76 13.99 20.39 17.21 22.94 28.66
b 10 - 20 Km. 10.92 12 17.45 14.73 19.65 24.55
c 20 - 40 Km. 9.39 10.32 15.03 12.66 16.9 21.12
d 40 - 80 Km. 8.1 8.93 14.1 10.92 14.54 18.23
e Above 80 Km. 7.4 8.14 11.83 9.99 13.29 16.62
Note:
1 The above rates do not include stacking charges [as per Circular Memo No. 230 Wks. IV (2) / 62-3, dated 10.06.1962 of Chief Engineer (General)].
2 For conveyance of materials on cart track, allow 20% extra over the above rates excluding loading and unloading charges.
3 For sandy and slusly soil tracks, add 50% extra over the above rates excluding loading and unloading charges.
4 The quantity for payment towards conveyance of earth in Column (5) is for the pit measured quantity at the site of excavation only.
5 For conveyance of laterite, broken stone jelly, etc., through lorries, the rates provided are for the volume with voids.
6 For all materials which finds place in Column, 3,4,5,6,7 and 8 above, necessary incidental charges, loading charges and unloading charges have been included already under their basic cost furnished below the head "Rates of Materials" itself. Hence, no separate incidental charges, loading and unloading charges shall be allowed for the above materials.
7 The Basic Rate adopted under this Head, "Annexure-V - (B). Rates of Conveyance of Materials by Road in Hills" is exclusive of all taxes and GST.

 * * *