DISMANTLING (ANALYSIS OF RATES 2006) | ||||||
Sl. No | Description | Quantity Required |
Unit | Rate Rs. P |
Amount Rs. P |
Remarks |
(1) | (2) | (3) | (4) | (5) | (6) | (7) |
1 | Dismantling brick or stone masonry in clay under 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum Data for 2.83 cum | |||||
a) | Labour | |||||
Man Mulia | 1.25 Nos | Each | 55.00 | 68.75 | ||
Woman Mulia | 3.50 Nos | Each | 55.00 | 192.5 | ||
b) | Overhead Charges @ 10% on (a) | 26.13 | ||||
c) | 2% Sundries T & P etc. on (a) | 5.23 | ||||
Total (a+b+c) | 292.61 | |||||
Rate per 1 cum = | 292.61 | = 103.39/cum | ||||
2.83 | ||||||
Say Rs.= 103.40/cum | ||||||
2 | Dismantling brick or stone masonry in clay above 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum Data for 2.83 cum | |||||
a) | Labour | |||||
Man Mulia | 1.50 Nos | Each | 55.00 | 82.50 | ||
Woman Mulia | 3.50 Nos | Each | 55.00 | 192.50 | ||
b) | Overhead Charges @ 10% on (a) | 27.50 | ||||
c) | 2% Sundries T & P etc. on (a) | 5.50 | ||||
Total (a+b+c) | 308.00 | |||||
Rate per 1 cum = | 308.00 | = 108.83/cum | ||||
2.83 | ||||||
Say Rs.= 108.83/cum | ||||||
3 | Dismantling brick or stone masonry in lime or cement mortar under 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum Data for 2.83 cum | |||||
a) | Labour | |||||
Man Mulia | 4.00 Nos | Each | 55.00 | 220.00 | ||
Woman Mulia | 4.50 Nos | Each | 55.00 | 247.50 | ||
b) | Overhead Charges @ 10% on (a) | 46.75 | ||||
c) | 2% Sundries T & P etc. on (a) | 9.35 | ||||
Total (a+b+c) | 523.60 | |||||
Rate per 1 cum = | 523.60 | = 185.02/cum | ||||
2.83 | ||||||
Say Rs.= 185.00/cum | ||||||
4 | Dismantling brick or stone masonry in lime or cement mortar above 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum Data for 2.83 cum | |||||
a) | Labour | |||||
Man Mulia | 4.50 Nos | Each | 55.00 | 247.50 | ||
Woman Mulia | 4.50 Nos | Each | 55.00 | 247.50 | ||
b) | Overhead Charges @ 10% on (a) | 49.50 | ||||
c) | 2% Sundries T & P etc. on (a) | 9.90 | ||||
Total (a+b+c) | 554.40 | |||||
Rate per 1 cum = | 554.40 | = 195.90/cum | ||||
2.83 | ||||||
Say Rs.= 195.90/cum | ||||||
5 | Removing thatched roof including tying of useful thatches to small bundles and stacking them carefully for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 Sqm | |||||
a) | Labour | |||||
Man Mulia | 0.50 Nos | Each | 55.00 | 27.50 | ||
Woman Mulia | 1.75 Nos | Each | 55.00 | 96.25 | ||
b) | Overhead Charges @ 10% on (a) | 12.38 | ||||
c) | 2% Sundries T & P etc. on (a) | 2.48 | ||||
Total (a+b+c) | 138.61 | |||||
Rate per 1 sqm = | 138.61 | = 14.90/sqm | ||||
9.30 | ||||||
Say Rs.= 14.90/sqm | ||||||
6 | Dismantling roof timbers of thatched roof including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 Sqm | |||||
a) | Labour | |||||
Man Mulia | 0.30 Nos | Each | 55.00 | 16.50 | ||
Woman Mulia | 0.25 Nos | Each | 55.00 | 13.75 | ||
b) | Overhead Charges @ 10% on (a) | 3.03 | ||||
c) | 2% Sundries T & P etc. on (a) | 0.61 | ||||
Total (a+b+c) | 33.89 | |||||
Rate per 1 sqm= | 33.89 | = 3.64/sqm | ||||
9.30 | ||||||
Say Rs.= 3.60/sqm | ||||||
7 | Dismantling pan or single Nuria or Mangalore tileroofing (Tiles only) including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.00 Nos | Each | 55.00 | 55.00 | ||
Woman Mulia | 1.75 Nos | Each | 55.00 | 96.25 | ||
b) | Overhead Charges @ 10% on (a) | 15.13 | ||||
c) | 2% Sundries T & P etc. on (a) | 3.03 | ||||
Total (a+b+c) | 169.41 | |||||
Rate per 1 sqm = | 169.41 | = 18.22/sqm | ||||
9.30 | ||||||
Say Rs.= 18.20/sqm | ||||||
8 | Dismantling double Nuria tileroofing (Tiles only) including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.25 Nos | Each | 55.00 | 68.75 | ||
Woman Mulia | 3.00 Nos | Each | 55.00 | 165.00 | ||
b) | Overhead Charges @ 10% on (a) | 23.38 | ||||
c) | 2% Sundries T & P etc. on (a) | 4.68 | ||||
Total (a+b+c) | 261.81 | |||||
Rate per 1 sqm = | 261.81 | = 28.15/sqm | ||||
9.30 | ||||||
Say Rs.= 28.20/sqm | ||||||
9 | Dismantling flat & pan tiled roofing (Tiles only) including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.25 Nos | Each | 55.00 | 68.75 | ||
Woman Mulia | 4.00 Nos | Each | 55.00 | 220.00 | ||
b) | Overhead Charges @ 10% on (a) | 28.88 | ||||
c) | 2% Sundries T & P etc. on (a) | 5.78 | ||||
Total (a+b+c) | 323.41 | |||||
Rate per 1 sqm = | 323.41 | = 34.77/sqm | ||||
9.30 | ||||||
Say Rs.= 34.80/sqm | ||||||
10 | Dismantling reepers under tiled roof (pan, flat or nuria tiles) after careful removal of nails including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Carenter(2nd Class) | 0.33 No | Each | 75.00 | 24.75 | ||
Man Mulia | 1.25 Nos | Each | 55.00 | 68.75 | ||
b) | Overhead Charges @ 10% on (a) | 9.35 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.87 | ||||
Total (a+b+c) | 104.72 | |||||
Rate per 1 sqm = | 104.72 | = 11.26/sqm | ||||
9.30 | ||||||
Say Rs.= 11.30/sqm | ||||||
11 | Dismantling and removing lime concrete flooring 7.5 cm to 10 cm thick including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Carenter(2nd Class) | ||||||
Man Mulia | 0.75 No | Each | 55.00 | 41.25 | ||
Woman Mulia | 2.00 Nos | Each | 55.00 | 110.00 | ||
b) | Overhead Charges @ 10% on (a) | 15.13 | ||||
c) | 2% Sundries T & P etc. on (a) | 3.03 | ||||
Total (a+b+c) | 169.41 | |||||
Rate per 1 sqm = | 169.41 | = 18.22/sqm | ||||
9.30 | ||||||
Say Rs.= 18.20/sqm | ||||||
12 | Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 0.75 No | Each | 55.00 | 41.25 | ||
Woman Mulia | 1.25 Nos | Each | 55.00 | 68.75 | ||
b) | Overhead Charges @ 10% on (a) | 11.00 | ||||
c) | 2% Sundries T & P etc. on (a) | 2.20 | ||||
Total (a+b+c) | 123.20 | |||||
Rate per 1 sqm = | 123.20 | = 13.25/sqm | ||||
9.30 | ||||||
Say Rs.= 13.20/sqm | ||||||
13 | Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.00 No | Each | 55.00 | 55.00 | ||
b) | Overhead Charges @ 10% on (a) | 5.50 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.10 | ||||
Total (a+b+c) | 61.60 | |||||
Rate per 1 sqm = | 61.60 | = 6.62/sqm | ||||
9.30 | ||||||
Say Rs.= 6.60/sqm | ||||||
14 | Dismantling flag stone flooring including stacking the useful stones for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 0.50 Nos | Each | 55.00 | 27.50 | ||
Woman Mulia | 1.00 No | Each | 55.00 | 55.00 | ||
b) | Overhead Charges @ 10% on (a) | 8.25 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.65 | ||||
Total (a+b+c) | 92.40 | |||||
Rate per 1 sqm = | 92.40 | = 9.94/sqm | ||||
9.30 | ||||||
Say Rs.=9.90/sqm | ||||||
15 | Dismantling terraced roof (Madras or Orissa) including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 2.35 Nos | Each | 55.00 | 129.25 | ||
Woman Mulia | 4.00 Nos | Each | 55.00 | 220.00 | ||
b) | Overhead Charges @ 10% on (a) | 34.93 | ||||
c) | 2% Sundries T & P etc. on (a) | 6.99 | ||||
Total (a+b+c) | 391.17 | |||||
Rate per 1 sqm = | 391.17 | = 42.06/sqm | ||||
9.30 | ||||||
Say Rs.=42.10/sqm | ||||||
16 | Dismantling G.C.I. or A.C. sheet roofing after carefully removing the bolts and nuts including stacking of he materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Fitter (2nd Class) | 0.25 Nos | Each | 75.00 | 18.75 | ||
Man Mulia | 0.50 Nos | Each | 55.00 | 27.50 | ||
Woman Mulia | 1.00 Nos | Each | 55.00 | 55.00 | ||
b) | Overhead Charges @ 10% on (a) | 10.13 | ||||
c) | 2% Sundries T & P etc. on (a) | 2.03 | ||||
Total (a+b+c) | 113.41 | |||||
Rate per 1 sqm = | 113.41 | = 12.19/sqm | ||||
9.30 | ||||||
Say Rs.=12.20/sqm | ||||||
17 | Dismantling wrought and framed timber in roof frame work of floors after careful removal of nail, bolts etc. and stacking of the materials for reuse and removing the debris within 50m lead per 1 cum Data for 0.0283 sqm | |||||
a) | Labour | |||||
Carpenter (2nd class) | 0.03 Nos | Each | 75.00 | 2.25 | ||
Man Mulia | 0.04 Nos | Each | 55.00 | 2.20 | ||
b) | Overhead Charges @ 10% on (a) | 0.45 | ||||
c) | 2% Sundries T & P etc. on (a) | 0.09 | ||||
Total (a+b+c) | 4.99 | |||||
Rate per 1 sqm = | 4.99 | = 176.33/sqm | ||||
0.0283 | ||||||
Say Rs.=176.30/sqm | ||||||
18 | Dismantling and removing doors, windows and ventilators including removal of frame, hinges, fastening and stacking the same for reuse and removing the debris within 50m lead per 1 sqm Consider a door of (1.22 M×2.13 M=2.60sqm) | |||||
a) | Labour | |||||
Carpenter (2nd class) | 0.50 Nos | Each | 75.00 | 37.50 | ||
Man Mulia | 0.60 Nos | Each | 55.00 | 33.00 | ||
Woman Mulia | 1.00 No | Each | 55.00 | 55.00 | ||
b) | Overhead Charges @ 10% on (a) | 12.55 | ||||
c) | 2% Sundries T & P etc. on (a) | 2.51 | ||||
Total (a+b+c) | 140.56 | |||||
Rate per 1 sqm = | 140.56 | = 54.06/sqm | ||||
2.60 | ||||||
Say Rs.=54.10/sqm | ||||||
19 | Dismantling dry or grouted rough stone revetments of approns or retaining walls and stacking the stones for reuse and removing the debris within 50m lead per 1 cum Data for 2.83 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.00 Nos | Each | 55.00 | 55.00 | ||
Woman Mulia | 3.50 No | Each | 55.00 | 192.50 | ||
b) | Overhead Charges @ 10% on (a) | 24.75 | ||||
c) | 2% Sundries T & P etc. on (a) | 4.95 | ||||
Total (a+b+c) | 277.20 | |||||
Rate per 1 sqm = | 277.20 | = 97.95/sqm | ||||
2.83 | ||||||
Say Rs.=98.00/sqm | ||||||
20 | Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 0.75 Nos | Each | 55.00 | 41.25 | ||
Woman Mulia | 1.25 Nos | Each | 55.00 | 68.75 | ||
Woman Mulia for lifting the debries | 0.25 Nos | Each | 55.00 | 13.75 | ||
b) | Overhead Charges @ 10% on (a) | 12.38 | ||||
c) | 2% Sundries T & P etc. on (a) | 2.48 | ||||
Total (a+b+c) | 138.61 | |||||
Rate per 1 sqm = | 138.61 | = 14.90/sqm | ||||
9.30 | ||||||
Say Rs.=14.90/sqm | ||||||
21 | Removing old grading plaster from roof slab, cleaning the surface, lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.40 Nos | Each | 55.00 | 77.00 | ||
Woman Mulia | 0.15 Nos | Each | 55.00 | 8.25 | ||
b) | Overhead Charges @ 10% on (a) | 8.53 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.71 | ||||
Total (a+b+c) | 95.49 | |||||
Rate per 1 sqm = | 95.49 | = 10.27/sqm | ||||
9.30 | ||||||
Say Rs.=10.30/sqm | ||||||
22 | Removing old tarfelt from roof slab, cleaning the surface, lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.75 Nos | Each | 55.00 | 96.25 | ||
b) | Overhead Charges @ 10% on (a) | 9.63 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.93 | ||||
Total (a+b+c) | 107.81 | |||||
Rate per 1 sqm = | 107.81 | = 11.59/sqm | ||||
9.30 | ||||||
Say Rs.=11.60/sqm | ||||||
23 | Removing old tarfelt from roof slab, cleaning the surface, lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.50 Nos | Each | 55.00 | 82.50 | ||
Woman Mulia | 0.10 Nos | Each | 55.00 | 5.50 | ||
b) | Overhead Charges @ 10% on (a) | 8.80 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.76 | ||||
Total (a+b+c) | 98.56 | |||||
Say Rs.=98.60/sqm | ||||||
24 | Dismantling and removing R.C.C. columns beams slab staircase landing lintels including stacking the useful materials for reuse and removing the debris within 50m lead per 1 cum | |||||
a) | Labour | |||||
Semiskilled Mulia | 1.50 Nos | Each | 65.00 | 97.50 | ||
Man Mulia | 1.50 Nos | Each | 55.00 | 82.50 | ||
b) | Overhead Charges @ 10% on (a) | 18.00 | ||||
c) | 2% Sundries T & P etc. on (a) | 3.60 | ||||
Total (a+b+c) | 201.60 | |||||
Say Rs.=201.60/sqm | ||||||
25 | Dismantling and removing R.C.C. Chajja, Shelves, fins and parapet including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 3.50 Nos | Each | 55.00 | 192.50 | ||
b) | Overhead Charges @ 10% on (a) | 19.25 | ||||
c) | 2% Sundries T & P etc. on (a) | 3.85 | ||||
Total (a+b+c) | 215.60 | |||||
Rate per 1 sqm = | 215.60 | = 23.18/sqm | ||||
9.30 | ||||||
Say Rs.=23.20/sqm | ||||||
26 | Dismantling and removing marble chips flooring including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 0.85 Nos | Each | 55.00 | 46.75 | ||
Woman Mulia | 1.40 Nos | 1.40 Nos | 55.00 | 77.00 | ||
b) | Overhead Charges @ 10% on (a) | 12.38 | ||||
c) | 2% Sundries T & P etc. on (a) | 2.48 | ||||
Total (a+b+c) | 138.60 | |||||
Rate per 1 sqm = | 138.60 | = 14.90/sqm | ||||
9.30 | ||||||
Say Rs.=14.90/sqm | ||||||
27 | Dismantling and removing marbel chips dados & skirting from walls including rackingout joints 12mm. Deepstacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.10 Nos | Each | 55.00 | 60.50 | ||
b) | Overhead Charges @ 10% on (a) | 6.05 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.21 | ||||
Total (a+b+c) | 67.76 | |||||
Rate per 1 sqm = | 67.76 | = 7.29/sqm | ||||
9.30 | ||||||
Say Rs.=7.30/sqm | ||||||
28 | Dismantling and removing old tiled flooring including removing the base coarse and stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.00 Nos | Each | 55.00 | 55.00 | ||
Woman Mulia | 1.50 Nos | Each | 55.00 | 82.50 | ||
b) | Overhead Charges @ 10% on (a) | 13.75 | ||||
c) | 2% Sundries T & P etc. on (a) | 2.75 | ||||
Total (a+b+c) | 154.00 | |||||
Rate per 1 sqm = | 154.00 | = 16.56/sqm | ||||
9.30 | ||||||
Say Rs.=16.60/sqm | ||||||
29 | Dismantling and removing old tiled cladding from walls including racking out joints 12mm deep stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm | |||||
a) | Labour | |||||
Man Mulia | 1.30 Nos | Each | 55.00 | 71.50 | ||
b) | Overhead Charges @ 10% on (a) | 7.15 | ||||
c) | 2% Sundries T & P etc. on (a) | 1.43 | ||||
Total (a+b+c) | 80.08 | |||||
Rate per 1 sqm = | 80.08 | = 8.61/sqm | ||||
9.30 | ||||||
Say Rs.=8.60/sqm | ||||||
Note: | 1 For dismantling work in 1st floor or any additional floor add 5% extra labour over & above the rate of next lower floor for lowering the dismantled materials. 2 10% excess on the above rate will be allowed for the works being executed inside jail premises. |
*****