DISMANTLING



  DISMANTLING (ANALYSIS OF RATES 2006)
Sl. No Description Quantity
Required 
Unit Rate
Rs.      P
Amount
Rs.       P
Remarks
(1) (2) (3) (4) (5) (6) (7)
1 Dismantling brick or stone masonry in clay under 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum Data for 2.83 cum          
a) Labour          
  Man Mulia 1.25 Nos Each 55.00 68.75  
  Woman Mulia 3.50 Nos Each 55.00 192.5  
b) Overhead Charges @ 10% on (a)       26.13  
c) 2% Sundries T & P etc. on (a)       5.23  
  Total (a+b+c)       292.61  
  Rate per 1 cum = 292.61 = 103.39/cum    
    2.83        
      Say Rs.= 103.40/cum    
2 Dismantling brick or stone masonry in clay above 3m. height  including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum Data for 2.83 cum          
a) Labour          
  Man Mulia 1.50 Nos Each 55.00 82.50  
  Woman Mulia 3.50 Nos Each 55.00 192.50  
b) Overhead Charges @ 10% on (a)       27.50  
c) 2% Sundries T & P etc. on (a)       5.50  
  Total (a+b+c)       308.00  
  Rate per 1 cum = 308.00 = 108.83/cum    
    2.83        
      Say Rs.= 108.83/cum    
3 Dismantling brick or stone masonry in lime or cement mortar under 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead  per 1 cum Data for 2.83 cum          
a) Labour          
  Man Mulia 4.00 Nos Each 55.00 220.00  
  Woman Mulia 4.50 Nos Each 55.00 247.50  
b) Overhead Charges @ 10% on (a)       46.75  
c) 2% Sundries T & P etc. on (a)       9.35  
  Total (a+b+c)       523.60  
  Rate per 1 cum = 523.60 = 185.02/cum    
    2.83        
      Say Rs.= 185.00/cum    
4 Dismantling brick or stone masonry in lime or cement mortar above 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum Data for 2.83 cum          
a) Labour          
  Man Mulia 4.50 Nos Each 55.00 247.50  
  Woman Mulia 4.50 Nos Each 55.00 247.50  
b) Overhead Charges @ 10% on (a)       49.50  
c) 2% Sundries T & P etc. on (a)       9.90  
  Total (a+b+c)       554.40  
  Rate per 1 cum = 554.40 = 195.90/cum    
    2.83        
      Say Rs.= 195.90/cum    
5 Removing thatched roof including tying of useful thatches to small bundles and stacking them carefully for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 Sqm          
a) Labour          
  Man Mulia 0.50 Nos Each 55.00 27.50  
  Woman Mulia 1.75 Nos Each 55.00 96.25  
b) Overhead Charges @ 10% on (a)       12.38  
c) 2% Sundries T & P etc. on (a)       2.48  
  Total (a+b+c)       138.61  
  Rate per 1 sqm = 138.61 = 14.90/sqm    
    9.30        
      Say Rs.= 14.90/sqm    
6 Dismantling roof timbers of thatched roof including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm  Data for 9.30 Sqm          
a) Labour          
  Man Mulia 0.30 Nos Each 55.00 16.50  
  Woman Mulia 0.25 Nos Each 55.00 13.75  
b) Overhead Charges @ 10% on (a)       3.03  
c) 2% Sundries T & P etc. on (a)       0.61  
  Total (a+b+c)       33.89  
  Rate per 1 sqm= 33.89 = 3.64/sqm    
    9.30        
      Say Rs.= 3.60/sqm    
7 Dismantling pan or single Nuria or Mangalore tileroofing (Tiles only) including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm           
a) Labour          
  Man Mulia 1.00 Nos Each 55.00 55.00  
  Woman Mulia 1.75 Nos Each 55.00 96.25  
b) Overhead Charges @ 10% on (a)       15.13  
c) 2% Sundries T & P etc. on (a)       3.03  
  Total (a+b+c)       169.41  
  Rate per 1 sqm = 169.41 = 18.22/sqm    
    9.30        
      Say Rs.= 18.20/sqm    
8 Dismantling double Nuria tileroofing (Tiles only) including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 1.25 Nos Each 55.00 68.75  
  Woman Mulia 3.00 Nos Each 55.00 165.00  
b) Overhead Charges @ 10% on (a)       23.38  
c) 2% Sundries T & P etc. on (a)       4.68  
  Total (a+b+c)       261.81  
  Rate per 1 sqm = 261.81 = 28.15/sqm    
    9.30        
      Say Rs.= 28.20/sqm    
9 Dismantling flat & pan tiled roofing (Tiles only) including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 1.25 Nos Each 55.00 68.75  
  Woman Mulia 4.00 Nos Each 55.00 220.00  
b) Overhead Charges @ 10% on (a)       28.88  
c) 2% Sundries T & P etc. on (a)       5.78  
  Total (a+b+c)       323.41  
  Rate per 1 sqm = 323.41 = 34.77/sqm      
    9.30        
      Say Rs.= 34.80/sqm      
10 Dismantling reepers under tiled roof (pan, flat or nuria tiles) after careful removal of nails including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Carenter(2nd Class) 0.33 No Each 75.00 24.75  
  Man Mulia 1.25 Nos Each 55.00 68.75  
b) Overhead Charges @ 10% on (a)       9.35  
c) 2% Sundries T & P etc. on (a)       1.87  
  Total (a+b+c)       104.72  
  Rate per 1 sqm = 104.72 = 11.26/sqm      
    9.30        
      Say Rs.= 11.30/sqm      
11 Dismantling and removing lime concrete flooring 7.5 cm to 10 cm thick including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Carenter(2nd Class)          
  Man Mulia 0.75 No Each 55.00 41.25  
  Woman Mulia 2.00 Nos Each 55.00 110.00  
b) Overhead Charges @ 10% on (a)       15.13  
c) 2% Sundries T & P etc. on (a)       3.03  
  Total (a+b+c)       169.41  
  Rate per 1 sqm = 169.41 = 18.22/sqm      
    9.30        
      Say Rs.= 18.20/sqm      
12 Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 0.75 No Each 55.00 41.25  
  Woman Mulia 1.25 Nos Each 55.00 68.75  
b) Overhead Charges @ 10% on (a)       11.00  
c) 2% Sundries T & P etc. on (a)       2.20  
  Total (a+b+c)       123.20  
  Rate per 1 sqm = 123.20 = 13.25/sqm      
    9.30        
      Say Rs.= 13.20/sqm      
13 Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 1.00 No Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       5.50  
c) 2% Sundries T & P etc. on (a)       1.10  
  Total (a+b+c)       61.60  
  Rate per 1 sqm = 61.60 = 6.62/sqm      
    9.30        
      Say Rs.= 6.60/sqm      
14 Dismantling flag stone flooring including stacking the useful stones for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 0.50 Nos Each 55.00 27.50  
  Woman Mulia 1.00 No Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       8.25  
c) 2% Sundries T & P etc. on (a)       1.65  
  Total (a+b+c)       92.40  
  Rate per 1 sqm = 92.40 = 9.94/sqm      
    9.30        
      Say Rs.=9.90/sqm      
15 Dismantling terraced roof (Madras or Orissa) including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm  Data for 9.30 sqm          
a) Labour          
  Man Mulia 2.35 Nos Each 55.00 129.25  
  Woman Mulia 4.00 Nos Each 55.00 220.00  
b) Overhead Charges @ 10% on (a)       34.93  
c) 2% Sundries T & P etc. on (a)       6.99  
  Total (a+b+c)       391.17  
  Rate per 1 sqm = 391.17 = 42.06/sqm      
    9.30        
      Say Rs.=42.10/sqm      
16 Dismantling G.C.I. or A.C. sheet roofing after carefully removing the bolts and nuts including stacking of he materials for reuse and removing the debris within 50m lead  per 1 sqm Data for 9.30 sqm          
a) Labour          
  Fitter (2nd Class) 0.25 Nos Each 75.00 18.75  
  Man Mulia 0.50 Nos Each 55.00 27.50  
  Woman Mulia 1.00 Nos Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       10.13  
c) 2% Sundries T & P etc. on (a)       2.03  
  Total (a+b+c)       113.41  
  Rate per 1 sqm = 113.41 = 12.19/sqm      
    9.30        
      Say Rs.=12.20/sqm      
17 Dismantling wrought and framed timber in roof frame work of floors after careful removal of nail, bolts etc. and stacking of the materials for reuse and removing the debris within 50m lead per 1 cum Data for 0.0283 sqm          
a) Labour          
  Carpenter (2nd class) 0.03 Nos Each 75.00 2.25  
  Man Mulia 0.04 Nos Each 55.00 2.20  
b) Overhead Charges @ 10% on (a)       0.45  
c) 2% Sundries T & P etc. on (a)       0.09  
  Total (a+b+c)       4.99  
  Rate per 1 sqm = 4.99 = 176.33/sqm      
    0.0283        
      Say Rs.=176.30/sqm      
18 Dismantling and removing doors, windows and ventilators  including removal of frame, hinges, fastening and stacking the same for reuse and removing the debris within 50m lead per 1 sqm Consider a door of (1.22 M×2.13 M=2.60sqm)          
a) Labour          
  Carpenter (2nd class) 0.50 Nos Each 75.00 37.50  
  Man Mulia 0.60 Nos Each 55.00 33.00  
  Woman Mulia 1.00 No Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       12.55  
c) 2% Sundries T & P etc. on (a)       2.51  
  Total (a+b+c)       140.56  
  Rate per 1 sqm = 140.56 = 54.06/sqm      
    2.60        
      Say Rs.=54.10/sqm      
19 Dismantling dry or grouted rough stone revetments of approns or retaining walls and stacking the stones for reuse and removing the debris within 50m lead per 1 cum Data for 2.83 sqm           
a) Labour          
  Man Mulia 1.00 Nos Each 55.00 55.00  
  Woman Mulia 3.50 No Each 55.00 192.50  
b) Overhead Charges @ 10% on (a)       24.75  
c) 2% Sundries T & P etc. on (a)       4.95  
  Total (a+b+c)       277.20  
  Rate per 1 sqm = 277.20 = 97.95/sqm      
    2.83        
      Say Rs.=98.00/sqm      
20 Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 0.75 Nos Each 55.00 41.25  
  Woman Mulia 1.25 Nos Each 55.00 68.75  
  Woman Mulia for lifting the debries 0.25 Nos Each 55.00 13.75  
b) Overhead Charges @ 10% on (a)       12.38  
c) 2% Sundries T & P etc. on (a)       2.48  
  Total (a+b+c)       138.61  
  Rate per 1 sqm = 138.61 = 14.90/sqm      
    9.30        
      Say Rs.=14.90/sqm      
21 Removing old grading plaster from roof slab, cleaning the surface, lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 1.40 Nos Each 55.00 77.00  
  Woman Mulia 0.15 Nos Each 55.00 8.25  
b) Overhead Charges @ 10% on (a)       8.53  
c) 2% Sundries T & P etc. on (a)       1.71  
  Total (a+b+c)       95.49  
  Rate per 1 sqm = 95.49 = 10.27/sqm      
    9.30        
      Say Rs.=10.30/sqm      
22 Removing old tarfelt from roof slab, cleaning the surface, lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm           
a) Labour          
  Man Mulia 1.75 Nos Each 55.00 96.25  
b) Overhead Charges @ 10% on (a)       9.63  
c) 2% Sundries T & P etc. on (a)       1.93  
  Total (a+b+c)       107.81  
  Rate per 1 sqm = 107.81 = 11.59/sqm      
    9.30        
      Say Rs.=11.60/sqm      
23 Removing old tarfelt from roof slab, cleaning the surface, lowering and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm            
a) Labour          
  Man Mulia 1.50 Nos Each 55.00 82.50  
  Woman Mulia 0.10 Nos Each 55.00 5.50  
b) Overhead Charges @ 10% on (a)       8.80  
c) 2% Sundries T & P etc. on (a)       1.76  
  Total (a+b+c)       98.56  
      Say Rs.=98.60/sqm      
24 Dismantling and removing R.C.C. columns beams slab staircase landing lintels including stacking the useful materials for reuse and removing the debris within 50m lead per 1 cum          
a) Labour          
  Semiskilled Mulia 1.50 Nos Each 65.00 97.50  
  Man Mulia 1.50 Nos Each 55.00 82.50  
b) Overhead Charges @ 10% on (a)       18.00  
c) 2% Sundries T & P etc. on (a)       3.60  
  Total (a+b+c)       201.60  
      Say Rs.=201.60/sqm      
25 Dismantling and removing R.C.C. Chajja, Shelves, fins and parapet including stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 3.50 Nos Each 55.00 192.50  
b) Overhead Charges @ 10% on (a)       19.25  
c) 2% Sundries T & P etc. on (a)       3.85  
  Total (a+b+c)       215.60  
  Rate per 1 sqm = 215.60 = 23.18/sqm      
    9.30        
      Say Rs.=23.20/sqm      
26 Dismantling and removing marble chips flooring including  stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 0.85 Nos Each 55.00 46.75  
  Woman Mulia 1.40 Nos 1.40 Nos 55.00 77.00  
b) Overhead Charges @ 10% on (a)       12.38  
c) 2% Sundries T & P etc. on (a)       2.48  
  Total (a+b+c)       138.60  
  Rate per 1 sqm = 138.60 = 14.90/sqm      
    9.30        
      Say Rs.=14.90/sqm      
27 Dismantling and removing marbel chips dados & skirting from walls including rackingout joints 12mm. Deepstacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 1.10 Nos Each 55.00 60.50  
b) Overhead Charges @ 10% on (a)       6.05  
c) 2% Sundries T & P etc. on (a)       1.21  
  Total (a+b+c)       67.76  
  Rate per 1 sqm = 67.76 = 7.29/sqm      
    9.30        
      Say Rs.=7.30/sqm      
28 Dismantling and removing old tiled flooring including removing the base coarse and stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 1.00 Nos Each 55.00 55.00  
  Woman Mulia 1.50 Nos Each 55.00 82.50  
b) Overhead Charges @ 10% on (a)       13.75  
c) 2% Sundries T & P etc. on (a)       2.75  
  Total (a+b+c)       154.00  
  Rate per 1 sqm = 154.00 = 16.56/sqm      
    9.30        
      Say Rs.=16.60/sqm      
29 Dismantling and removing old tiled cladding from walls including racking out joints 12mm deep stacking the useful materials for reuse and removing the debris within 50m lead per 1 sqm Data for 9.30 sqm          
a) Labour          
  Man Mulia 1.30 Nos Each 55.00 71.50  
b) Overhead Charges @ 10% on (a)       7.15  
c) 2% Sundries T & P etc. on (a)       1.43  
  Total (a+b+c)       80.08  
  Rate per 1 sqm = 80.08 = 8.61/sqm      
    9.30        
      Say Rs.=8.60/sqm      
Note: 1 For dismantling work in 1st floor or any additional floor add 5% extra labour over & above the rate of next lower floor for lowering the dismantled materials.
2 10% excess on the above rate will be allowed for the works being executed inside jail premises.
 

*****