FLOORING



FLOORING  (ANALYSIS OF RATES 2006)
Sl. No Description Qunatity Required Unit Rate
Rs.                       P
Amount
Rs.                       P
Remarks
(1) (2) (3) (4) (5) (6) (7)
1 10cm moorum flooring (Gravel) per 1 Sqm.          
a) Material          
  Gravel 0.15 cum cum 45.00 6.75  
b) Labour          
  Man mulia 0.11 Nos each 55.00 6.05  
  Women mulia 0.05 Nos each 55.00 2.75  
c) Overhead charges @ 10% on (a+b)       1.56  
  Total (a+b+c)       17.11  
          Say Rs. 17.10/Sqm  
2 2.5cm artificial stone flooring with cement concrete (1:2:4) including punning using 12 mm size hand broken granites chips          
a) Material          
  Hand broken granite Chips (12mm, screened) 0.023 cum 1 cum 494.00 11.36  
  sand (Screened and washed)          
  Cement ( 0.006 cum) 0.012 cum 1cum 29.00 0.35  
b) Labour 0.0858 Qntl 1qntl 341.00 29.26  
  Man mulia for mixingchips cement and sand in small quantity and watering 0.03 Nos Each 55.00 1.65  
  Mason special 0.13 Nos Each 85.00 11.05  
  Women mulia 0.22 Nos Each 55.00 12.10  
  Man mulia 0.11 Nos Each 55.00 6.05  
c) Overhead charges @ 10% on (a+b)       7.18  
  Total (a+b+c)       79.00  
          Say Rs. 79.00 / Sqm  
3 2.5cm thick artificial stone flooring (1:2:4) with
washed gravel including punning Per 1sqm
         
a) Rate as per item No.2       79.00  
b) Deduct-The difference of rate for hard granite chips
and washed gravel 543.0-93.50 =449.50 including OHC
-0.023 cum cum 449.50 -10.34  
  Total (a-b)       68.66  
          Say Rs. 68.70 / Sqm  
4 2.5cm artificial stone flooring with cement concrete (1:3:5) using 12mm size hand broken granite chips including punning per 1 Sqm.          
a) Material          
  Hand broken granite chips 0.023 cum 1cum 494.00 11.36  
  12mm size screened sand 0.0138 cum 1cum 29.00 0.40  
  (screened and washed ) 0.0658 Qntl 1qntl 341.00 22.44  
  cement 0.0046cum          
b) Labour          
  Labour as per item No.2       30.85  
c) Overhead charges @ 10% on (a+b)       6.51  
  Total (a+b+c)       71.56  
          Say Rs. 71.60 / Sqm  
5 2.5cm artificial stone flooring with cement concrete (1:3:6) using 12mm size hand broken granite chips including punning per 1 sqm          
a) Rate as per item No.2       79.00  
b) Deduct-Difference in quantity of cement due to less proportion (0.006 cum - 0.0038cum) 0.0022 cum or, 0.031 Qntl. incl. OHC -0.031 Qntl 1qntl 375.10 -11.60  
  Total (a-b)       67.40  
          Say Rs. 67.40 / Sqm  
6 2.5cm artificial stone flooring with cement concrete (1:3:6) with washed gravel including punning per 1 sqm          
a) Rate as per item No.3 including OHC       68.70  
b) Deduct-Difference in quantity of cement due to less proportion including OHC -0.031 Qntl 1qntl 375.10 -11.60  
  Total (a-b)       57.10  
          Say Rs. 57.10 / Sqm  
7 Flooring with 10cm. thick concrete broken stone, hard granite in lime mortar and renderd smooth with 9kgs of portland cement per 1 sqm          
a) Material          
  Concrete broken stone in lime mortar (1:2) as per item No.2 of concrete incl. OHC  0.10 cum 1cum 1006.50 100.65  
  cement 0.0072 Qntl 1qntl 341.00 2.46  
b) Labour          
  Manson, special 0.03 Nos each 85.00 2.55  
  Women mulia 0.08 Nos each 55.00 4.40  
c) Overhead charges @ 10% on (a+b)       0.94  
  Total (a+b+c)       111.00  
          Say Rs. 111.00 / Sqm  
8 Flooring with dry stone, jelly 10cm sand grouted and finished the top with 12mm thick cement plaster (1:3) including punning per 1 sqm          
a) Material          
  Hand broken metal other than Granite broken to 4cm size 0.10 cum 1cum 199.00 19.90  
  Gravel (washed) for grouting 0.03 cum 1cum 85.00 2.55  
b) Labour          
  Man mulia for ramming laying 0.11 Nos each 55.00 6.05  
  gravel or sand for grouting          
  women mulia for watering and ramming 0.22 Nos each 55.00 12.10  
  plastering with cement mortar   1sq   46.10  
  (1:3) 12mm, thick (As per item          
  No.3 of plastering including OHC )          
c) Overhead charges @ 10% on (a+b)       4.06  
  Total (a+b+c)       90.76  
          Say Rs. 90.80 / Sqm  
9 10cm thick dry brick khoa well watered & rammed to receive A.S.flooring Per 1 sqm.            
a) Material          
  K.B.brick khoa 4cm size 0.14 cum 1cum 239.00 33.46  
b) Labour          
  Mason 2nd class 0.05 Nos each 75.00 3.75  
  Man mulia for ramming 0.16 Nos each 55.00 8.80  
  women mulia for watering 0.22 Nos each 55.00 12.10  
c) Overhead charges @ 10% on (a+b)       5.81  
  Total (a+b+c)       63.92  
          Say Rs. 63.90 / Sqm  
10 10cm dry epidorite metal or any other hard metal of 4cm size well watered and rammed per 1 sqm          
a) Labour as per item No.9       24.65  
b) Add. Cost of hard metal 0.14 cum 1cum 199.00 27.86  
c) Overhead charges @ 10% on (a+b)       5.25  
  Total (a+b+c)       57.76  
          Say Rs. 57.80 / Sqm  
11 Brick on edge flooring over one brick flat set in cement mortal (1:8) per 1 sqm          
a) Material          
  1st class kiln burnt bricks of size (25cm ×12cm×8cm)          
  Having crushing strength not less than 75 Kg/cm2 80 nos 1000 2192.00 175.36  
  sand (Screened and washed) 0.06 cum cum 29.00 1.74  
  cement 0.0071 cum 0.1015 Qntl 1qntl 341.00 34.61  
b) Labour          
  Take 0.19 times of labour of item No. 1 of brick masonry =0.19X271.30 =       51.55  
  Man mulia for mixing sand and cement 0.07 Nos each 55.00 3.85  
c) Overhead charges @ 10% on (a+b)       26.71  
  Total (a+b+c)       293.82  
          Say Rs. 293.80 / Sqm  
12 35mm thick marble chips flooring of dark, light of medium shade rubbed and polished to granolithic finish under layer 25mm thick C.C (1:2:4) with 12m size black hard granitechips and top layer 10mm thick with marble chips of 4 to 7 mm nominal size laid in cement marble powder mix 3:1 (3 cement :1 marblepowder by weight) in prop.4:7 (4 cement marble
powder mix :7 marble chips by volume.) Per 1 sqm
Details of cost for 10sqm with
         
a) Material          
  ordinary cement.          
  Bottom layer          
  12mm size chips 0.23 cum 1cum 494.00 113.62  
  sand (Screened & washed) 0.12 cum 1cum 29.00 3.48  
  Cement 0.754 Qntl 1Qntl 341.00 257.11  
        Total 374.21  
  Top Layer Marble chips 4 mm. to 7mm size 1.4 Qntl 1Qntl 458.00 641.20  
  Cement 0.578 Qntl 1Qntl 341.00 197.10  
  Marble powder 0.1927 Qntl 1Qntl 309.00 59.54  
        Total 897.84  
b) Labour          
  Mason special          
  Bottom layer 2.3 each 85.00 195.50  
  Manson, special(toplayer)          
  Mulia (Bottom layer)3.3Nos 4.65 each 55.00 255.75  
  Mulia (top layer)=1.35 Nos          
  Semi-skilled mulia or rubbing 10.8 each 65.00 702.00  
  (top layer)          
c) Overhead charges @ 10% on (a+b)       242.53  
  Total (a+b+c)       2667.83  
  Rate per 1 Sqm = 2667.83     = 266.78 / Sqm  
    10        
    Say Rs. 266.80 / Sqm        
    8.50        
  Add for wax polishing Total 275.30 / Sqm    
             
13 31mm thick marble chips flooring of dark, light of medium shade rubbed and polished to graolithic finish under layer 25mm thick C.C (1:2:4) with 6m size black hard granitechips and top layer 10mm thick with marble chips of 4 to 7 mm nominal size laid in cement
marble powdermix 3:1 (3 cement :1 marblepowder by weight) in prop.4:7 (4 cement marble powder mix : 7 marble chips by volume) Per 1 sqm (Data for 10Sqm)
With ordinary cement -
         
a) Bottoml layer )same as Item No.-12       374.21  
b) Top Layer          
  Marble chips 0.872 Qntl 1qntl 458 399.38  
  Cement 0.405 Qntl 1qntl 341 138.11  
  Marble powder 0.135 Qntl 1qntl 309 41.72  
  Labour sameas item No.12       1153.25  
c) Overhead charges @ 10% on (a+b+c)       210.67  
  Total (a+b+c+d)       2317.34  
  Rate per 1 Sqm = 2317.34     = 231.73 / Sqm  
    10        
    Say Rs. 231.70 / Sqm        
  Wax polishing 8.50        
    Say Rs. 240.20 / Sqm        
             
14 18mm thick marble chips skirting to dados with dark light or medium shade rubbed and polished to granolithic finish with under layer 12mm. Thick cement plaster (1:3) and top layer 6mm thick with marble chips of 4to 7mm nominal size said in cement marble powder mix 3:1 (3cement :1 marble powder by weight) in prop 4:7 (4 cement marble powder. Mix : 7 marble chips in volume) per 1sqm (Data for 10sqm)
with ordinary cement
         
a) Bottom layer cement 0.715 Qntl 1qtnl 341.00 243.82  
  sand (Screened & washed) 0.15 cum 1cum 29.00 4.35  
b) Top Layer same as item No.13       579.21  
c) Labour          
  Mason special (top layer)1.1No 2.5 Nos each 85.00 212.50  
  Mason special (Bottom layer)1.4          
  Mulia (Bottom layer)1.2Nos. 2.55 Nos each 55.00 140.25  
  Mulia (top layer)=1.35 Nos          
  Semi-skilled mulia or rubbing 10.8 Nos each 65.00 702.00  
  Overhead charges @ 10% on (a+b+c)       188.21  
  Total (a+b+c+d)       2070.34  
  Rate per 1 Sqm = 2070.34     = 207.03 / Sqm  
    10        
        Say Rs. 207.00 / Sqm    
  Wax polishing   8.50      
        Total Rs. 215.50 / Sqm    
             
  Labour charges for fixing glass/ aluminium strips in joints of marble chips floor per 1 metre (Details for 10M)          
a) Labour          
  Mason (2nd class) 0.25 Nos each 75.00 18.75  
  Mulia 0.25 Nos each 55.00 13.75  
b) Overhead charges @ 10% on (a)       3.25  
c) 5% sundries, including T & P       1.63  
  Total (a+b)       37.38  
  Rate per 1 m = 37.38     =3.74 / RM
    10        
      Say Rs. 3.70 / RM      
             
16 Fixing tiles in floors treads or steps and landing on 25mm thick bed of cement mortar 1:1 (1cement : 1sand) jointed with neat cement slury mixed with pigment to match the shades of the tiles including rubbing and polishing complete excluding cost of precast tiles per 1 sqm (Data for 10sqm)          
a) Material          
  Cement 0.13cum 1.857 Qntl 1qntl 341.00 633.24  
  sand (Screened & washed) 0.13 cum 1cum 29.00 3.77  
  cement for slurry at the rate of 4.4 kg/sqm 0.44 Qntl 1qntl 341.00 150.04  
  Cement for grouting 0.44 Qntl 1qtn 341.00 150.04  
b) Labour          
  Mason, special 2.16 Nos each 85.00 183.60  
  Semi-skilled mulia or rubbing 5.5 No each 65.00 357.50  
  Mulia 2.16Nos each 55.00 118.8  
c) Overhead charges @ 10% on (a+b)       159.70  
  Total (a+b+c)       1756.69  
  Rate per 1 Sqm = 1756.69   175.67    
    10        
      Say 175.70      
  Wax polishing   8.50      
      184.20 / Sqm      
             
17 Fixing tiles in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete excluding cost of precast tiles. per 1 sqm (Details for 10sqm)          
a) Material          
  a) Using oridinary cement          
  UNDER LAYER          
  Sand (screened & washed) 0.15 cum 1cum 29 4.35  
  cement 0.715 Qntl 1qntl. 341 243.82  
  cement for slury 0.66 Qntl 1qntl. 341 225.06  
b) Labour          
  Mason (special) 3.25 Nos each 85.00 276.25  
  Mulia 3.25 Nos each 55.00 178.75  
  Semi-skilled mulia for rubbing 7.6 Nos each 65.00 494.00  
c) Overhead charges @ 10% on (a+b)       142.22  
  Total (a+b+c)       1564.45  
  Rate per 1 Sqm = 1564.45   156.44    
    10        
    Say 156.40      
  Wax polishing   8.50      
    Say Rs. 164.90 / Sqm      
             
18 Extra labour for laying tile flooring on stair treads not exceeding 30cm. in width including cost of forming, nosing etc. per 1 sqm (Details for 10sqm)          
a) Labour          
  Mason (special) 0.3 Nos each 85.00 25.50  
  Helper (semi-skilled mulia) 0.3 Nos each 65.00 19.50  
  Mulia 0.3 Nos each 55.00 16.50  
b) Overhead charges @ 10% on (a)       6.15  
  5% Sundries, T&P       3.08  
  Total (a+b)       70.73  
  Rate per 1 Sqm = 70.73   7.07 /Sqm  
    10        
    Say Rs. 7.10 / Sqm        
             
19 Extra labour for making chequers of approved pattern on cement concrete, flooring steps, landing pavement or overplastered surface per 1 sqm (Data for 10sqm)          
a) Labour          
  Mason (2nd class) 0.36 Nos each 75.00 27.00  
  Semi-skilled  0.36 Nos each 65.00 23.40  
b) Overhead charges @ 10% on (a)       5.04  
  c) 2% Sundries, etc.       1.01  
  Total (a+b+c)       56.45  
  Rate per 1 Sqm = 56.45   5.65 /Sqm  
    10        
      Say Rs. 5.60 / Sqm      
20 2.5 cm. Damp proof course with C.C. (1:2:4) using 12mm. Size hard broken granite Chips per1 Sqm.          
a) Material          
  Hand broken granite chips 0.023 cum 1cum. 494.00 11.36  
  12mm. Size          
  Sand (Screened & washed) 0.012 cum 1cum. 29.00 0.35  
  Cement 0.0754 Qntl 1 qntl 341.00 25.71  
b) Labour          
  Man Mulia 0.33 Nos each 55.00 18.15  
  Mason special 0.103 Nos each 85.00 8.76  
  Man Mulia for mixing chips, sand and cement 0.03 Nos each 55.00 1.65  
c) Overhead charges @ 10% (a+b)        6.6  
  Total (a+b+c)       72.58  
        Say Rs. 72.60 / Sqm    
  32mm. thick red oxide flooring, under layer of 25mm. thick C.C. (1:2:4) with 12mm. Size granite chips and top layer of 6mm. Thick  plaster cement red oxide mix, using 3.5kg. Of red oxide per 50kg. of cement 1:3 finished with a floating coat of cement and oxide mix
of same proportion: Per 1 Sqm ( Data for 10 Sqm.)
         
  Material          
  chips 0.23 Cum. 0.023 cum 1cum. 494.00 113.62  
  Sand (Screened & washed ) 0.12 cum 1cum. 29.00 3.48  
  Cement 0.754 Qntl 1Qntl. 341.00 257.11  
  6mm. Colour topping          
  Cement 0.357 Qntl 1Qntl. 341.00 121.74  
  Sand (Screened & washed ) 0.075 cum 1cum. 29.00 2.18  
  Cement for floating coat 0.114 Qntl 1Qntl. 341.00 38.87  
  Red oxide (3.5kg. Per          
  50kgs. Of cement)                    11.40×3.5 0.8 kg 1kg. 83.000 66.40  
  50          
  Labour          
  Mason special 2.7 Nos each 85.00 229.50  
  Semi-skilled mulia helper 8.56 Nos each 65.00 556.40  
  Mulia 1.62 Nos each 55.00 89.10  
c) Overhead charges @ 10% (a+b)        147.84  
  Total (a+b+c)       1626.24  
  Rate per 1 Sqm = 1626.24   162.62 /Sqm  
    10        
      Say Rs. 162.60 / Sqm      
             
Note:            
1 Rate have been arrived on hand broken chips and if crusher broken chips used the difference in cost of materials to be added to arrive at finished rate.  
2 For flooring work in 1st floor or any additional floor add 5 percent extra labour over & above the rate of next lower floor.  
3 For repair item of flooring in 1st. Floor or any additional floor add 2 percent extra labour over & above the rate of next lower floor.  
4 For stone cladding to outer walls of 1st floor and subsequent higher floors add 10 percent extra labour over and above the next lower floor.  
5 In case of stone cladding to outer walls & glazed tile fixing on walls provision of semi-skilled mulia for rubbing & wax polishing as in analysis will not be considered.  
6 Fixing tiles in item No. 16,17 and 18 includes marble, kota, khandalite, granite, kodapa, dholpuri stone, chequered tiles, glazed tiles and terrazzo tiles etc.  
7 For flooring work below ground level beyond 1.5m. And upto 4.5m. Depth add 5% extra labour over and above the rates of the respective items for lowering the materials.  
8 For flooring work below ground level beyond 4.5m. And upto 7.5m. Depth add 7% extra labour over and above the rate of the respective items for lowering the materials.  
9 10% on the above rates will be allowed for the works being executed inside jail premises.  

*****