Hire Charges for Machinery
Sl. No. |
Description |
Unit |
S.Rates for HireCharges for2019-20 |
Remarks |
|
Machine |
Activity |
( Rupees) |
|||
1 |
2 |
3 |
4 |
6 |
7 |
1 |
Dozer( D 80 ) |
Spreading |
Per Hour |
|
As per I&CAD S.No 8 |
Cutting |
|||||
Cleaning |
|||||
2 |
Dozer( D 50 ) |
Spreading Cutting Cleaning |
Per Hour |
1758.4 |
|
3 |
Mortor Grader |
Clearing |
Per Hour |
3601.92 |
|
Spreading |
|||||
GSB |
|||||
WMM |
|||||
4 |
Hydraulic Excavator |
Soil Ordinary |
Per Hour |
|
As per I&CAD S.No.52 |
Soil Marshy |
|||||
Soil unsuitable |
|||||
5 |
Front end loader |
Soil loading |
Per Hour |
1843.52 |
|
Aggregate loading |
Per Hour |
||||
6 |
Tipper- 5.5 Cum |
Transportation of soil, GSB,WMM, Hot mix etc |
Per Hour |
|
As per I&CAD S.No.54 |
Per tonne Km |
8.00 |
|
|||
7 |
Vibratory roller 8 tonne |
Earth/Soil, GSB, |
Per Hour |
|
As per I&CAD S.No.62 |
WMM |
|||||
8 |
Smooth wheeled roller 8 tonne |
Soil compaction ,BM compaction |
Per Hour |
|
As per I&CAD S.No.50 |
9 |
Water tanker 8 Kilolitre |
Water transport |
Per Hour |
|
As per I&CAD S.No.64 |
10 |
Water tanker 6 Kilolitre |
Water transport |
Per Hour |
698.88 |
|
11 |
Tractor |
Pulling |
Per Hour |
464.8 |
|
12 |
Tractor with rotavator |
Scarifying |
Per Hour |
472.64 |
|
13 |
Tractor with ripper attachment |
Scarifying |
Per Hour |
568.232 |
|
14 |
Air Compressor |
General purpose |
Per Hour |
|
As per I&CAD S.No.2 |
15 |
Wet mix plant 60 TPH |
Wet mix |
Per Hour |
1843.52 |
|
16 |
Mechanical broom Hydraulic |
Surface cleaning |
Per Hour |
399.84 |
|
17 |
Bitumen Pressure Distributor |
Applying bitumen tack coat |
Per Hour |
1677.76 |
|
18 |
Emulsion Pressure Distributor |
Applying emulsion tack coat |
Per Hour |
963.2 |
|
19 |
Hot mix Plant – 120 TPH capacity |
DBM/BM/SDC |
Per Hour |
31556 |
|
/Premix |
|||||
20 |
Hot mix Plant – 100 TPH capacity |
DBM/BM/SDC |
Per Hour |
27071.52 |
|
/Premix |
|||||
21 |
Hot mix Plant – 60 TPH capacity |
DBM/BM/SDC |
Per Hour |
24268.16 |
|
/Premix |
|||||
22 |
Hot mix Plant – 40 to 60 TPH capacity |
DBM/BM/SDC |
Per Hour |
21414.4 |
|
/Premix |
|||||
23 |
Paver Finisher Hydrostatic with sensor control 100 TPH |
DBM/BM/SDC |
Per Hour |
3426.6512 |
|
/Premix |
|||||
24 |
PaverfinisherMechanical100 |
Paving of WMM, paving of DLC |
Per Hour |
2518.88 |
|
25 |
Hydraulic Chip Spreader |
Surface dressing |
Per Hour |
2875.04 |
|
26 |
Tandem Road roller |
Rolling of Asphaltic surface |
Per Hour |
1843.52 |
|
27 |
Pneumatic Road roller |
Rolling of Asphaltic surface |
Per Hour |
1436.96 |
|
28 |
Pot-Hole repair machine |
Repair of pot-holes |
Per Hour |
946.4 |
|
29 |
Bitumen boiler oil fired |
Bitumen Spraying |
Per Hour |
234.08 |
|
30 |
GSB Plant 50 Cum |
Producing GSB |
Per Hour |
1280.16 |
|
31 |
Mastic Cooker |
Mastic wearing coat |
Per Hour |
72.8 |
|
32 |
BatchingandMixingPlant(a) 30 Cum capacity |
Concrete mixing |
Per Hour |
1379.728 |
As per I&CAD S.No.10 |
(b) 15 - 20 Cum capacity |
Concrete mixing |
Per Hour |
|
||
33 |
Transit mixer |
Transportation of concrete mix |
Per Hour |
|
As per I&CAD S.No.1 |
34 |
Concrete pump of 45 and 30 cum |
Pumping of Concrete |
Per Hour |
899.36 |
|
35 |
Cranes |
|
|
|
|
(a) 80 tonnes |
Lifting purpose |
Per Hour |
1311.52 |
||
(b) 35 tonnes |
885.92 |
||||
(c) 3 tonnes |
394.24 |
||||
(d)Crane with grab bucket 0.75 cum |
Well foundation |
Per Hour |
2419.2 |
||
(e)Crane with grab bucket 1 cum |
Well foundation |
Per Hour |
3955.84 |
||
36 |
Concrete bucket |
For pouring concrete |
Per Hour |
|
As per I&CAD S.No.14 |
37 |
Kerb casting machine |
Kerb making |
Per Hour |
348.32 |
|
38 |
Concrete mixer |
Concrete mixing |
Per Hour |
|
As per I&CAD S.No.18 |
(a)0.28 cum |
|||||
(b) 1.0 cum |
Concrete mixing |
Per Hour |
726.88 |
||
39 |
Piling rig with bantonite pump |
0.75 m dia to 1.20 m dia boring attachment |
Per Hour |
6132 |
|
40 |
Concrete paver finisher with 40 HP motor |
Paving of concrete surface |
Per Hour |
3248 |
|
41 |
Integrated stone crusher |
Crushing of spalls 100 TPH |
Per Hour |
9757.44 |
|
Crushing of spalls 200 TPH |
Per Hour |
20573.28 |
|||
42 |
Pre stressing jack with pump and access |
Stressing of steel wires/ stands |
Per Hour |
157.92 |
|
43 |
Generator |
|
|
|
|
250 KVA |
Generation of electric energy |
Per Hour |
2072 |
|
|
125 KVA |
Per Hour |
1478.4 |
|
||
100 KVA |
Per Hour |
1261.12 |
|
||
30 KVA |
Per Hour |
|
As per I&CAD S.No.23 |
||
44 |
Pneumatic sinking of Plants |
Pneumatic sinking of wells |
Per K.m. |
62.72 |
|
45 |
Truck 5.5 cum per 10 tonnes |
Material transport |
Per Km. |
|
As per I&CAD S.No.58 |
46 |
Road marking machine |
Road marking |
Per Hour |
124.32 |
|
47 |
Mobile slurry seal equipment |
Mixing and laying slurry seal |
Per Hour |
1261.12 |
|
48 |
Plate compacter |
For compacting in medians |
Per Hour |
53.76 |
|
49 |
Drilling equipment |
For drilling |
Per Hour |
|
As per I&CAD S.No.22 |
Note: The above hire charges of machinery & plant includes crew, oils, conveyance of machinery to site and all other incidentalcharges.
*****