IRON WORK



  IRON WORK (ANALYSIS OF RATES 2006)
Sl. No Description Quantity
Required 
Unit Rate
Rs.      P
Amount
Rs.       P
Remarks
(1) (2) (3) (4) (5) (6) (7)
1 Hoisting joists and trusses and placing in position (labour only) Per 1 Qntl. Data for 0.508 Qntl.          
a) Labour          
  Sangi Mulia for conveying joist from outside to the buildings. 0.25 no Each 65.00 16.25  
  Sangi Mulia for lifting joists up to top of the walls with ropes, etc..  0.75 no Each 65.00 48.75  
  Man Mulia for placing joists in position 0.17 no Each 55.00 9.35  
b) Overhead Charges @ 10% on (a)       7.44  
c) 2% Scaffolding ropes, Sundries, T&P etc. on (a)       1.49  
  Total (a+b+c)       83.28  
  Rate per 1 Qntl. = 83.28 =163.94 / Qntl      
    0.508        
  Say Rs. 163.90 / Qntl          
2 Iron work wrought and put up in window grating including drilling holes in choukathas (labour only) per 1 Qntl. Data for 0.508 Qntl.          
a) Labour          
  Carpenter (2nd Class) 0.75 no Each 75.00 56.25  
  Semi-skilled mulia 0.75 no Each 65.00 48.75  
b) Overhead Charges @ 10% on (a)       10.50  
c) 2% Sundries T & P etc.on (a)       2.10  
  Total (a+b+c)       117.60  
  Rate per 1 Cum. = 117.60 =231.50/Qntl      
    0.508        
  Say Rs. 231.50/Qntl          
3 Iron work wrought and put up in trusses and record racks(labour only) per 1 Qntl. Data for 0.508 Qntl.          
a) Labour          
  Black smith (2nd Class) 1.25 Nos Each 75.00 93.75  
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Helper 1.00 No Each 65.00 65.00  
  Man Mulia 2.50 Nos Each 55.00 137.50  
b) Overhead Charges @ 10% on (a)       37.13  
c) 2% Sundries T & P etc.on (a)       7.43  
  Total (a+b+c)       415.81  
  Rate per 1 Cum = 415.81 =818.52/Qntl      
    0.508        
  Say Rs. 818.50/Qntl          
4 Iron work wrought and put up in grated doors, windows and cage latrines (labour only) per 1 Qntl. Data for 0.508 Qntl.          
a) Labour          
  Black smith (Special) 0.75 Nos Each 85.00 63.75  
  Black smith (2nd Class) 1.00 No Each 75.00 75.00  
  Fitter (Special) 1.00 No Each 85.00 85.00  
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Helper to Black smith 1.00 No Each 65.00 65.00  
  Man Mulia 3.25 Nos Each 55.00 178.75  
b) Overhead Charges @ 10% on (a)       54.25  
c) 2% Sundries T & P etc.on (a)       10.85  
  Total (a+b+c)       607.60  
  Rate per 1 Cum. = 607.60 =1196.06/Qntl      
    0.508        
  Say Rs.1196.10/Qntl          
5 Iron work wrought and put up in bolts of over 15 cm in length (labour only) per 1 Qntl. Data for 0.508 Qntl.          
a) Labour          
  Black smith (Special) 1.00 No Each 85.00 85.00  
  Black smith (2nd Class) 1.50 Nos Each 75.00 112.50  
  Fitter (Special) 1.00 No Each 85.00 85.00  
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Helper to Black smith 2.00 Nos Each 65.00 130.00  
  Man Mulia 3.00 Nos Each 55.00 165.00  
b) Overhead Charges @ 10% on (a)       65.25  
c) 2% Sundries T & P etc.on (a)       13.05  
  Total (a+b+c)       730.80  
  Rate per 1 Cum = 730.80 =1438.58/Qntl      
    0.508        
  Say Rs.1438.60/Qntl          
6 Iron work wrought and put up in bolts less than 15 cm in length (labour only) per 1 Qntl. Data for 0.508 Qntl          
a) Labour          
  Black smith (Special) 1.00 No Each 85.00 85.00  
  Black smith (2nd Class) 1.80 Nos Each 75.00 135.00  
  Fitter (Special) 1.25 No Each 85.00 106.25  
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Hamer Man 2.00 Nos Each 65.00 130.00  
  Man Mulia 3.00 Nos Each 55.00 165.00  
b) Overhead Charges @ 10% on (a)       69.63  
c) 2% Sundries T & P etc.on (a)       13.93  
  Total (a+b+c)       779.81  
  Rate per 1 Cum. = 779.81 =1535.06/Qntl      
    0.508        
  Say Rs.1535.10/Qntl          
7 Drilling holes 6mm to 12mm dia in iron flats, angles, tees etc. of 6mm to 10mm thick with hand drill(labour only) Per each Data for 36 Nos. of holes          
a) Labour          
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Man Mulia 1.00 No Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       13.00  
c) 2% Sundries T & P etc.on (a)       2.60  
  Total (a+b+c)       145.60  
  Rate per 1 Cum. = 145.60 =4.04/Qntl      
    36.00        
  Say Rs.4.00/Qntl          
8 Drilling holes 12mm to 25mm dia in iron flats, angles, tees etc. of 6mm to 10mm thick with hand drill(labour only) Per each Data for 27 Nos. of holes          
a) Labour          
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Man Mulia 1.00 No Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       13.00  
c) 2% Sundries T & P etc.on (a)       2.60  
  Total (a+b+c)       145.60  
  Rate per 1 Cum. = 145.60 =5.39/Qntl      
    27.00        
  Say Rs.5.40/Qntl          
9 Drilling holes 6mm to 12mm dia in iron flats, angles, tees etc. above 10mm thick & upto 16mm thick with hand drill(labour only) Per each Data for 27 Nos. of holes          
a) Labour          
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Man Mulia 1.00 No Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       13.00  
c) 2% Sundries T & P etc.on (a)       2.60  
  Total (a+b+c)       145.60  
  Rate per 1 Cum. = 145.60 =5.39/Qntl      
    27.00        
  Say Rs.5.40/Qntl          
10 Drilling holes 12mm to 25mm dia in iron flats, angles, tees etc. above 10mm thick & upto 16mm thick with hand drill(labour only) Per each Data for 18 Nos. of holes          
a) Labour          
  Fitter (2nd Class) 1.00 No Each 75.00 75.00  
  Man Mulia 1.00 No Each 55.00 55.00  
b) Overhead Charges @ 10% on (a)       13.00  
c) 2% Sundries T & P etc.on (a)       2.60  
  Total (a+b+c)       145.60  
  Rate per 1 Cum. = 145.60 =8.09/Qntl      
    18.00        
  Say Rs.8.10/Qntl          
Note : 1 10% excess on the above rate will be allowed for the works being executed inside jail premises.    

*****