PROCEDURE FOR LOW RISK BASED BUILDING PERMISSION 

Procedure for Building Permission (1-150 sq. mts) 

1)In this case, the applicant applies for building permission if he wants to apply for 1-150 sq. mts.  Only Ground floor construction is allowed for Low Risk Building Permission 

2)Applicant fills up the form (Annexure A-1) and submits the application with supporting documents 

3)Applicant also has to submit self-certified plan in drawing and the documents to register the application. 

4)This application goes in for approval. 

5)Assistant Town Planner / Municipal engineer checks and counter signs on the self –certified plan and documents. 

6)ATP / Municipal Engineer verifies the calculation of charges to be paid for building permission. 

7)Architect/Owner has to pay the required charges for building permission online. 

8)On verification of payment, Assistant town planner digitally signs on the Building Permission certificate which is then available for printing online. 

 Note:  

1)Site Visit and Scrutiny inspection verification is not applicable in case of Low Risk. 

2) No File movement for Chief Officer or Commissioner for Building Permission. 

3)Plinth Permission is not applicable in case of Low Risk Building Permission

Document Checklist 

Document List Mandatory / Optional
Self-Certified documents as:  
XML File Mandatory 
TP File Mandatory 
Original Sale Deed /Lease Deed/Power of attorney/enabling ownership documen Mandatory 
V.F. No 7/12 extract or CTS Card show of area holding Mandatory 
Tax Receipt / Assessment copy of current year Mandatory 
Certified copy of approved Sub Division /Amalgamation/layout of land from concerned authority  Mandatory 
Certified Copy of Measurement Plan of Plot /Layout plan Optional 
Statement of area of holding Optional 
Affidavit From Owner Regard To Area on plan Optional 
Affidavit From Architect/Engineer/Supervisor/Structural Designer Optional 
NA Order  Optional 
Third party interest created by way of agreement of sale or mortgage etc Optional 
Is land leased by Government or local authorities? If YES, Attached NOC of Government or local authority Optional 
Proposed Plan Mandatory 

Procedure for Occupancy Certificat

1)Applicant applies for the proposal of occupancy service. 

2)Applicant submits self-certified completion plan and other related documents along with the proposal.

3)This application then goes for approval to Assistant Town Planner / Municipal Engineer 

4)Assistant Town Planner / Municipal Engineer checks and counter signs the self-certified completion plan and other related documents. 

5)ATP then digitally signs on the Occupancy certificate. 

6)The Occupancy certificate will then be available to the Architect for printing. 

 Note: 

1) Site Visit and Scrutiny inspection verification is not applicable in case of Low Risk. 

2) No charges applicable for Occupancy. All the charges are taken at the time of Building Permission itself. 

3) No File movement for Chief Officer or Commissioner for Occupancy Certificate.

**Note:  Site Visit and Scrutiny inspection verification is not applicable in case of Low Risk. No File movement for Chief Officer or Commissioner for Building Permission. Plinth Permission is not applicable in case of Low Risk Building Permission

Workflow for Low Risk Based Occupancy Certificate 

**Note: Site Visit and Scrutiny inspection verification is not applicable in case of Low Risk. No charges applicable for Occupancy. All the charges are taken at the time of Building Permission itself. No File movement for Chief Officer or Commissioner for Occupancy Certificate

*****