MASONRY STONE WORK



MASONRY STONE WORK  (ANALYSIS OF RATES 2006)
Sl. No Description Qunatity required Unit Rate
Rs.P
Amount
Rs.P
Remarks
(1) (2) (3) (4) (5) (6) (7)
1 Random rubble H.G. stone Masonry in lime mortar (1:2) in foundation and plinth. Per 1 cum.          
a) Material          
  Rough granite stone quarried including bond stones 1 cum 1cum 148.00 148.00  
  Lime (Ghooting) unslaked 0.17 cum 1cum 1720.00 292.40  
  Sand (screened &washed) 0.24 cum 1cum 29.00 6.96  
  Grinding lime mortar (vide item No 1 of concrete
excluding O.H.C )
0.34 cum 1cum. 176.95 60.16  
b) Labour          
  Mason special 0.35 Nos Each 85.00 29.75  
  Mason 2nd class 1.41 Nos Each 75.00 105.75  
  Man Mulia 1.41 Nos Each 55.00 77.55  
  Woman Mulia 1.41 Nos Each 55.00 77.55  
c) Overhead charges @ 10% on (a+b)       79.81  
  Total (a+b+c)       877.94  
          Say Rs. 877.90 / cum  
2 Random rubble H.G. stone Masonry in cement mortar (1:5) in foundation and plinth. Per 1 cum.          
a) Material          
  Rough granite stone quarried including bond stones 1 cum 1cum. 148.00 148.00  
             
  Sand (screened &washed) 0.34 cum 1cum. 29.00 9.86  
  Cement 0.9724 Qntl 1Qntl 341.00 331.59  
b) Labour          
  Man Mulia for mixing mortar  0.35 Nos Each 55.00 19.25  
  Labour as per item No.1       290.60  
c) Overhead charges @ 10% on (a+b)       79.93  
  Total (a+b+c)       879.23  
          Say Rs. 879.20 / cum  
3 Random rubble H.G. stone Masonry in cement mortar (1:6) in foundation and plinth. Per 1 cum.          
a) Material          
  Rough granite stone quarried 1 cum 1cum. 148.00 148.00  
  including bond stones          
  Sand (screened &washed) 0.34 cum 1cum. 29.00 9.86  
  Cement 0.8151 Qntl 1Qntl 341.00 277.95  
b) Labour          
  Man Mulia for mixing mortar 0.35 Nos Each 55.00 19.25  
  Labour as per item No.1       290.6  
c) Overhead charges @ 10% on (a+b)       74.57  
  Total (a+b+c)       820.23  
          Say Rs. 820.20/cum  
4 Random rubble H.G. stone Masonry in cement mortar (1:8) in foundation and plinth. Per 1 cum.          
a) Material          
  Rough granite stone quarried 1 cum 1cum 148.00 148.00  
  including bond stones          
  Sand (screened &washed) 0.34 cum 1cum. 29.00 9.86  
  Cement 0.6078 Qntl 1Qntl 341.00 207.26  
b) Labour          
  Man Mulia for mixing mortar 0.35 Nos Each 55.00 19.25  
  Labour as per item No.1       290.60  
c) Overhead charges @ 10% on (a+b)       67.50  
  Total (a+b+c)       742.47  
          Say Rs. 742.50 / cum  
5 Random rubble H.G. stone Masonry in cement mortar (1:4) in foundation and plinth. Per 1 cum.          
a) Material          
  Rough granite stone quarried 1 cum 1cum 148.00 148.00  
  including bond stones          
  Sand (screened &washed) 0.34 cum 1cum. 29.00 9.86  
  Cement 1.2156 Qntl 1Qntl 341.00 414.52  
b) Labour          
  Man Mulia for mixing mortar 0.35 Nos Each 55.00 19.25  
  Labour as per item No.1       290.60  
c) Overhead charges @ 10% on (a+b)       88.22  
  Total (a+b+c)       970.45  
          Say Rs. 970.50 / cum  
6 Coursed rubble hard Granite stone masonry (first class) in lime mortar (1:2) in foundation and plinth Per 1 cum           
a) Material          
  Rough granite stone quarried 1 cum 1cum 148.00 148.00  
  Bond stone          
  Lime (Ghooting) unslaked 0.12 cum 1cum 1720.00 206.40  
  Sand (screened &washed) 0.24 cum 1cum 29.00 6.96  
  Grinding lime mortar 0.24 cum 1cum 176.95 42.47  
b) Labour          
  Labour as per item No.1excluding O.H.C       290.60  
  Add difference in cost of 1.41 Nos Each 10.00 14.10  
  Sangi and Man mulia          
  Add. Extra mason special.. 2.47 Nos Each 85.00 209.95  
c) Overhead charges @ 10% on (a+b)       91.85  
  Total (a+b+c)       1010.33  
          Say Rs. 1010.30 / cum  
7 Coursed rubble hard Granite stone masonry (first class) in cement mortar (1:5) in foundation and plinth Per 1 cum.          
a) Material          
  Rough stone granite including 1 cum 1cum 148.00 148.00  
  Bond stone          
  Sand (screened &washed) 0.24 cum 1cum. 29.00 6.96  
  cement 0.6864 Qntl 1Qntl 341.00 234.06  
b) Labour          
  Labour as per item No.6       514.65  
  Man mulia for mixing sand 0.25 Nos Each 55.00 13.75  
  and cement in small quantities          
  and gettering water          
c) Overhead charges @ 10% on (a+b)       91.74  
  Total (a+b+c)       1009.16  
          Say Rs. 1009.20 / cum  
8 Coursed rubble hard Granite stone masonry (first class) in cement mortar (1.4) in foundation and plinth Per 1 cum.          
a) Rate as per item No.7       1009.20  
b) Add, extra cost of cement with 10% OHC 0.1716 Qntl 1qntl 375.10 64.37  
  Total (a+b)       1073.57  
          Say Rs. 1073.60 / cum  
9 Coursed rubble hard Granite stone masonry (first class) in cement mortar (1.6) in foundation and plinth Per 1 cum.           
a) Material          
  Rough stone granite including 1 cum 1cum 148.00 148.00  
  Bond stone          
  Sand (screened &washed) 0.24 cum 1cum. 29.00 6.96  
  cement 0.572 Qntl 1Qntl 341.00 195.05  
b) Labour          
  Labour as per item No.6       514.65  
  Man mulia for mixing sand 0.25 Nos Each 55.00 13.75  
  and cement in small quantities          
  and gettering water          
c) Overhead charges @ 10% on (a+b)       87.84  
  Total (a+b+c)       966.25  
          Say Rs. 966.30 / cum  
10 Coursed rubble hard Granite stone masonry (first class) in cement mortar (1.8) in foundation and plinth Per 1 cum.          
a) Material          
  Rough stone granite including 1 cum 1cum 148.00 148.00  
  Bond stone          
  Sand (screened &washed) 0.24 cum 1cum. 29.00 6.96  
  cement 0.429 Qntl 1Qntl 341.00 146.29  
b) Labour          
  Labour as per item No.6       514.65  
  Man mulia for mixing sand 0.25 Nos Each 55.00 13.75  
  and cement in small quantities          
  and gettering water          
c) Overhead charges @ 10% on (a+b)       82.96  
  Total (a+b+c)       912.61  
          Say Rs. 912.60 / cum  
11 Random rubble hard granite stone masonry in clay or sand or gravel grouted in foundation and plinth Per 1 cum.          
a) Material          
  Rough stone granite including 1 cum 1cum 148.00 148.00  
  Bond stone          
  Puddle clay or sand earth Puddle clay or sand earth 0.24 cum 1cum. 37.00 8.88  
  watering          
b) Labour          
  Mason 2nd class 1.41 Nos Each 75.00 105.75  
  Man mulia 1.06 Nos Each 55.00 58.3  
  Woman Mulia 1.41 Nos Each 55.00 77.55  
c) Overhead charges @ 10% on (a+b)       39.85  
  Total (a+b+c)       438.33  
          Say Rs. 438.30 / cum  
12 Dry stone masonry or rough stone dry masonary for guard walls and retaining walls with hard granite stones
Per 1 cum.
         
a) Material          
  Rough stone granite including 1 cum 1cum 148.00 148.00  
  Bond stone          
b) Labour          
  Mason 2nd class 0.52 Nos Each 75.00 39.00  
  Semiskilled mulia 0.52 Nos Each 65.00 33.80  
  Man mulia 0.52 Nos Each 55.00 28.60  
  Woman Mulia 0.52 Nos Each 55.00 19.25  
c) Overhead charges @ 10% on (a+b)       26.87  
  Total (a+b+c)       295.52  
          Say Rs. 295.50 / cum  
  Rough stone dry packing in approns and revetments with hard granite stones (15cm to 30cm) Per 1 cum.          
a) Material          
  Rough stone granite including 1 cum 1cum 148.00 148.00  
  spalls for filling and wedging          
b) Labour          
  Mason special 0.17 Nos Each 85.00 14.45  
  stone packer 0.35 Nos Each 65.00 22.75  
  Woman Mulia 0.52 Nos Each 55.00 28.60  
  male mulia 0.52 Nos Each 55.00 28.60  
c) Overhead charges @ 10% on (a+b)       24.24  
  Total (a+b+c)       266.64  
          Say Rs. 266.60 / cum  
14 Removing old revetment and approns and repacking with old stones Per 1 cum          
a) Rate as per item No.13 Deduct       266.64  
  Cost of H.G. stone including 10% O.H.C     (-) 162.8  
          103.84  
b) Add for dis-mantling          
  Man mulia 0.35 Nos Each 55.00 19.25  
  Woman Mulia 1 No Each 55.00 55.00  
c) Overhead charges @ 10% on (a+b)       7.43  
  Total (a+b+c)       185.52  
          Say Rs. 185.50 / cum  
15 Rough stones dry packing in approns and revetment with hard granite stone 30cm and above size Per 1 cum.          
a) Rate as per item No.13 Deduct       266.60  
b) Man mulia extra for carryng heavy stones 0.35 Nos Each 55.00 19.25  
c) Overhead charges @ 10% on (a+b)       1.93  
  Total (a+b+c)       185.52  
          Say Rs. 287.80 / cum  
16 Laterite stone masonry in cement mortar (1:8) in foundation and plinth Per 1 cum.          
a) Material          
  Rough dressed laterite stone 1 cum 1cum. 372.00 372.00  
  Sand (screened &washed) 0.24 cum 1cum. 29.00 6.96  
  cement 0.429 Qntl 1 qntl 341.00 146.29  
b) Labour          
  stone dresser or cutter, 2.12 Nos Each 85.00 180.20  
  Sangi mulia 1.41 Nos Each 65.00 91.65  
  Mason ( special ) 0.175 Nos Each 85.00 14.88  
  Mason 2nd class 1.05 Nos Each 75.00 78.75  
  Man mulia 1.05 Nos Each 55.00 57.75  
  Man mulia for preparing mortar and curring etc 0.16 Nos Each 55.00 8.80  
c) Overhead charges @ 10% on (a+b)       95.73  
  Total (a+b+c)       1053  
          Say Rs. 1053.00 / cum  
17 Laterite stone masonry in cement mortar (1 : 6) in foundationand plinth Per 1 cum.           
a) Rate as per item No.16       1053.00  
b) Add difference in cost including 10% O.H.C 0.143 Qntl 1qntl 375.10 53.64  
  of cement (0.572 - 0.429)Qntl=0.143 Qntl          
  Total (a+b)       1106.64  
          Say Rs. 1106.60 / cum  
18 Laterite stone masonry in cement mortar (1:4) in foundationand plinth Per 1 cum          
a) Rate as per item No.16       1053.00  
b) Add difference in cost including 10% O.H.C 0.43 Qntl 1qntl 375.10 161.29  
  of cement (0.858 - 0.428)Qntl=0.43 Qntl       1214.29  
  Total (a+b)       Say Rs. 1214.30 / cum  
             
19 Laterite stone masonry in cement mortar (1 : 12)
in foundationand plinth Per 1 cum.
         
a) Rate as per item No.16       1053.00  
b) Deduct cost including 10% O.H.C for less -0.142 Qntl 1qntl 375.10 -53.34  
  cement (0.429-0.2868=0.1422Qntl)       999.66  
  Total (a-b)       Say Rs. 999.70 / cum  
             
20 Laterite stone masonry in lime mortar (1:2)
in foundationand plinth Per 1 cum
         
a) Rate as per item No.16       1053.00  
b) Deduct cost including 10% O.H.C  -0.429 Qntl 1qntl 375.10 -160.92  
  cement as per item 16          
  Add-Cost of lime including 10% O.H.C 0.12 cum 1cum. 1926.4 231.17  
  (Ghooting unslaked)       1123.25  
  Total       Say Rs. 1123.30 / cum  
             
21 Laterite stone masonry in clay in foundation and plinth
Per 1 cum.
         
a) Material          
  clay mortar for masonry work 0.24 cum 1cum. 37.00 8.88  
  Rough dressed laterite stone 1 cum 1cum. 372.00 372.00  
  Labour          
  stone dresser, 2.12 Nos each 85.00 180.2  
  sangi mulia 1.41 Nos each 65.00 91.65  
  Mason, 2nd class 1.05 Nos each 75.00 78.75  
  Man mulia 1.05 Nos each 55.00 57.75  
c) Overhead charges @ 10% on (a+b)       78.92  
  Total (a+b+c)       868.15  
          Say Rs. 868.20 / cum  
22 Laterite block edge packing
Per 1 cum.
         
a) (Labour only)          
  stone packer 0.71 Nos each 65.00 46.15  
  Semiskilled mulia 0.71 Nos each 65.00 46.15  
  Man mulia 0.71 Nos each 55.00 39.05  
b) Overhead charges @ 10% on (a)       13.14  
c) 2% sundries and T.&P. etc on (a).       2.63  
  Total (a+b+c)       147.11  
          Say Rs. 147.10 / cum  
23 Laterite block packing flat (Labour only)
Per 1 cum.
         
a) (Labour only)          
  stone packer 0.35 Nos each 65.00 22.75  
  Semiskilled mulia 0.71 Nos each 65.00 46.15  
  Man mulia 0.35 Nos each 55.00 19.25  
b) Overhead charges @ 10% on (a)       8.82  
c) 2% sundries and T.&P. etc on (a).       1.76  
  Total (a+b+c)       98.73  
          Say Rs. 98.70 / cum  
24 Collecting scattered rubbles and stacking within 50m lead
Per 1 cum.
         
a) Labour          
  Man mulia 0.53 Nos each 55.00 29.15  
b) Overhead charges @ 10% on (a)       2.92  
c) 2% sundries and T.&P. etc on (a).       0.58  
  Total (a+b+c)       32.65  
          Say Rs. 32.70 / cum  
25 Gravel backing to revetments
Per 1 cum.
         
a) Material          
  Gravel (moorum) 1 cum 1cum. 45.00 45.00  
b) Labour          
  Man mulia for working up 0.71 Nos each 55.00 39.05  
  with water to plastic state          
  Woman Mulia 0.35 Nos each 55.00 19.25  
c) Overhead charges @ 10% on (a+b)       10.33  
  Total (a+b+c)       113.63  
          Say Rs. 113.60 / cum  
26 Metal spall backing in the rear of wall steining or weep holes of abutments and for deep drains, per 1cum          
a) Material          
  Hand broken granite metal 1 cum 1cum. 311.00 311.00  
  5cm size 0.88 Nos each 55.00 48.40  
b) Labour          
  Man mulia for lowering the          
  materials and packing          
  in the rear of the steining          
c) Overhead charges @ 10% on (a+b)       35.94  
  Total (a+b+c)       395.34  
          Say Rs. 395.30 / cum  
Note       Unit Rate  
1 For stone masonry in super structure add extra labour for scaffolding to the rate in foundation and plinth ……………… cum 41.9  
2 For stone masonry in well steining add extra towards extra labour and scaffolding etc. to the rate in foundation and plinth … cum 71.7  
3 For dry stone masonry or rough stonedry masonry for well steining add extra towards labour and scaffolding etc to the rate of dry stone masonry for retaining walls (Item 12)……………… cum 58.5  
4 Where stone other than granite are used deduct the difference between the cost of stones from the respective items      
5 When crusher broken metals and chips are used, the difference in cost between hand broken and crusher broken materials in respective items are to be added.      
6 For stone masonry work below ground level beyond 1.5m and upto 4.5m depth add 15 percent extra labour over and above and above the rates of the respective item for lowering the materials      
7 For stone masonary work below ground level beyond 4.5m and upto 7.5m depth and 20percent extra labour over and above the rates of the respective items for lowering the materials.      
8 10 per cent on the above rate will be allowed for the works being executed inside jail premises.      

*****