MATERIALS



CONVEYANCE CHARGES FOR MATERIALS BY HEAD LOAD

FOR THE YEAR : 2018-19

S.No

Total distance 

(total lead includes initial lead)

Earth / sand / gravel / murrum / lime / surki / size stone / cut stone / rubble / coarse aggregate in -/cum cement / reinforcement & structural steel in -/t shahbad / PCC & BS slab / CC & laterite blocks / wood in -/cum
1 2 3 4 5
1  Total lead upto 50 m (Initial lead) Cost included in item basic rate in SR
2  Total lead upto 100 m 76.90 44.90 97.90
3  Total lead upto 150 m 153.80 89.70 195.80

NOTES:

1. For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be adopted irrespective of mode of conveyance.

2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of mode of conveyance.

3. Loading and unloading charges are not payable for conveyance by head load.

4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and stones are for loose volume and not for compacted or in-situ volume.

5. The rates for lead charges by head load and upto 5 km by any mode are cumulative and inclusive of lead charges for preceding lead.
Example: Lead charges for conveyance of Earth / Sand for total lead of 100 m shall be corrosponding to lead charges ' Total lead upto 100 m ' in the statement of lead charges by head load.

Lead charges for Earth / Sand for total lead of 100 m 76.90 / cum

CONVEYANCE CHARGES FOR MATERIALS BY ANY MODE

FOR THE YEAR : 2018-19

( Excluding loading and unloading charges )

Sl No. Distance Earth / sand / murum / gravel / lime in -/cum Rubble / Size Stone / Cut Stone / coarse aggregate im -/cum

cement / steel / pipes / ac sheet / gi sheet / rcc pole in -/cum

shahbad / pcc / bs slabs / cc / laterite blocks / wood in -/cum water in -/cum
1 2 3 4 5 6 7
1 Lead upto 1 km 66.60 101.50 78.80 205.80 60.80
2 Lead more than 1 km upto 2 km 78.60 113.30 86.10 223.10 68.10
3 Lead more than 2 km upto 3 km 89.70 124.80 93.30 240.10 75.30
4 Lead more than 3 km upto 4 km 100.50 135.70 100.20 256.10 82.10
5 Lead more than 4 km upto 5 km 111.20 146.40 106.90 271.90 88.80
6 Every km beyond 5 km upto 30 km 10.30 10.40 6.50 15.30 6.50
7 Every km beyond 30 km 9.70 9.80 6.10 14.40 6.1

NOTES:

1. For total lead exceeding 150 m conveyance by mechanical means only shall be added irrespective of mode of conveyance.

2. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and stones are for loose volume and not for compacted or in-situ volume.

3. The rates for lead charges upto 5 km by any mode are cumulative and inclusive of lead charges for preceding lead.
Example: Lead charges for conveyance of Earth / Sand for total lead of 4 kms shall be corrosponding to lead charges ' Beyond 3 km upto 4 km ' in the statement of lead charges by any mode.

Lead charges for Earth / Sand for total lead of 4 km 100.50 / cum

WRD: 1.4.3. LOADING AND UNLOADING CHARGES FOR MATERIALS

FOR THE YEAR : 2018-19

Sl No. Distance Earth / sand / murum / gravel / lime in -/cum Rubble / Size Stone / Cut Stone / coarse aggregate im -/cum

cement / steel / pipes / ac sheet / gi sheet / rcc pole in -/cum

shahbad / pcc / bs slabs / cc / laterite blocks / wood in -/cum water in -/cum
1 2 3 4 5 6 7
1 loading 129.20 152.50 139.70 134.60 34.50
2 unloading 18.10 76.25 139.70 134.60 gravity

NOTES:

1. Loading and unloading charges are not payable for conveyance by head load.

2. Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 50 m wherever specified.

3. Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond initial lead of 1 km wherever specified.

4. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone are inclusive of stacking.

5. Unloading of materials includes stacking wherever applicable.

LIFT CHARGES FOR MATERIALS 

FOR THE YEAR : 2018-19

S.No

Total distance 

(total lead includes initial lead)

Earth / sand / gravel / murrum / lime / surki / size stone / cut stone / rubble / coarse aggregate in -/cum cement / reinforcement & structural steel in -/t shahbad / PCC & BS slab / CC & laterite blocks / wood in -/cum
1 2 3 4 5
1

Total lift upto 1.50 m

( Initial lift )

Cost included in item basic rates in SR
2 Total lift upto 3.00 m 13.50 9.60 17.90
3 Total lift upto 4.50 m 26.90 19.20 35.90
4 Total lift upto 6.00 m 40.40 28.80 53.80
5 Total lift upto 7.50 m 53.80 38.50 71.80

NOTES :

1. The rates for lift charges are cumulative and inclusive of rates for preceding lift.
Example : Lift charges for total lift of 6 m shall be corrosponding to lift charges " Total lift upto 6.00 m " in the statement of lift charges.

Lift charges for Earth / Sand for total lift of 6 m 40.40 / cum

2. Lift charges are not payable where conveyance of materials is by mechanical means to final placing point.

ROYALTY RATES ON MATERIALS

FOR THE YEAR : 2018-19

Sl No. Name of minor mineral Area of applicability Rate in -/unit quality
1 2 3 4
1 Murum Entire state 20.00 / tonne
2 Ordinary building stones Entire state 60.00 / tonne
3 Lime stone under title ' Shahabad stone ' Entire state 70.00 / tonne
4 Ordinary sand Entire state 80.00 / tonne

NOTES :

1. The recovery of royalty charges on materials listed above, wherever applicable, shall be regulated as per Note.5 under " General notes on Schedule of Rates.

2. Royalty charges as applicable to murum shall be considered for Earth / Soil also.

3. Royalty charges as applicable to ordinary building stones shall be considered for coarse aggregate also.

4. Royalty charges as applicable to ordinary sand shall be considered for fine aggregate.

5. Royalty charges as applicable to Shahabad stone shall be considered for Yaragunta / Cudappa stone slabs also.

*****