PLASTERING



PLASTERING (ANALYSIS OF RATES 2006)
Sl. No Description Qunatity required Unit Rate
Rs.      P
Amount
Rs.       P
Remarks
(1) (2) (3) (4) (5) (6) (7)
1 12mm. thick lime plaster (1:2) on brick work per 1 Sqm            
a)  Materials            
  Lime (Ghooting unslaked) including punning. 0.008 cum 1 cum 1720.00 13.76  
  Sand (Screened and washed) 0.016 cum 1 cum 29.00 0.46  
b) Labour            
  Grinding lime mortar as per item No. 1 of concrete excluding 10% OHC . 0.016 cum 1 cum 176.95 2.83  
  Mason 2 nd class 0.14 Nos Each 75.00 10.50  
  Man Mulia 0.05 Nos Each 55.00 2.75  
  Women Mulia 0.05 Nos Each 55.00 2.75  
c) Overhead charges @10% on (a+b)         3.31  
  Total(a+b+c)         36.36  
          Say   Rs. 36.40 /Sqm
2 20mm. thick lime plaster (1:2) on brick work per 1 Sqm 0.011 cum 1 cum 1720.00 18.92  
a)  Materials            
  Lime (Ghooting unslaked) including punning Sand (Screened and washed) 0.022 cum 1 cum 29.00 0.64  
  Grinding lime mortar as per item No. 1 of concrete excluding 10% OHC . 0.022 cum 1 cum 176.95 3.89  
b) Labour            
  Mason (2nd class) 0.016 Nos Each 75.00 12.00  
  Man Mulia 0.11 Nos Each 55.00 6.05  
  Women Mulia 0.11 Nos Each 55.00 6.05  
c) Overhead charges @10% on (a+b)         4.75  
  Total(a+b+c)         52.31  
          Say   Rs. 52.30 /Sqm
3 12mm. thick cement plaster (1:3) on brick work per 1 Sqm            
a)  Materials            
  Sand (Screened and washed) 0.015 cum 1 cum 29.00 0.44  
  Cement 0.0715 Qntl 1Qntl 341.00 24.38  
  Man mulia for mixing sand and cement in small quantities and Watering 0.02 Nos Each 55.00 1.10  
b) Labour            
  Labour as per lime plaser on brick works as per items (I)          16.00  
c) Overhead charges @10% on (a+b)         4.19  
  Total(a+b+c)         46.11  
          Say   Rs. 46.10 /Sqm
4 12mm. thick cement plaster (1:6) for brick work per 1 Sqm            
a)  Materials            
  Sand (Screened and washed) 0.015 cum 1 cum 29.00 0.44  
  Cement   0.0025 cum 0.0358 Qntl 1Qntl 341.00 12.31  
b) Labour            
  Labour as per item No.3         17.10  
c) Overhead charges @10% on (a+b)         2.97  
  Total(a+b+c)         32.72  
          Say   Rs. 32.70 /Sqm
5 12mm. Thick cement plaser (1:8) for brick work per 1 Sqm.            
a)  Rate as per item No.4         32.70  
b) Deduct - Difference in cost of cement including OHC (0.0225-0.0019) = 0.0006cum or 0.0086Qntl -0.0086   1Qntl 375.10 -3.23  
  Total(a-b)         29.47  
          Say   Rs. 29.50 /Sqm
6 12mm thick cement plaster (1 : 4) over brick work with cement punning for skirting per 1 Sqm.            
a)  Materials            
  Sand (Screened and washed) 0.015 cum 1 cum 29.00 0.44  
  Cement   0.0045 cum 0.0644 Qntl 1Qntl 341.00 21.96  
b) Labour            
  Manson 2nd Class 0.15 Nos Each 75.00 11.25  
  Women Mulia 0.04 Nos Each 55.00 2.20  
  Man Mulia for mixing 0.05 Nos Each 55.00 2.75  
  Sand & Cement 0.02 Nos Each 55.00 1.10  
c) Overhead charges @10% on (a+b)         3.97  
  Total(a+b+c)         43.67  
          Say   Rs. 43.70 /Sqm
7 12mm thick cement plaster (1:4) over brick work including cement punning and bitumen painting over top of wall per 1 Sqm.            
a) Rate as per item No.6 1 Sqm     43.70  
b) Add for bitumen painting one coat 1 Sqm     6.60  
  Total(a+b)         50.30  
          Say   Rs. 50.30 /Sqm
8 20mm. thick cement plaster (1:6) for stone work per 1 Sqm.            
a) Materials            
  Sand ( Screened and washed ) 0.021 cum 1 cum 29.00 0.61  
  Cement   0.004 cum 0.057 Qntl 1 Qntl 341.00 19.44  
b) Labour            
  Man mulia for mixing sand and cement in small quantities and watering 0.02 Nos Each 55.00 1.10  
  Labour as per lime plaster on stone work (Vide item 2 )         24.10  
c) Overhead charges @10% on (a+b)         4.52  
  Total(a+b+c)         49.77  
          Say   Rs. 49.80 /Sqm
9 20 mm. thick cement plaster ( 1 : 8) for stone work per 1Sqm.            
a) Rate as per item No. 8         49.80  
b) Deduct - difference in cost of cement including
OHC
-0.0143 Qntl 1 Qntl 375.10 -5.36  
  Total(a-b)         44.44  
          Say   Rs. 44.40 /Sqm
10 Lime flush pointing to stone masonary (1 : 1.5)
Per 1 Sqm
           
a) Materials            
  Lime ( Ghooting unslaked) 0.006 cum 1 cum 1720.00 10.32  
  Sand (screened & washed) 0.006 cum 1 cum 29.00 0.17  
  Grinding lime mortar as per item No. 1 of concrete excluding 10% OHC and 2% T&P. 0.009 cum 1 cum 176.95 1.59  
b) Labour            
  Mason ( 2 nd class) 0.11 Nos Each 75.00 8.25  
  Man Mulia 0.05 Nos Each 55.00 2.75  
  Women Mulia 0.11 Nos Each 55.00 6.05  
c) Overhead charges @10% on (a+b)         2.91  
  Total(a+b+c)       Total 32.04  
          Say   Rs. 32.10 /Sqm
11 Lime flush pointing to brick masonry (1:1 1/2) per 1 Sqm            
a) Materials            
  Lime (ghooting unslacked) 0.0045   1 cum 1720.00 7.74  
  Sand ( Screened and washed) 0.006   1 cum 29.00 0.17  
  Grinding lime mortar as per item No. 1 of concrete excluding 10% OHC and 2% T&P. 0.009   1 cum 176.95 1.59  
b) Labour            
  Mason (2nd class) 0.13 Nos Each 75.00 9.75  
  Man Mulia 0.05 Nos Each 55.00 2.75  
  Women Mulia 0.11 Nos Each 55.00 6.05  
c) Overhead charges @10% on (a+b)         2.81  
  Total(a+b+c)         30.86  
          Say   Rs. 30.90 /Sqm
12 Cement flush pointing to stone masonry (1 :3) per 1 Sqm.            
a) Materials            
  Sand ( screened & washed) 0.009   1 cum 29.00 0.26  
  Cement 0.003 cum 0.043   1 qntl 341.00 14.66  
b) Labour            
  Man mulia for mixing cement and sand in small quantities and watering  0.009 Nos Each 55.00 0.50  
  labour as per lime flush pointing to stone masonry (vide item 10)         17.05  
c) Overhead charges @10% on (a+b)         3.25  
  Total(a+b+c)         35.72  
          Say   Rs. 35.70 /Sqm
13 Cement flush pointing to brick masonry ( 1 : 3)
per1 Sqm
           
a) Materials            
  Sand ( screened & washed) 0.006   1 cum 29.00 0.17  
  Cement 0.002 cum 0.0286   1 qntl 341.00 9.75  
b) Labour            
  Man mulia for mixing cement and sand in small quantities and watering for mixing 0.006 Nos Each 55.00 0.33  
  labour as per lime flush pointing to stone masonry (vide item 11)         18.55  
c) Overhead charges @10% on (a+b)         2.88  
  Total(a+b+c)         31.68  
          Say   Rs. 31.70 /Sqm
14 16 mm. thick cement plaster (1 :6) over brick or stone masonry per 1Sqm.            
a) Materials            
  Sand ( screened & washed) 0.018   1 cum 29.00 0.52  
  Cement 0.003 cum 0.043   1 qntl 341.00 14.66  
b) Labour            
  Labour as per item No. 8         25.20  
c) Overhead charges @10% on (a+b)         4.04  
  Total(a+b+c)         44.42  
          Say   Rs. 44.40 /Sqm
15 16 mm thick cement plaster (1:8) over brick or stone masonry per 1Sqm            
a) Materials            
  Sand ( screened & washed) 0.018   1 cum 29.00 0.52  
  Cement 0.0329   1 qntl 341.00 11.22  
b) Labour            
  Labour as per item No. 14         25.20  
c) Overhead charges @10% on (a+b)         3.69  
  Total(a+b+c)         40.63  
          Say   Rs. 40.60 /Sqm
16 12mm. thick cement plaster (1:4) over brick work per 1 Sqm.            
a) Materials            
  Sand ( screened & washed) 0.015   1 cum 29.00 0.44  
  Cement 0.0038 cum 0.0543   1 qntl 341.00 18.52  
b) Labour            
  Labour as per cement plaster (1:6) for brick work in item No.4         17.10  
c) Overhead charges @10% on (a+b)         3.61  
  Total(a+b+c)         39.67  
          Say   Rs. 39.70 /Sqm
17 20mm. thick cemet plaster (1:4) per 1Sqm            
a) Materials            
  Sand ( screened & washed) 0.021   1 cum 29.00 0.61  
  Cement  0.0744   1 qntl 341.00 25.37  
b) Labour            
  Labour as per 20 mm, thick cement plaster (1:6) vide Item.No.8         25.20  
c) Overhead charges @10% on (a+b)         5.12  
  Total(a+b+c)         56.30  
          Say   Rs. 56.30 /Sqm
18 12mm. thick sand and mud plaster er 1 Sqm            
a) Labour            
  Manson (2nd Class) 0.108 Nos Each 75.00 8.10  
  Woman mulia 0.04 Nos Each 55.00 2.20  
  Man mulia for preparation of mortar and watering 0.012 Nos Each 55.00 0.66  
b) Overhead charges @10% on (a)         1.10  
c) 10% preparation of mud and cowdung including cost of mud, sand and cowdung         1.10  
  Total(a+b+c)         13.16  
          Say   Rs. 13.20 /Sqm
19 Cement flush pointing to tile celiing (1:3) size of tiles 30 cm ×15cm. Per 1Sqm.            
a) Materials            
  Cement 0.0257   1Qntl 341.00 8.76  
  Sand (Screened and washed) 0.0055   1 Cum 29.00 0.16  
b) Labour            
  Manson (Special) 0.057 Nos Each 85.00 4.85  
  Women mulia 0.081 Nos Each 55.00 4.46  
  Man Mulia for preparation of mortar and watering 0.012 Nos Each 55.00 0.66  
c) Overhead charges @10% on (a+b)         1.89  
d) Add - Extra for scaffolding         0.64  
  Total(a+b+c+d)         21.42  
          Say   Rs. 21.40 /Sqm
20 Cement rule pointing including racking out joints (1 :3) over brick work per 1Sqm.            
a) Materials            
  Cement  0.0018 cum 0.02574   1Qntl 341.00 8.78  
  Sand (Screened and washed) 0.0055   1 Cum 29.00 0.16  
b) Labour            
  Manson (Special) 0.054 Nos Each 85.00 4.59  
  Mason (2nd class) 0.108 Nos Each 75.00 8.10  
  Women mulia 0.162 Nos Each 55.00 8.91  
  Man Mulia for preparation of mortar and watering etc., 0.012 Nos Each 55.00 0.66  
c) Overhead charges @10% on (a+b)         3.12  
  Total(a+b+c+d)         34.32  
          Say   Rs. 34.30 /Sqm
21 Cement rule pointing (1:3) including racking out
joints over brick work per 1Sqm(Labour only)
           
a) Labour            
  Manson (Special) 0.108 Nos Each 85.00 9.18  
  Women mulia 0.18 Nos Each 55.00 9.90  
  Man Mulia for preparation of mortar and watering  0.012 Nos Each 55.00 0.66  
b) Overhead charges @10% on (a)         1.97  
c) 2% sundries including watering for curing racking
out joints, tools and plants etc.
        0.39  
  Total(a+b+c+d)         22.10  
               
          Say   Rs. 22.10 /Sqm
22 Pebble dashed plaster with black hard granite chips 12mm. Size & 12mm. Thick cement plaster (1:4) per 1 sqm            
a) Rate of 12 mm thick cement plaster (1:4) as per item No 16 excluding OHC          36.05  
b) Hard black granite chips 12 mm size hand broken 0.0091   1 cum 494.00 4.50  
c) Labour            
  Manson (Special) 0.155 Nos Each 85.00 13.18  
  Man Mulia  0.135 Nos Each 85.00 7.43  
d) Overhead charges @10% on (a+b+c)         6.11  
  Total(a+b+c+d)         67.27  
          Say   Rs. 67.30 /Sqm
23 Rusticated (gravel planted) plaster with cement plaster 12mm. thick (1:4) and washed gravel per 1 Sqm.            
a) Rate for 12 mm. thick cement plaster (1 :4) as per item No. 16 excluding OHC         36.05  
b) Cost of washed gravel 0.0152   1 cum 85.00 1.29  
c) Labour            
  Manson (Special) 0.081 Nos Each 85.00 6.89  
  Man Mulia  0.108 Nos Each 55.00 5.94  
d) Overhead charges @10% on (a+b+c)         5.02  
  Total(a+b+c+d)         55.19  
          Say   Rs. 55.20 /Sqm
24 Lime rule pointing over brick work with the admixture of surki per 1Sqm.            
a) Materials            
  Ghooting lime unslacked 0.0024   1 cum 1720.00 4.13  
  Surki ( C. B Brick) 0.0035   1 cum 301.00 1.05  
b) Labour            
  Manson (Special) 0.162 Nos Each 85.00 13.77  
  Woman Mulia 0.162 Nos Each 55.00 8.91  
  Man Mulia for Preparation of mortar and watering 0.014 Nos Each 55.00 0.77  
c) Overhead charges @10% on (a+b)         2.86  
  Total(a+b+c)         31.49  
          Say   Rs. 31.50 /Sqm
25 2.5 cum. thick surki beaten plaster ( 1:2) per 1
Sqm
           
a) Materials            
  Ghooting lime unslacked 0.0122   1 cum 1720.00 20.98  
  Surki screened clampburnt 0.0244   1 cum 301.00 7.34  
b) Labour            
  Manson (2nd class) 0.162 Nos Each 75.00 12.15  
  Man Mulia 0.108 Nos Each 55.00 5.94  
  Woman Mulia 0.216 Nos Each 55.00 11.88  
c) Overhead charges @10% on (a+b)         5.83  
  Total(a+b+c)         64.12  
          Say   Rs. 64.10 /Sqm
26 6 mm thick cement plaster (1 : 4) finished smooth per 1 Sqm. Sand     ( Screened & Washed). 0.0075   1 cum 29.00 0.22  
a) Materials            
  Cement 0.0019 cum 0.0271   1 Qntl 341.00 9.24  
b) Labour            
  Labour as per cement plaster (1 : 6) for brick
work items No 4.
        17.10  
c) Overhead charges @10% on (a+b)         2.66  
  Total(a+b+c)         29.22  
          Say   Rs. 29.20 /Sqm
27 6 mm thick cement plaster (1:4) to R CC surfacesfinished smooth including closed deep chiping and slury treatment. Per 1 Sqm 0.0075   1 cum 29.00    
a) Materials            
  Sand(Screened & Washed) 0.0075   1 cum 29.00 0.22  
  Cement 0.0026 cum 0.0372   1 Qntl 341.00 12.69  
b) Labour            
  Labour as per cement plaster (1 : 6) for brick work items No 4.          17.10  
  Labour for closed deep chipping & cleaning Man Mulia 0.05 Nos Each 55.00 2.75  
c) Overhead charges @10% on (a+b)         3.28  
  Total(a+b+c)         36.04  
          Say   Rs. 36.00 /Sqm
28 16 mm thick cement plaster (1:6) over brick or stone masonary including punning . Per 1 Sqm.            
a) Materials            
  Sand(Screened & Washed) 0.018   1 cum 29.00 0.52  
  Cement 0.053   1 Qntl 341.00 18.07  
b) Labour            
  Mason ( 2nd class) 0.18 Nos Each 75.00 13.50  
  Man Mulia 0.11 Nos Each 55.00 6.05  
  Woman Mulia 0.11 Nos Each 55.00 6.05  
  man mulia for mixing sand & cement 0.02 Nos Each 55.00 1.10  
c) Overhead charges @10% on (a+b)         4.53  
  Total(a+b+c)         49.82  
          Say   Rs. 49.80 /Sqm
29 Cement punning per Sqm.            
a) Materials            
  Cement 0.0008 cum 0.0114   1 Qntl 341.00 3.89  
b) Labour            
  Mason (Special) 0.027 Nos Each 85.00 2.30  
  Woman Mulia 0.027 Nos Each 55.00 1.49  
c) Overhead charges @10% on (a+b)         0.77  
  Total(a+b+c)         8.45  
          Say   Rs. 8.40 /Sqm
30 White washing 1 coat with shell lime Per 1 Sqm. Data for 93Sqm.            
a) Materials            
  Shell lime unslacked 11.8   1 Kg 13.00 153.4  
b) Labour            
  Painter (2nd class) 0.75 Nos Each 75.00 56.25  
  Man Mulia 0.5 Nos Each 55.00 27.50  
c) Overhead charges @10% on (a+b)         23.72  
  Total(a+b+c)         260.87  
          Say   Rs. 8.40 /Sqm
  Rate per 1 Sqm   = 260.87 = 2.81 /Sqm    
        93      
    Say   Rs.   2.80 /Sqm    
31 White washing 1 coat with stone lime, per 1Sqm, Data for 93 Sqm            
a) Materials            
  Stone lime (unslaked) 0.021   1 cum 1500.00 31.50  
b) Labour            
  Labour as per white washing with shell lime item
30
        83.75  
c) Overhead charges @10% on (a+b)         11.53  
  Total(a+b+c)         126.78  
          Say   Rs. 8.40 /Sqm
  Rate per 1 Sqm   = 126.78 = 1.36 /Sqm    
        93      
    Say   Rs.   1.40 /Sqm    
32 White washing two coats with Shell lime per 1
Sqm Data for 93 Sqm.
           
a) Materials            
  Shell lime ( unslaked) 18.66   1 Kg 13.00 242.58  
b) Labour            
  painter (2nd class) 1 Nos Each 75.00 75.00  
  Man Mulia 0.75 Nos Each 55.00 41.25  
c) Overhead charges @10% on (a+b)         35.88  
  Total(a+b+c)         394.71  
          Say   Rs. 394.71 /Sqm
  Rate per 1 Sqm   = 394.71 = 4.24 /Sqm    
    93          
    Say   Rs.   4.20 /Sqm    
33 White washing 2 coat with stone lime per 1Sqm
Data for 93 Sqm.
           
a) Materials            
  Stone lime (unslaked) 0.032   1 cum 1500.00 48.00  
b) Labour            
  Labour as per white washing two coats with shell
lime item 32
        116.25  
c) Overhead charges @10% on (a+b)         16.43  
  Total(a+b+c)         180.68  
          Say   Rs. 180.68 /Sqm
  Rate per 1 Sqm   = 180.68 = 1.94 /Sqm    
    93          
    Say   Rs.   1.90 /Sqm    
34 White washing 3 coats with shell lime per 1Sqm
Data for 93 Sqm
           
a) Materials            
  Stone lime (unslaked) 23.32   1kg 13.00 303.16  
b) Labour            
  Painter (2nd class) 1.5 Nos Each 75.00 112.50  
  Man mulia 1 Nos Each 55.00 55.00  
c) Overhead charges @10% on (a+b)         47.07  
  Total(a+b+c)         517.73  
          Say   Rs. 517.73 /Sqm
  Rate per 1 Sqm   = 517.73 = 5.57 /Sqm    
    93          
    Say   Rs.   5.60 /Sqm    
35 White washing 3 coats with stone lime per 1Sqm
Data for 93 Sqm
           
a) Materials            
  Stone lime (unslaked) 0.0425   1 cum 1500.00 63.75  
b) Labour            
  Labour as per white washing 3 coats with shell
lime (item 34)
        167.50  
c) Overhead charges @10% on (a+b)         23.13  
  Total(a+b+c)         254.38  
          Say   Rs. 254.38 /Sqm
  Rate per 1 Sqm   = 254.38 = 2.74 /Sqm    
        93      
    Say   Rs.   2.70 /Sqm    
36 Colour washing 1 coat with Shell lime and
colouring materials per 1 Sqm.
Data for 93 Sqm
           
a) Rate for white washing one coat with shell lime
(vide item No. 30)
        260.87  
b) Add for extra labour and colouring materials         18.00  
  Total(a+b)         278.87  
          Say   Rs. 278.87 /Sqm
  Rate per 1 Sqm   = 278.87 = 3.00 /Sqm    
        93      
    Say   Rs.   3.00 /Sqm    
37 Colour washing one coat with stone lime and
colouring materials per 1 Sqm
Data for 93 Sqm.
           
a) Rate for white washing one coat with shell lime
(vide item No. 31)
        126.78  
b) Add for extra labour and colouring materials         18.00  
  Total(a+b)         144.78  
          Say   Rs. 144.78 /Sqm
  Rate per 1 Sqm   = 144.78 = 1.56 /Sqm    
    93          
    Say   Rs.   1.60 /Sqm    
38 Colour washing two coats with shell lime and colouring mateials per 1 Sqm Data for 93 Sqm.            
a) Rate for white washing one coat with shell lime (vide item No. 32)         394.71  
b) Add for extra labour and colouring materials         25.00  
  Total(a+b)         419.71  
          Say   Rs. 419.71 /Sqm
  Rate per 1 Sqm   = 419.71 = 4.51 /Sqm    
    93          
    Say   Rs.   4.50 /Sqm    
39 Colour washing two coats with Stone lime and colouring materials per 1Sqm. Data for 93 Sqm.            
a) Rate for white washing one coat with shell lime (vide item No. 33)         180.68  
b) Add for extra labour and colouring materials         30.00  
  Total(a+b)         210.68  
          Say   Rs. 210.68 /Sqm
  Rate per 1 Sqm   = 210.68 = 2.27 /Sqm    
    93          
    Say   Rs.   2.30 /Sqm    
40 Cement washing 1 coat per 1 Sqm Data for 93 Sqm             
a) Materials            
  Cement 0.07 cum 1.001   1 Qntl 341.00 341.34  
b) Labour            
  Labour as per white washing one coat (item No.31)         83.75  
  Extra labour for mixing cement for aplication 0.5 Nos Each 55.00 27.50  
  Overhead charges @ 10% on (a+b)         45.26  
  Total(a+b+c)         497.85  
          Say   Rs. 497.85 /Sqm
  Rate per 1 Sqm   = 497.85 = 5.35 /Sqm    
    93          
    Say   Rs.   5.40 /Sqm    
41 Cement washing two coats per 1 Sqm Data for 93 Sqm            
a) Materials            
  Cement 0.105 cum 1.5015   1 Qntl 341.00 512.01  
b) Labour            
  Labour as per white washing one coat (item No.32)         116.25  
  Extra labour for mixing cement for application (Man Mulia) 0.88 Nos Each 55.00 48.40  
c) Overhead charges @ 10% on (a+b)         67.67  
  Total(a+b+c)         744.33  
          Say   Rs. 744.33 /Sqm
  Rate per 1 Sqm   = 744.33 = 8.00 /Sqm    
    93          
    Say   Rs.   8.00 /Sqm    
42 Mud and cowdung leaping per 1Sqm Data for 9.3 Sqm            
a) Labour            
  Woman mulia 0.33 Nos Each 55.00 18.15  
b) Overhead charges @ 10% on (a)         1.82  
c) 2% sundries, gum indigo and brushes on (a)         0.36  
  Total(a+b+c)         20.33  
          Say   Rs. 20.33 /Sqm
  Rate per 1 Sqm   = 20.33 = 2.19 /Sqm    
    9.3          
    Say   Rs.   2.20 /Sqm    
43 Plastering inside the well steining (labour only)
per 1 Sqm. Data for scaffolding lowering material , etc
           
a) Labour            
  Mason (Special) 0.5 Nos Each 85.00 42.50  
  Man Mulia 0.5 Nos Each 55.00 27.50  
  Woman mulia 1 Nos Each 55.00 55.00  
b) Overhead charges @ 10% on (a)         12.50  
c) 2% sundries, gum indigo and brushes on (a)         2.50  
  Total(a+b+c)         140.00  
          Say   Rs. 140.00 /Sqm
  Rate per 1 Sqm   = 140.00 = 15.05 /Sqm    
    9.3          
    Say   Rs.   15.10 /Sqm    
Note              
  (I) For inside cement or lime plaster or pointing in each subsequent floor above ground floor add 3 percent extra labour over and above the rates of next lower floor.  
  (ii) For inside white washing, colour washing, and cement washing in each subsequent floor above ground floor add 3 percent extra labour over and above the rates to next lower floors.  
  (iii) For repair items of white washing and colour washing inside add 2 percent extra labour to the respective items of next lower floor.  
  (iv) For repair items of plastering add 2 percent extra labour to the resepctive items of next lower floor.  
  (v) For out side cement plaster, white washing, colour washing and cement washing add 5 percent extra labour for scaffolding etc. over and above the rates of next lower floor.  
  (vi) for plastering, pointing, cement washing, white washing and colour washing works below ground level beyond 1.5m and uto 4.5m depth add 5 percent extra labour over and above the rates of the resepctive item for lowering the materilas.  
  (vii) for plastering , pointing, cement washing, white washing and colour washing works below ground level beyond 4.5m and upto 7.5m depth and 7 percent extra labour over and above the rates of the respective items for lowring the materials.  
  (viii) 10 percent excess on the above rates will be allowed in the works being executed inside jail premises.  

*****