WRD: 8. PRELIMINARY & MAINTENANCE WORKS
QUANTITY OF MATERIALS FOR ADDITIONAL LEAD CHARGES
Item no | Description of work | unit |
Quantity of materials required per unit quantity of work |
|||
murum cum |
cement kg |
sand/fa cum |
stone cum |
|||
8.12 | 200x200x750 mm boundary stone fixing | Each | 0.055 | 0.030 | ||
stone cum |
cement kg |
sand/fa cum |
ca cum |
|||
8.13 | Temperary BM in CC 1:4:8 | Each | 0.030 | 9.10 | 0.025 | 0.050 |
8.14 | Permanent BM in CC 1:3:6 with UCR wall | Each | 0.320 | 262.00 | 0.600 | 1.000 |
8.16 | Reconstruction of revetment | sqm | 0.153 | |||
8.17 | Reconstruction of rock-toe | cum | 0.098 | |||
8.18 | Resetting Shahbad slabs in CM 1:3 | sqm | 1.00 | 0.002 | ||
soil cum |
cement kg |
sand/fa cum |
ca cum |
|||
8.22 | Impervious hearting with borrow area soil | cum | 1.20 | --- | --- | --- |
8.23 | Semipervious casing with borrowarea soil | cum | 1.20 | --- | --- | --- |
8.24 | Impervious hearting using dump area soil | cum | 1.20 | --- | --- | --- |
8.25 | Semipervious casing using dumparea soil | cum | 1.20 | --- | --- | --- |
8.30 | Cleaning gates by sand blasting | sqm | --- | --- | 0.300 | --- |
8.39 | 40 mm th shotcreting in CC 1:2:2 propn | sqm | --- | 25.50 | 0.032 | 0.032 |
Notes:
1. The quantities of materials specified in the above table are for loose volume.
2. The quantity of cement for cement concrete items includes requirement of cement for any incidental works such as mortar layer at lift joints, repair of honeycombs etc.
3. The quantities of materials are inclusive of wastage as under:
Cement 1.00 percent.
Sand / Fine aggregate 2.00 percent.
Coarse aggregate 2.00 percent.
Stones / Stone chips 2.00 percent.
*****