ROOFING



  ROOFING (ANALYSIS OF RATES 2006)
Sl. No Description Qunatity required Unit Rate
Rs.          P
Amount
Rs.             P
Remarks
(1) (2) (3) (4) (5) (6) (7)
1 20cm to 25cm. Single Nuria tiles roofing with cement
mortar (1:6) borders 23cm×5cm at 1.8 meters intervals complete per 1 sqm.
Data for 9.3 sqm.
           
a) Materials            
  Nuria tiles 20cm to 25 cm long 1000 Nos 1000 523.00 523.00  
  Cement 0.0372 cum 0.530 qntl Qntl 341.00 180.73  
  Sand(Screened and Washed) 0.19 cum cum 29.00 5.51  
b) Labour            
  Gharami or Thacher 2 Nos Each 65.00 130.00  
  Mason (Second class) for forming cement mortar border 0.25 Nos Each 75.00 18.75  
  Woman Mulia 0.5 Nos Each 55.00 27.50  
c) Overhead charges @ 10% on (a+b)         88.55  
  Total (a+b+c) =         974.04  
  Rate per 1 Sqm   = 974.04 = 104.74/Sqm      
    9.3          
        Say Rs.104.70 /Sqm    
2 25cm to 30cm.long Single Nuria tiles roofing with cement mortar(1:6) borders 23cm×5cm at 1.80 meters intervals complete per 1 sqm.
Data for 9.3 sqm.
           
a) Materials            
  Nuria tiles 25cm to 30 cm 800 Nos 1000 647.00 517.60  
b) Labour            
  Labour and other materials as per item NO.1         362.49  
c) Overhead charges @ 10% on (a+b)         88.01  
  Total (a+b+c) =         968.10  
  Rate per 1 Sqm   = 968.10 = 104.10/Sqm      
    9.3          
        Say  Rs.104.10 /Sqm    
3 20cm to 25cm. Long double Nuria tiles roofing with
cement mortar(1:6) borders 23cm×5cm at 1.80 meters intervals complete per 1 sqm.
Data for 9.3 sqm.
           
a) Materials            
  Nuria tiles 20cm to 25 cm 2000 Nos 1000 523.00 1046.00  
  Cost of cement and sand
mortar as in Item No.1
0.530 qntl Qntl 341.00 186.24  
b) Labour            
  Gharami or Thatcher 3 Nos Each 65.00 195.00  
  Labour as per item No.1 above
(except Gharami)
        46.25  
c) Overhead charges @ 10% on (a+b)         147.35  
  Total (a+b+c) =         1620.84  
  Rate per 1 Sqm   = 1620.84 = 174.28/Sqm      
    9.3          
        Say  Rs.174.30 /Sqm    
4 25cm to 30cm. Long double Nuria tiles roofing cement mortar (1:6)borders 23cm×5cm at 1.8 meters intervals complete per 1 sqm.
Data for 9.3 sqm.
           
a) Materials            
  Nuria tiles 25cm to 30 cm long 1600 Nos 1000 647.00 1035.20  
b) Labour            
  Labour and other materials as per item NO.3         427.49  
c) Overhead charges @ 10% on (a+b)         146.27  
  Total (a+b+c) =         1608.96  
  Rate per 1 Sqm   = 1608.96 = 173.01 /Sqm    
    9.3          
    Say   Rs.   173.00 /Sqm    
5 Roofing with pan tiles with cement mortar(1:6) border 23cm×5cm at 1.80 meter intervals, complete
per 1 sqm Data for 9.3 sqm.
           
a) Materials            
  Pan tiles 2400 Nos 1000 227.00 544.80  
  Cement 0.0372 cum 0.53   Qntl 341.00 180.73  
  Sand(Screened and Washed) 0.19   Cum 29.00 5.51  
b) Labour            
  Mason (special) 1.25 Nos Each 85.00 106.25  
  Man Mulia 1 Nos Each 55.00 55.00  
  Woman Mulia 3.5 Nos Each 55.00 192.50  
c) Overhead charges @ 10% on (a+b)         108.48  
  Total (a+b+c) =         1193.27  
  Rate per 1 Sqm   = 1193.27 = 128.31 /Sqm    
    9.3          
    Say   Rs.   128.30 /Sqm    
6 Roofing with an flat and pan tiles and cement mortar
(1:6)borders 23cm ×5cm at 1.80 meters intervals,
complete per 1 sqm Data for 9.3 sqm.
           
a) Materials            
  Pan tiles 2400 Nos 1000 227.00 544.80  
  Flat tiles 14cm×14 cm×1cm  500 Nos 1000 222.00 111.00  
  Unslacked shell lime for white
washing underneath the flat tiles
2   Kg 13.00 26.00  
  Cement 0.105 1.50   Qntl 341.00 511.50  
  Sand(Screened and Washed) 1.30   cum 29.00 8.70  
b) Labour            
  Mason (special) 2 Nos Each 85.00 170.00  
  Man Mulia 1 Nos Each 55.00 55.00  
  Woman Mulia 5 Nos Each 55.00 275.00  
c) Overhead charges @ 10% on (a+b)         170.20  
  Total (a+b+c) =         1872.20  
  Rate per 1 Sqm   = 1872.20 = 201.31 /Sqm    
    9.3          
    Say   Rs.   201.30 /Sqm    
7 Roofing with pan tiles over existing G.C.I. Sheet or
A.C. sheet per 1 sqm Data for 9.3 sqm.
           
a) Materials            
  Pan tiles 1800 Nos 1000 227.00 408.60  
b) Labour            
  Mason (special) 1 Nos Each 85.00 85.00  
  Man Mulia 1 Nos Each 55.00 55.00  
  Woman Mulia 3 Nos Each 55.00 165.00  
c) Overhead charges @ 10% on (a+b)         71.36  
  Total (a+b+c) =         784.96  
  Rate per 1 Sqm   = 784.96 = 84.40 /Sqm    
    9.3          
    Say   Rs.   84.40 /Sqm    
8 Forming Cement mortar(1:6) border, 23cm×5cm at
1.80 metres invervals per 1 sqm Data for 9.3 sqm.
           
a) Materials            
  Cement 0.0372 cum 0.530   Qntl 341.00 180.73  
  Sand(Screened and Washed) 0.19   Cum 29.00 5.51  
b) Labour            
  Mason (2nd class) 0.25 Nos Each 75.00 18.75  
  Woman Mulia 0.50 Nos Each 55.00 27.50  
c) Overhead charges @ 10% on (a+b)         23.25  
  Total (a+b+c) =         255.74  
  Rate per 1 Sqm   = 255.74 = 27.50 /Sqm    
    9.3          
    Say   Rs.   27.50 /Sqm    
9 Shifting pan tiles (labour only) per 1 sqm
Data for 9.3 sqm.
           
a) Labour            
  Mason (2nd class) 1.00 Nos Each 75.00 75.00  
  Woman Mulia 1.00 Nos Each 55.00 55.00  
b) Overhead charges @ 10% on (a)         13.00  
c) 2% Sundries T & P etc.         2.60  
  Total (a+b+c) =         145.60  
  Rate per 1 Sqm   = 145.60 = 15.66 /Sqm    
    9.3          
    Say   Rs.   15.70 /Sqm    
10 Roofing or re-tiling with old flat & pan tiles over
G.C.I or asbestos sheets on repers (labour only) per 1
Data for 9.3 sqm.
           
a) Labour            
  Mason (2nd class) 1.00 Nos Each 85.00 85.00  
  Man Mulia 1.00 Nos Each 55.00 55.00  
  Woman Mulia 2.00 Nos Each 55.00 110.00  
b) Overhead charges @ 10% on (a)         25.00  
c) 2% Sundries T & P etc.         5.00  
  Total (a+b+c) =         280.00  
  Rate per 1 Sqm   = 280.00 = 30.11 /Sqm    
    9.3          
    Say   Rs.   30.10 /Sqm    
11 Re-roofing with old flat & pan tiles including cost of
cement mortar(1: 6) borders per 1 sqm.
Data for 9.3 sqm.
           
a) Materials            
  Cement 0.063 cum 0.911   Qntl 341.00 310.65  
  Sand(Screened and Washed) 0.19   cum 29.00 5.51  
b) Labour            
  Mason (Special) 1.00 Nos Each 85.00 148.75  
  Man Mulia 1.00 Nos Each 55.00 55.00  
  Woman Mulia 2.00 Nos Each 55.00 247.50  
c) Overhead charges @ 10% on (a+b)         76.74  
  Total (a+b+c) =         844.15  
               
  Rate per 1 Sqm   = 844.15 = 90.77 /Sqm    
    9.3          
    Say   Rs.   90.80 /Sqm    
12 Renewing eaves of nuria tile roof with old tiles set in
cement mortar(1:6) per 1 metre Data for 30.48 metre
           
a) Materials            
  Cement 0.0372 cum 0.530   Qntl 341.00 180.73  
  Sand(Screened and Washed) 0.19   cum 29.00 5.51  
b) Labour            
  Mason (2nd class) 3.00 Nos Each 75.00 225.00  
  Man Mulia 2.00 Nos Each 55.00 110.00  
  Woman Mulia 2.00 Nos Each 55.00 110.00  
c) Overhead charges @ 10% on (a+b)         63.12  
  Total (a+b+c) =         694.36  
               
  Rate per 1 Sqm   = 694.36 = 22.78 /RM    
    30.48          
    Say   Rs.   22.80 /RM    
13 Renewing eaves of nuria tile roof with new tiles, 20cm to 25cm long set in cement mortar(1:6) per 1 metre Data for 30.48 metre            
a) Materials            
  Nuria tiles 20cm to 25 cm 500.00   1000 523.00 261.50  
b) Labour            
  Labour, materials as per item 12 above         631.24  
c) Overhead charges @ 10% on (a+b)         89.27  
  Total (a+b+c) =         982.01  
               
  Rate per 1 Sqm   = 982.01 = 32.22 /RM    
    30.48          
    Say   Rs.   32.20 /RM    
14 Renewing eaves of nuria tile roof with new tiles, 25cm to 30cm long set in cement mortar(1:6) per 1 metre Data for 30.48 metres             
a) Materials            
  Nuria tiles 25cm to 30 cm long 400.00   1000 647.00 258.80  
b) Labour            
  Labour, materials as per item 12 above         631.24  
c) Overhead charges @ 10% on (a+b)         89.00  
  Total (a+b+c) =         979.04  
               
  Rate per 1 Sqm   = 979.04 = 32.12 /m    
    30.48          
    Say   Rs.   32.10 /m    
15 Renewing mortar band with new nuria tiles 25cm to
30 cm long set in cement mortar(1:6) per 1 meter
Data for 30.48 meter.
           
a) Materials            
  Nuria tiles 25cm to 30cm long 275.00 Nos 1000 647.00 177.93  
  cement 0.01 cum 0.14   Qntl 341.00 48.76  
  Sand(Screened and Washed) 0.08   Cum 29.00 2.32  
b) Labour            
  Mason (2nd Class) 2 Nos Each 75.00 150  
  Man Mulia 2 Nos Each 55.00 110  
  Woman Mulia 2 Nos Each 55.00 110  
c) Overhead charges @ 10% on (a+b)         59.90  
  Total (a+b+c) =         658.91  
               
  Rate per 1 Sqm   = 658.91 = 21.62 /m    
    30.48          
    Say   Rs.   21.60 /m    
16 Renewing ridges of Nuria tiles roofs with new ridge tiles set in mud mortar and top pointed with cement mortar(1:6) per 1 meter Data for 30.48 meter.            
a) Materials            
  Ridge tiles 250.00 Nos 1000 741.00 185.25  
  cement 0 .028 cum 0.40040   Qntl 341.00 136.54  
  Sand(Screened and Washed) 0.057   Cum 29.00 1.65  
b) Labour            
  labour as per item 12         445  
c) Overhead charges @ 10% on (a+b)         76.84  
  Total (a+b+c) =         845.28  
               
  Rate per 1 Sqm   = 845.28 = 27.73 /m    
    30.48          
    Say   Rs.   27.70 /m    
17 25cm to 30 cm long single layer of Nuria tile roofing
over a layer of 30 cm ×30cm ×2.50cm of flat tiles per
1 sqm Data for 9.3 sqm.
           
a) Materials            
  Nuria tiles 800 Nos 1000 647.00 517.60  
  Nuria tiles 105 Nos 1000 1210.00 127.05  
b) Labour            
  Mason (2nd Class) 0.75 Nos Each 75.00 56.25  
  Man Mulia 1 Nos Each 55.00 55.00  
  Woman Mulia 2 Nos Each 55.00 110.00  
c) Overhead charges @ 10% on (a+b)         86.59  
  Total (a+b+c) =         952.49  
               
  Rate per 1 Sqm   = 952.49 = 102.42 /Sqm    
    9.3          
    Say   Rs.   102.40 /Sqm    
18 25cm to 30 cm long single layer of Nuria tile roofing
over a layer of 30 cm ×30cm ×2.50cm of flat tiles per
1 sqm Data for 9.3 sqm.
           
a) Materials            
  Nuria tiles 1600 Nos 1000 647.00 1035.20  
  Nuria tiles 105 Nos 1000 1210.00 127.05  
b) Labour            
  Mason (2nd Class) 1.00 Nos Each 75.00 75  
  Man Mulia 3 Nos Each 55.00 165.00  
  Woman Mulia 3 Nos Each 55.00 165.00  
c) Overhead charges @ 10% on (a+b)         156.73  
  Total (a+b+c) =         1723.98  
               
  Rate per 1 Sqm   = 1723.98 = 185.37 /Sqm    
    9.3          
    Say   Rs.   185.40 /Sqm    
19 Shifting or relaying Nuria tiles in single Nuria tiles
roof (labour only) per 1 sqm. Data for 9.3 sqm.
           
a) Labour            
  Gharami 1 Nos Each 65.00 65.00  
  Man Mulia 0.5 Nos Each 55.00 27.50  
b) Overhead charges @ 10% on (a)         9.25  
c) 2% Sundries T & P etc on (a).         1.85  
  Total (a+b+c) =         103.60  
  Rate per 1 Sqm   = 103.60 = 11.14 /Sqm    
    9.3          
    Say   Rs.   11.10 /Sqm    
20 Shifting or relaying Nuria tiles in double Nuria tils
roof (labour only) per 1 sqm. Data for 9.3 sqm.
           
a) Gharami 2 Nos Each 65.00 130.00  
  Man Mulia 0.75 Nos Each 55.00 41.25  
b) Overhead charges @ 10% on (a)         17.13  
c) 2% Sundries T & P etc on (a).         3.43  
  Total (a+b+c) =         191.80  
  Rate per 1 Sqm   = 191.80 = 20.62 /Sqm    
    9.3          
    Say   Rs.   20.60 /Sqm    
21 8 cm beaten lime terracing for roof with hard stone
other than granite broken to 2.5cm per 1 Sqm.
Data for 9.3 sqm.
           
a) Materials            
  Hardstone other than granite broken to 2.5 cm size 0.79   Cum 217.00 171.43  
  Lime(Ghooting unslaked) including 0.014 cum for
lime mortar
0.23   Cum 1720.00 395.60  
  Surkhi(C.B.Brick) 0.21   Cum 301.00 63.21  
b) Labour            
  Mason (Special) 1 Nos Each 85.00 85.00  
  Man Mulia 2.5 Nos Each 55.00 137.50  
  Woman Mulia for beating and watering for 3 weeks 10 Nos Each 55.00 550.00  
c) Overhead charges @ 10% on (a+b)         140.27  
  Total (a+b+c) =         1543.01  
  Rate per 1 Sqm   = 1543.01 = 165.92 /Sqm    
    9.3          
    Say   Rs.   165.90 /Sqm    
22 8 cm beaten lime terracing for roof with washed gravel per 1 Sqm. Data for 9.3 sqm.            
a) Materials            
  Screen washed gravel (12 mm to 20 mm) 0.79   Cum 85.00 67.15  
  material as per item no 21(a)         630.24  
b) Labour            
  Labour as per item no 21(b)         772.50  
c) Overhead charges @ 10% on (a+b)         146.99  
  Total (a+b+c) =         1616.88  
  Rate per 1 Sqm   = 1616.88 = 173.86 /Sqm    
    9.3          
    Say   Rs.   173.90 /Sqm    
23 10 cm beaten lime terracing for roof with hard stone
other than granite broken to 2.5cm per 1 Sqm.
Data for 9.3 sqm.
           
a) Materials            
  Hards(tone othegr than gran)ite brokegn to 2 cm size 1.05   Cum 217.00 227.85  
  lime mortar 0.30   Cum 1720.00 516.00  
  Surkhi(C.B.Brick) 0.28   Cum 301.00 84.28  
b) Labour            
  Mason (Special) 1 Nos Each 85.00 85.00  
  Man Mulia 3.0 Nos Each 55.00 165.00  
  Woman Mulia 12 Nos Each 55.00 660.00  
c) Overhead charges @ 10% on (a+b)         173.81  
  Total (a+b+c) =         1911.94  
  Rate per 1 Sqm   = 1911.94 = 205.58 /Sqm    
    9.3          
    Say   Rs.   205.60 /Sqm    
24 10 cm beaten lime terracing for roof with washed
gravel per 1 Sqm. Data for 9.3 sqm.
           
a) Materials            
  Rate with hard broken stone as in item 23         1911.94  
b) Deduct-Difference in cost of hard broken stone and washed gravel (217.00-65.00) -1.05   Cum 152.00 -159.60  
  Total (a-b) =         1752.34  
  Rate per 1 Sqm   = 1752.34 = 188.42 /Sqm    
    9.3          
    Say   Rs.   188.40 /Sqm    
25 13 cm beaten lime terracing for roof with hard stone
other than granite broken to 2.5cm per 1 Sqm.
Data for 9.3 sqm.
           
a) Materials            
  Hards(tone othegr than gran)ite brokegn to 1 cm size 1.27   Cum 217.00 275.59  
  lime mortar 0.37   Cum 1720.00 636.40  
  Surkhi 0.35   Cum 301.00 105.35  
b) Labour            
  Mason (Special) 1.50 Nos Each 85.00 127.50  
  Man Mulia 4 Nos Each 55.00 220.00  
  Woman Mulia for beating and watering for 3 weeks 15 Nos Each 55.00 825.00  
c) Overhead charges @ 10% on (a+b)         218.98  
  Total (a+b+c) =         2408.82  
  Rate per 1 Sqm   = 2408.82 = 259.01 /Sqm    
    9.3          
    Say   Rs.   259.00 /Sqm    
26 13 cm beaten lime terracing for roof with washed
gravel per 1 Sqm. Data for 9.3 sqm.
           
a) Rate with hard broken stone as in item 25         2408.82  
b) Deduct-Difference in cost of hard broken stone and
washed gravel (217.00-65.00)
-1.27   Cum 152.00 -193.04  
  Total (a-b) =         2215.78  
  Rate per 1 Sqm   = 2215.78 = 238.26 /Sqm    
    9.3          
    Say   Rs.   238.30 /Sqm    
27 8 cm thick beaten terrace in lime with brick khoa and
ghooting lime per 1 Sqm. Data for 9.3 sqm.
           
a) Materials            
  4cm brick khoa (1st class)C.B.Brick 0.71   Cum 172.00 122.12  
  Ghooting lime unslaked 0.212   Cum 1720.00 364.64  
  Surkhi 0.212   Cum 301.00 63.81  
b) Labour            
  Labour as per item 21 1.50 Nos Each 85.00 772.50  
c) Overhead charges @ 10% on (a+b)         132.31  
  Total (a+b+c) =         1455.38  
  Rate per 1 Sqm   = 1455.38 = 156.49 /Sqm    
    9.3          
    Say   Rs.   156.50 /Sqm    
28 10 cm thick beaten lime terrace in lime with brick
khoa and ghooting lime per 1 Sqm. Data for 9.3 sqm.
           
a) Materials            
  4cm brick khoa (C.B.Brick) 0.962   Cum 172.00 165.46  
  Ghooting lime (unslaked) 0.218   Cum 1720.00 374.96  
  Surkhi ( CB Brick ) 0.283   Cum 301.00 85.18  
b) Labour            
  Labour as per item 25         1172.50  
c) Overhead charges @ 10% on (a+b)         179.81  
  Total (a+b+c) =         1977.92  
  Rate per 1 Sqm   = 1977.92 = 212.68 /Sqm    
    9.3          
    Say   Rs.   212.70 /Sqm    
29 13 cm average thick beaten terrace with brick khoa
and ghooting lime per 1 Sqm. Data for 9.3 Sqm
           
a) Materials            
  Material 4 cm brick khoa 1.19   Cum 172.00 204.68  
  Ghooting lime (Unslaked) 0.354   Cum 1720.00 608.88  
  Surkhi 0.354   Cum 301.00 106.55  
b) Labour            
  Labour as per item no 25         1172.50  
c) Overhead charges @ 10% on (a+b)         209.26  
  Total (a+b+c) =         2301.87  
  Rate per 1 Sqm   = 2301.87 = 247.51 /Sqm    
    9.3          
    Say   Rs.   247.50 /Sqm    
30 Laying two layers of earthern tiles 2.5 cm thick 30cm
×30 cm and 30 cm ×15 cm with 2.50 cm cement
mortar(1: 6)in between to receive terracing per 1 sqm
Data for 9.3 sqm.
           
a) Materials            
  Tiles 30cm×30 cm×2.5cm 105.00 Nos 1000 1210.00 127.05  
  Tiles 30cm×15 cm×2.5cm 210.000 Nos 1000 1005.00 211.05  
  cement 0.114 cum 1.630   Qntl 341.00 555.83  
  Sand (screened and washed) 0.362   Cum 29.00 10.50  
b) Labour            
  Labour            
  Mason (2nd class) 2 Nos Each 75.00 150.00  
  Man mulia 2 Nos Each 55.00 110.00  
  Woman Mulia for carring materials 4 Nos Each 55.00 220.00  
c) Overhead charges @ 10% on (a+b)         138.44  
  Total (a+b+c) =         1522.87  
  Rate per 1 Sqm   = 1522.87 = 163.75 /Sqm    
    9.3          
    Say   Rs.   163.70 /Sqm    
31 Picking out old lime terracing on roof and clearing the
debris for laying half terracing per 1 sqm
Data for 9.3 sqm.
           
a) Labour            
  Man Mulia 1.5 Nos Each 55.00 82.50  
  Woman Mulia 2.25 Nos Each 55.00 123.75  
b) Overhead charges @ 10% on (a)         20.63  
c) 2 % sundries and T&P etc on (a)         4.13  
  Total (a+b+c) =         231.01  
  Rate per 1 Sqm   = 231.01 = 24.84 /Sqm    
    9.3          
    Say   Rs.   24.40 /Sqm    
32 Labour for fixing G.C.I. Sheet in roof drilling hole in
wind ties including fixing of ridges valleys wind ties
etc. excluding cost of fitting per 1 Sqm.
Data for 9.3 sqm.
           
a) Labour            
  Carpenter (Secial) 0.5 Nos Each 85.00 42.50  
  Fitter(Secial) 1 Nos Each 85.00 85.00  
  Man Mulia 2 Nos Each 55.00 110  
b) Overhead charges @ 10% on (a)         23.75  
c) 2 % sundries and T&P etc on (a)         4.75  
  Total (a+b+c) =         266.00  
  Rate per 1 Sqm   = 266.00 = 28.60 /Sqm    
    9.3          
    Say   Rs.   28.60 /Sqm    
33 Labour for fixing big six or trafford A.C. Sheet in roof
including fixing of ridges wind ties etc. complete but
excluding cost of fitting including drilling holes in
wind ties per 1 Sqm. Data for 9.3 sqm.
           
a) Labour            
  Carpenter (Secial) 1.00 Nos Each 85.00 85.00  
  Man Mulia 3.00 Nos Each 55.00 165.00  
b) Overhead charges @ 10% on (a)         25.00  
c) 2 % sundries and T&P etc on (a)         5.00  
  Total (a+b+c) =         280.00  
  Rate per 1 Sqm   = 280.00 = 30.11 /Sqm    
    9.3          
    Say   Rs.   30.10 /Sqm    
34 Labour for fixing and fitting Asbestos sheet ridges or
valleys (double) per 1 RM Data for 30.48 RM
           
a) Labour            
  Carpenter (Special) 0.50 Nos Each 85.00 42.50  
  Carpenter (2nd Class) 1.50 Nos Each 75.00 112.50  
  Fitter(1st Class) 3.00 Nos Each 85.00 255.00  
  Man Mulia 4.00 Nos Each 55.00 220.00  
b) Overhead charges @ 10% on (a)         63.00  
c) 2 % sundries and T&P etc on (a)         12.60  
  Total (a+b+c) =         705.60  
  Rate per 1 Sqm   = 705.60 = 23.15 /Sqm    
    30.48          
    Say   Rs.   23.10 /Sqm    
35 Labour for fixing corrugated iron sheets in walling
including cost of nuts and bolts etc. but excluding cost  of sheets per 1 Sqm. Data for 9.30 sqm
           
a) Rate as per item for fixing corrugated sheet in roof
(item NO.32)
        266.00  
b) Add for cost of bolts and nuts 0.50 Nos Each 85.00 40.00  
c) Deduct-for cost of fixing ridges 1.50 Nos Each 75.00 -10.00  
  Total (a+b-c) =         296.00  
  Rate per 1 Sqm   = 296.00 = 31.83 /Sqm    
    9.3          
    Say   Rs.   31.80 /Sqm    
36 Fixing asbestos sheets in walls excluding cost of A.C.
sheet but including cost of bolts and nuts (labour only) per 1 sqm. Data for 9.30 sqm
           
a) Rate as per item No.33)         280.00  
b) Add for cost of bolts and nuts 0.50 Nos Each 85.00 40.00  
c) Deduct-for cost less labour and scaffolding 1.50 Nos Each 75.00 -12.00  
  Total (a+b-c) =         308.00  
  Rate per 1 Sqm   = 308.00 = 33.12 /Sqm    
    9.3          
    Say   Rs.   33.10 /Sqm    
37 New bamboo frames made of 2.5cm to 4cm dia
bamboo for nuria tile roofing for single and double
layers per 1 Sqm. Data for 9.30 Sqm
           
a) 2.5cm to 4cm dia 1st class bamboos= …292.61……..
R.M. (4.15 meters each av ) or say 70 Nos
70 Nos 100 1700.00 1190.00  
b) 5cm long french reapers nails 1.36 Nos Kg 40.00 54.40  
c) Man Mulia 1.50 Nos Each 55.00 82.50  
d) Overhead charges @ 10% on (a+b+c)         132.69  
  Total (a+b-c) =         1459.59  
  Rate per 1 Sqm   = 1459.59 = 156.95 /Sqm    
    9.3          
    Say   Rs.   156.90 /Sqm    
38 Non-sal wood reapers fixed on rafters with reaper
nails at 10cm centres including coaltaring the top of
the reapers for receiving pan tiled roof per 1 Sqm Data
for 9.3 sqm.
           
a) Materials            
  Non Sal wood reapers 5cm × 2.5cm
99.06m or 0.1238 cum
0.1238   Cum 9340.00 1156.29  
  5cm long french reapers nails 1.36   Kg 40.00 54.40  
b) Labour            
  Carpenter (2nd class) 0.88 Nos Each 75.00 66.00  
  Woman Mulia 1 Nos Each 55.00 55.00  
c) Overhead charges @ 10% on (a+b)         133.17  
  Total (a+b+c) =         1464.86  
  Rate per 1 Sqm   = 1464.86 = 157.51 /Sqm    
    9.3          
    Say   Rs.   157.50 /Sqm    
39 Non-sal wood reapers fixed on rafters with reaper
nails at 15cm centres including coaltaring the top of
the reapers for receiving flat and pan tiled roof per 1
Sqm Data for 9.3 sqm.
           
a) Materials            
  Non Sal wood reapers 5cm × 2.5cm 68.60m or 0.0850   Cum 9340.00 793.90  
  5cm long french reapers nails 1   Kg 40.00 40.00  
b) Labour            
  Carpenter (2nd class) 0.75 Nos Each 75.00 56.25  
  Woman Mulia 1 Nos Each 55.00 55.00  
c) Overhead charges @ 10% on (a+b)         94.52  
  Total (a+b+c) =         1039.67  
  Rate per 1 Sqm   = 1039.67 = 111.79 /Sqm    
    9.3          
    Say   Rs.   111.80 /Sqm    
40 Best thatched roofing 22.5cm in two layers 7.5cm
bottom layer and 15cm top layers including split
bamboo jaffry on top per 1 sqm.
Data for 9.3 sqm
           
a) Materials            
  Bundle of thatch 30 cm girth 350   100 208.00 728.00  
  2.5cm to 4cm dia bamboos for jaffry on top and
bottom of thatch layers
18   100 1700.00 306.00  
b) Labour            
  Man mulia 2.00 Nos Each 55.00 110.00  
  Thatcher of Gharami 1.5 Nos Each 65.00 97.50  
c) Overhead charges @ 10% on (a+b)         124.15  
  Total (a+b+c) =         1365.65  
  Rate per 1 Sqm   = 1365.65 = 146.84 /Sqm    
    9.3          
    Say   Rs.   146.80 /Sqm    
41 Split bamboo jaffry fitted and fixed on thatched roof
per 1sqm. Data for 9.3 sqm
           
a) Materials            
  2.5cm to 4.cm dia bamboo 8 Nos 100 1700.00 136.00  
b) Labour            
  Man mulia 0.50 Nos Each 55.00 27.50  
c) Overhead charges @ 10% on (a+b)         16.35  
  Total (a+b+c) =         179.85  
  Rate per 1 Sqm   = 179.85 = 19.34 /Sqm    
    9.3          
    Say   Rs.   19.30 /Sqm    
42 Best thached roofing 15cm thick including split
bamboo jaffry on top per 1 sqm.
Data for 9.3 sqm
           
a) Materials            
  Bundles of thatch 30cm girth 230 Nos 100 208.00 478.40  
  2.5cm to 4.cm dia bamboo of jaffry on top and bottom
of the thatchelayers
15 Nos 100 1700.00 255.00  
b) Labour            
  Thatcher or Gharami 1 Nos Each 65.00 65.00  
  Man mulia 1.5 Nos Each 55.00 82.50  
c) Overhead charges @ 10% on (a+b)         88.09  
  Total (a+b+c) =         968.99  
  Rate per 1 Sqm   = 968.99 = 104.19 /Sqm    
    9.3          
    Say   Rs.   104.20 /Sqm    
43 Best thatched roofing 7.5cm thick including split
bamboo jaffry on top per 1sqm. Data for 9.3 sqm
           
a) Materials            
  Bundles of thatch 30cm girth 115 Nos 100 208.00 239.20  
  2.5cm to 7.cm dia bamboo of jaffry on top and bottom
of the thatchelayers
12 Nos 100 1700.00 204.00  
b) Labour            
  Thatcher or Gharami 0.75 Nos Each 65.00 48.75  
  Man mulia 1 Nos Each 55.00 55.00  
c) Overhead charges @ 10% on (a+b)         54.7  
  Total (a+b+c) =         601.65  
  Rate per 1 Sqm   = 601.65 = 64.69 /Sqm    
    9.3          
    Say   Rs.   64.70 /Sqm    
44 First class strong bamboo framing for 23cm apart 22.5 thick thatching per 1sqm. Data for 9.3 sqm            
a) Materials            
  7cm to 10cm dia bamboo 1st class 37 Mtr 6 100.00 609.67  
  Belangi bamboo 20 Nos 100 1700.00 340.00  
b) Labour            
  carpenter 2nd class 0.50 Nos Each 75.00 37.50  
  Thatcher or Gharami 0.75 Nos Each 65.00 48.75  
  Man mulia 1 Nos Each 55.00 55.00  
c) Overhead charges @ 10% on (a+b)         109.09  
  Total (a+b+c) =         1200.01  
  Rate per 1 Sqm   = 1200.01 = 129.03 /Sqm    
    9.3          
    Say   Rs.   129.00 /Sqm    
45 Bamboo mat over bamboo frame fitted and fixed per
1sqm Data for 9.3 sqm
           
a) Materials            
  Bamboo mat including laps 9.75   Sqm 85.00 828.75  
  Belangi bamboo 2.51 cm to 4 cm dia and above 5 mtr. 5   100 1700.00 85.00  
b) Labour            
  Thatcher or Gharami 0.5 Nos Each 65.00 32.50  
  Man mulia 0.5 Nos Each 55.00 27.50  
c) Overhead charges @ 10% on (a+b)         97.38  
  Total (a+b+c) =         1071.13  
  Rate per 1 Sqm   = 1071.13 = 115.18 /Sqm    
    9.3          
    Say   Rs.   115.20 /Sqm    
46 Roofing with 2 layers of flat tiles 30cm×15cm×2.5cm
set in cement mortar (1:3) with 2.5cm. Thick cement
mortar (1:6) in between and top cement grouted
(Cuttack pattern) including cost of cement per 1Sqm. Data for 9.3 sqm
           
a) Materials            
  Flat tiles 30cm × 15cm × 2.50cm 410.00 Nos 1000 1005.00 412.05  
  Sand (screened & washed) 0.26   Cum 29.00 7.54  
  cement 0.047 cum        
    0.6721   Qntl 341.00 229.19  
b) Labour            
  Manson special            
  Man mulia 1.25 Nos Each 85.00 106.25  
  women mulia 1.5 Nos Each 55.00 82.50  
  Man mulia for mixing sand and cement 6.0 Nos Each 55.00 330.00  
c) Overhead charges @ 10% on (a+b) 1 Nos Each 55.00 55.00  
  Total (a+b+c) =         122.25  
            1344.78  
  Rate per 1 Sqm   = 1344.78 = 144.60 /Sqm    
    9.3          
    Say   Rs.   144.60 /Sqm    
47 15cm thick thatch with old and new straw thatching
including top jaffery after removal of old thatch as per
necessity per 1sqm Data for 9.3 sqm
           
a) Rate as per item No.42         968.99  
  Deduct cost of thatch ( 230 - 115 ) = 115 bundles 115.00   100 208.00 239.20  
  Total (a-b) =         729.79  
  Rate per 1 Sqm   = 729.79 = 78.47 /Sqm    
    9.3          
    Say   Rs.   78.50 /Sqm    
48 2nd class country bamboo framing for 1.5cm thatching Data for 9.3 sqm            
a) Materials            
  Country bamboo 7cm to 10cm dia 20.12 Nos 6 60.00 201.20  
  Belangi bamboos 15.00 Nos 100 1700.00 255.00  
  Coir rope 1.87   Kg 25.00 46.75  
b) Labour            
  Carpenter 2nd class 0.5 Nos Each 75.00 37.50  
  Gharami or thatcher 0.5 Nos Each 65.00 32.50  
  Man mulia 1 Nos Each 55.00 55.00  
c) Overhead charges @ 10% on (a+b)         62.80  
  Total (a+b+c) =         690.75  
               
  Rate per 1 Sqm   = 690.75 = 74.27 /Sqm    
    9.3          
    Say   Rs.   74.30 /Sqm    
49 Bamboo mat ceiling inclusive of bamboo frame fitting
fixing etc. complete per 1sqm Data for 9.3 sqm
           
a) Materials            
  Bamboo mat including over lapping 10.22   Sqm 85.00 868.70  
  Half split belangi bamboos 2.5cm to 4cm dia for
battens 3 metres long each
8 Nos 100 1700.00 136.00  
  5cm long french reaper nails 0.11   Kg 40.00 4.40  
b) Labour            
  Carpenter 2nd class 0.25 Nos Each 75.00 18.75  
  Man mulia 1.5 Nos Each 55.00 82.50  
  Women mulia 1 Nos Each 55.00 55.00  
c) Overhead charges @ 10% on (a+b)         116.54  
  Total (a+b+c) =         1281.89  
               
  Rate per 1 Sqm   = 1281.89 = 137.84 /Sqm    
    9.3          
    Say   Rs.   137.80 /Sqm    
50 6mm thick A.C. sheet flat ceiling fitted and fixed
complete excluding cost of A.C.sheets but including
batttens 5cm ×3cm×1cm Per 1sqm Data for 9.3 sqm
           
a) Materials            
  50mm × 30mm ×10mm Sal wooden strips including framing and beading the edges 1.06   Sqm 135.00 143.10  
  4 cm nail 200 Nos 1.135   Kg 36.00 40.86  
  5cm long wood screws 100 Nos 100 63.00 63.00  
b) Labour            
  Carpenter 2nd class 1 Nos Each 75.00 75.00  
  Man mulia 2 Nos Each 55.00 110.00  
  Women mulia 2 Nos Each 55.00 110.00  
c) Overhead charges @ 10% on (a+b)         54.20  
  Total (a+b+c) =         596.16  
               
  Rate per 1 Sqm   = 596.16 = 64.10 /Sqm    
    9.3          
    Say   Rs.   64.10 /Sqm    
Notes :              
  1 10 per cent excess on the above rates will be allowed for the work being executed inside jail premises.  

*****