Site Clearance



CHAPTER : 2.0
SITE CLEARANCE
Item No. Descriptions Unit Rate
2.1

Cutting of Trees, including Cutting of Trunks, Branches and Removal

Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit..

   
  (i) Girth from 300 mm to 600 mm each 214.00
  (ii) Girth from 600 mm to 900 mm each 387.00
  (iii) Girth from 900 mm to 1800 mm each 746.00
  (iv) Girth above 1800 mm each 1408.00
2.2

Clearing and Grubbing Road Land

Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.

   
  A In area of light jungle hectare 43742.00
  B In area of thorny jungle hectare 58603.00
2.3

Dismantling of Structures

Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres.

   
  (i) Lime /Cement Concrete    
  A  Lime Concrete, cement concrete grade M-10 and below cum 322.00
  B  Cement Concrete Grade M-15 & M-20 cum 380.00
  C  Prestressed / Reinforced cement concrete grade M-20 & above cum 984.00
  (ii)  Dismantling Brick / Tile work    
  A  In lime mortar cum   
  B In cement mortar cum  
  C In mud mortar cum  
  D Dry brick pitching or brick soling cum  
  (iii) Dismantling Stone Masonry    
  A  Rubble stone masonry in lime mortar cum 230.00
  B  Rubble stone masonry in cement mortar. cum 265.00
  C  Rubble Stone Masonry in mud mortar. cum 206.00
  D  Dry rubble masonry cum 195.00
  E  Dismantling stone pitching/ dry stone spalls. cum 184.00
  F  Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials. cum 206.00
  (iv)  Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level. cum 490.00
  (v)  Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet    
  A Including dismembering tonne 1242.00
  B Excluding dismembering. tonne 913.00
  C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 9.00
  (vi) Scraping of bricks dismantled from brick work including stacking.    
  A In lime/Cement mortar 1000 numbers 1011.00
  B In mud mortar 1000 numbers 361.00
  (vii) Scraping of Stone from dismantled stone masonry    
  A In cement and lime mortar cum 405.00
  B In Mud mortar cum 86.00
  (viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 13.00
  (ix) Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and dismantling of masonry works.    
  A  Up to 600 mm dia metre 150.00
  B  Above 600 mm to 900 mm dia metre 203.00
  C  Above 900 mm metre 347.00
2.4

Dismantling of Flexible Pavements

Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately.

cum 253.00
2.5

Dismantling of Cement Concrete Pavement

Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately

cum 1076.00
2.6

Dismantling Guard Rails

Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.

metre 65.00
2.7

Dismantling Kerb Stone

Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre

metre 13.00
2.8

Dismantling Kerb Stone channel

Dismantling kerb stone channel by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre

metre 19.00
2.9 Dismantling Kilometre Stone Dismantling of kilometre stone including cutting of earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back filling of pit.    
  A 5th KM stone each 308.00
  B Ordinary KM Stone each 186.00
  C Hectometre Stone each 37.00
  D Boundary Stone each
 
36.00
2.10

Dismantling of Fencing

Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable material and unserviceable material separately.

metre
 
41.00
2.11

Dismantling of CI Water Pipe Line

Dismantling of CI water pipe line upto 600 mm dia including disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of concerned department.

metre
 
103.00
2.12

Removal of Cement Concrete Pipe of Sewer Gutter

Removal of cement concrete pipe of sewer gutter upto 1500 mm dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.
metre

metre 128.00
2.13

Removal of Telephone / Electric Poles and Lines

Removal of telephone / Electric poles including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable and unserviceable material separatel

each
 
145.00

*****