CHAPTER : 2.0 SITE CLEARANCE |
|||
Item No. | Descriptions | Unit | Rate |
2.1 |
Cutting of Trees, including Cutting of Trunks, Branches and Removal Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit.. |
||
(i) Girth from 300 mm to 600 mm | each | 214.00 | |
(ii) Girth from 600 mm to 900 mm | each | 387.00 | |
(iii) Girth from 900 mm to 1800 mm | each | 746.00 | |
(iv) Girth above 1800 mm | each | 1408.00 | |
2.2 |
Clearing and Grubbing Road Land Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. |
||
A In area of light jungle | hectare | 43742.00 | |
B In area of thorny jungle | hectare | 58603.00 | |
2.3 |
Dismantling of Structures Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres. |
||
(i) Lime /Cement Concrete | |||
A Lime Concrete, cement concrete grade M-10 and below | cum | 322.00 | |
B Cement Concrete Grade M-15 & M-20 | cum | 380.00 | |
C Prestressed / Reinforced cement concrete grade M-20 & above | cum | 984.00 | |
(ii) Dismantling Brick / Tile work | |||
A In lime mortar | cum | ||
B In cement mortar | cum | ||
C In mud mortar | cum | ||
D Dry brick pitching or brick soling | cum | ||
(iii) Dismantling Stone Masonry | |||
A Rubble stone masonry in lime mortar | cum | 230.00 | |
B Rubble stone masonry in cement mortar. | cum | 265.00 | |
C Rubble Stone Masonry in mud mortar. | cum | 206.00 | |
D Dry rubble masonry | cum | 195.00 | |
E Dismantling stone pitching/ dry stone spalls. | cum | 184.00 | |
F Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials. | cum | 206.00 | |
(iv) Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level. | cum | 490.00 | |
(v) Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet | |||
A Including dismembering | tonne | 1242.00 | |
B Excluding dismembering. | tonne | 913.00 | |
C Extra over item No( V ) A and( V ) B for cutting rivets. | tonne | 9.00 | |
(vi) Scraping of bricks dismantled from brick work including stacking. | |||
A In lime/Cement mortar | 1000 numbers | 1011.00 | |
B In mud mortar | 1000 numbers | 361.00 | |
(vii) Scraping of Stone from dismantled stone masonry | |||
A In cement and lime mortar | cum | 405.00 | |
B In Mud mortar | cum | 86.00 | |
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry | sqm | 13.00 | |
(ix) Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and dismantling of masonry works. | |||
A Up to 600 mm dia | metre | 150.00 | |
B Above 600 mm to 900 mm dia | metre | 203.00 | |
C Above 900 mm | metre | 347.00 | |
2.4 |
Dismantling of Flexible Pavements Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately. |
cum | 253.00 |
2.5 |
Dismantling of Cement Concrete Pavement Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately |
cum | 1076.00 |
2.6 |
Dismantling Guard Rails Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately. |
metre | 65.00 |
2.7 |
Dismantling Kerb Stone Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre |
metre | 13.00 |
2.8 |
Dismantling Kerb Stone channel Dismantling kerb stone channel by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre |
metre | 19.00 |
2.9 | Dismantling Kilometre Stone Dismantling of kilometre stone including cutting of earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back filling of pit. | ||
A 5th KM stone | each | 308.00 | |
B Ordinary KM Stone | each | 186.00 | |
C Hectometre Stone | each | 37.00 | |
D Boundary Stone | each |
36.00 | |
2.10 |
Dismantling of Fencing Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable material and unserviceable material separately. |
metre |
41.00 |
2.11 |
Dismantling of CI Water Pipe Line Dismantling of CI water pipe line upto 600 mm dia including disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of concerned department. |
metre |
103.00 |
2.12 |
Removal of Cement Concrete Pipe of Sewer Gutter Removal of cement concrete pipe of sewer gutter upto 1500 mm dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works. |
metre | 128.00 |
2.13 |
Removal of Telephone / Electric Poles and Lines Removal of telephone / Electric poles including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable and unserviceable material separatel |
each |
145.00 |
*****