WOOD WORK



  WOOD WORK (ANALYSIS OF RATES 2006)
Sl. No Description Qunatity Required Unit Rate
Rs.      P
Amount
Rs.       P
Remarks
(1) (2) (3) (4) (5) (6) (7)
1 Dressed seasoned sal wood work framed and fixed (wrought and put up) in burgahs, rafters and posts per 1cum Data for 0.028 cum.          
a)  Material          
  Sal wood scantling sawn
(Rate based on forest corporation rates)
0.028 Cum Cum 25934.00 726.15  
b)  Labour          
  Carpenter 2nd class 0.33 Nos Each 75.00 24.75  
  Man mulia 0.33 Nos Each 55.00 18.15  
c) Overhead charges@ 10% on (a+b)       76.91  
  Total (a+b+c) =       845.96  
  Rate per 1 cum = 845.96 =30212.76 / cum    
    0.028        
      Say Rs. 30212.80 / cum    
2 Dressed seasoned sal wood work framed and fixed (wrought and put up) in trusses, purlines, frames of doors, windows, ventilabours and
beams per 1cum Data for 0.028 cum.
         
a)  Material          
  Sal wood scantling sawn
(Rate based on forest corporation rates)
0.028 Cum Cum 28378.00 794.58  
  Carpenter special 0.5 Nos Each 85.00 42.50  
b)  Labour          
  Man mulia 0.5 Nos Each 55.00 27.50  
c) Overhead charges@ 10% on (a+b)       82.21  
  Total (a+b+c) =       946.79  
  Rate per 1 cum = 946.79 =33814.01 / cum    
    0.028        
      Say Rs.33814.00/ cum    
3 32mm piasal wood or local Teak wood panelled
shutters moulded panels with all labour, iron
fittings, and wooden hinged cleats etc fitted and
fixed complete in all respect. But excluding the
cost of iron fittings Per 1Sqm
Data for a doors 1.07m x 2.13m
         
a)  Material          
  Area of shutters 0.94 × 2.0m = 1.88sqm
Piasal wood planks for shutters
2.08 sqm        
  or 0.06656 Cum Cum 40414.00 2689.96  
  Wooden hinged cleats 2 Nos Each 12.50 25.00  
b)  Labour          
  Labour for making shutters 1.88 Sqm Sqm 300.00 564.00  
i) Carpenter Special 2 Nos
85.00/each = 170.00
- - - -  
(ii) Helper 2 Nos. 65.00/each = 130.00 (170.00+130.00 = 300.00)
Labour for fixing shutters Carpenter 2nd class
1 Nos Each 75.00 75.00  
  Man mulia 1 Nos Each 55.00 55.00  
c) Overhead charges@ 10% on (a+b)       340.9  
  Total (a+b+c) =     Total = 3749.85  
  Rate per 1 cum = 3749.85 =1994.6 /cum    
    1.88        
      Say Rs.1994.60/cum    
4 32mm thick piasal wood or local teak wood fully glazed shutters complete with iron fitting and wooden hinged cleats etc., fitted and fixed in position including all labour, but excluding the cost of glass panes and iron fittings Per 1Sqm Data for a door 1.08m × 2.15 sqm.          
a)  Material          
  Area of shutters 0.94 × 2.0m = 1.88sqm Piasal wood planks for shutters 1.42        
   
0.04544
Cum 40414 1836.41  
b)  Labour          
  Labour for making shutters 1.88 Sqm Sqm 249.70 469.44  
i) Carpenter special 1.5Nos
at the rate of 85.00/each = 127.50
- - - -  
(ii)  Helper 1.88 Nos. at the rate of 65.00 = 122.20          
  Wooden hinged cleats
Labour for fixing shutters
2 Nos Each 12.50 25.00  
  Carpenter 2nd class 1 Nos Each 75.00 75.00  
  Man mulia 1 Nos Each 55.00 55.00  
c) Overhead charges@ 10% on (a+b)       246.08  
  Total (a+b+c) =     Total = 2706.93  
  Rate per 1 Sqm = 2706.93 =1439.86 /Sqm    
    1.88        
    Say Rs. 1439.90/Sqm    
5 25mm thick piasal wood or local teak wood
ledged, braced and planked 25 mm thick ledges
and braces and 25mm thick ledges and braces
and 25mm thick plank shutters completed with
iron fittings. Wooden hinged cleates etc. fixd in
position including all labour charges but
excluding the cost of iron fittings.
Per 1Sqm Data for a doors 0.90m × 1.95 sqm.
         
a)  Material          
  Area of shutters 0.79 × 1.89m = 1.49sqm
Piasal wood planks for shutters
2.16 sqm        
    0.054 Cum 40414.00 2182.36  
b)  Labour          
  Labour for making shutters          
i) Carpenter special 1 Nos
at the rate of 85.00/each = 85.00
1.49 Sqm 194.85 290.33  
(ii)  Helper 1.69 Nos. at the rate of 65.00/each
85.00+109.85=194.85 Wooden hinged cleats
2 Nos Each 12.50 25.00  
  Labour for fixing shutters          
  Carpenter 2nd class 0.5 Nos Each 75.00 37.50  
  Man mulia 0.5 Nos Each 55.00 27.50  
c) Overhead charges@ 10% on (a+b)       256.27  
  Total (a+b+c) =     Total = 2818.95  
  Rate per 1 Sqm = 2818.95 =1891.91 /Sqm    
    1.49        
    Say Rs. 1891.90/Sqm    
6 25mm thick piasal wood or local teak wood
false pannel shutters complete with iron fittings
and wooden hinged cleats, etc. fixed in
position including all labour charges, but
excluding the cost of fittings
Per 1Sqm
Data for 1.07m × 2.13 sqm.
         
a)  Material          
  Area 0.94 × 2.00m = 1.88sqm
Piasal wood planks for shutters
2.08 sqm        
    0.052 Cum 40414.00 2101.53  
  Wooden hinged cleats 2 Nos Each 12.50 25.00  
  Labour for making shutters 1.88 Sqm 196.15 368.76  
b)  Labour          
(i) Carpenter special 1 No.@ Rs85.00/ Each = 85.00        
(ii) Helper 1.71 Nos. @ Rs.65.00/ Each = 111.15        
    196.15        
  Labour for fixing shutters as per item No.3 - - - 130.00  
c) Overhead charges@ 10% on (a+b)       262.53  
  Total (a+b+c) =     Total = 2887.82  
  Rate per 1 Sqm = 2887.82 =1536.07/Sqm    
    1.88        
    Say Rs. 1536.10/Sqm    
7 19mm thick piasal wood or local teak wood
ledged, braced and planked 19 mm thick ledges
and braces and 19mm thick plank shutters
completed with iron fittings. Wooden hinged
cleates etc.fitted and fixd in position including
all labour charges but excluding the coot of iron
fittings per 1sqm
Data for 0.90m × 1.95 m.
         
a)  Material          
  Area of 0.79 × 1.89m = 1.49sqm
Piasal wood planks for shutters
1.85 sqm        
    0.03515 Cum 40414.00 1420.55  
  Wooden hinged cleats 2 Nos Each 12.50 25.00  
b)  Labour          
  Labour for making shutters as per item No.5 - - - 290.33  
  Labour for fixing shutters as per item No.5 - - - 65.00  
c) Overhead charges@ 10% on (a+b)       180.09  
  Total (a+b+c) =     Total = 1980.97  
  Rate per 1 Sqm = 1980.97 =1329.51/Sqm    
    1.49        
    Say Rs. 1329.50/Sqm    
8 38mm thick piasal pannel shutter 38mm style
and 22mm to 25 mm. thick pannel plank
complete with iron fitting and wooden hinged
cleats etc. fitted and fixed in position for doors
and windows including all labour charges, but
excluding the cost of iron fittings
Per 1 sqm
         
a)  Rate as per item No.3       1994.60  
b) Add-for excess quantity of wood 0.00664 Cum 40414.00 268.35  
c) Overhead charges@ 10% on (b)       26.83  
  Total (a+b+c) =     Total = 2289.78  
  Rate per 1 Sqm = 2289.80/Sqm        
9 25mm thick piasal pannel shutter 25mm style &
12 mm. thick pannel plank complete with iron
fitting and wooden hinged cleates etc. including
all labour charges, but excluding the cost of
iron fittings per 1sqm
         
a)  Rate as per item No. 3       1994.60  
b) Deduct-less cost of wood including OHC 0.00775 Cum 45263.68 350.79  
  Total (a-b) =     Total = 1643.81  
  Rate per 1 Sqm = 1643.80/Sqm        
10 25mm thick piasal fully glazed shutter 25mm
style complete with iron fittings and wooden
hinged cleats, etc. fitted and fixed in position
for doors and windows including all labour
charges, but excluding the cost of glass panes
and iron fittings per 1sqm rate
         
a)  Rate as per item No. 4       1439.90  
b) Deduct-less cost of wood including OHC 0.00529 Cum 45263.68 239.44  
  Total (a-b) =     Total = 1200.46  
  Rate per 1 Sqm = 1200.50/Sqm        
11 38mm thick piasal fully glazed shutter 38mm
style complete with iron fittings and wooden
higned cleats, etc. fitted and fixed in position
for doors and windows including all labour
charges, but excluding the cost of glass panes
and iron fittings per 1sqm
         
a)  Rate as per item No. 4       1439.90  
  Add-for excess quantity of wood including          
b) OHC 0.00453 Cum 45263.68 205.04  
  Total (a+b) =     Total = 1644.94  
  Rate per 1 Sqm = 1644.90/Sqm        
12 38mm thick sal wood planks fitted and fixed
for shelves Per 1 sqm
         
a)  Material          
  Sal planks 0.038 Cum 25698.00 976.52  
b) Labour          
  Carpenter 2nd class 0.75 Each 75.00 56.25  
  Man Mulia 1 Each 55.00 55  
  Total (a+b) =     Total = 1087.77  
  Rate per 1 Sqm = 1087.80/Sqm        
13 2.5cm thick sal wood frame and 19mm thick
planked door shutters complete with iron fitting
and wooden hinged cleats etc, but excluding the
cost of iron fittings. Per 1 sqm
Data for a door 1.20m × 1.95m
         
a)  Material          
  Area of shuttes 1.08m × 1.89m = 2.04sqm
Sal wood planks for shutters
2.04sqm        
    0.051 Cum 25698.00 1310.6  
b) Labour          
  Labour for making shutters 2.04 Sqm 218.25 445.23  
(i) Carpenter (second class) =1.48Nos
Rs. 75.00/each
111.00        
(ii) Helper 1.65 Nos.@ 65.00/each 107.25        
    218.25        
  Wooden hinged cleats 2 Nos Each 12.50 25.00  
  Labour for fixing shutters as per item No.5       65.00  
c) Overhead charges@ 10% on (a+b)       184.58  
  Total (a+b) =     Total = 2030.41  
  Rate per 1 Sqm = 2030.41 =995.30/Sqm    
    2.04        
    Say Rs. 995.30/Sqm    
14 Dressed sal wood works in beams above 15cm
size and above 5m length per 1cum
Data for 0.0283cum
         
a)  Seasoned sal wood 0.0283 Cum 28340.00 802.02  
b) 2% sawing, shapping, fitting & fixing etc.on       16.04  
c) Overhead charges@ 10% on (a+b)       81.81  
  Total (a+b+c) =     Total = 899.87  
  Rate per 1 Cum = 899.87 =31797.48/Cum    
    0.0283        
    Say Rs. 31797.50/Cum    
15 Sal wood work squared and rough dressed
fitted and fixed complete per 1cum
Data for 0.0283cum
         
a)  Seasoned sal wood 0.0283 Cum 25934.00 733.93  
b) 2% sawing, shapping, fitting & fixing etc.on       14.68  
c) Overhead charges@ 10% on (a+b)       74.86  
  Total (a+b+c) =     Total = 823.47  
  Rate per 1 Cum = 823.47 =29097.95/Cum    
    0.0283        
    Say Rs. 29097.90/Cum    
16 10cm dia sal bullah upto 5.50m long fitted and
fixed complete per 1R.M.
Data for 0.3048cum
         
a)  Seasoned sal bullah 0.3048 RM 69.00 21.03  
b) 2% sawing, shapping, fitting & fixing etc.on       0.42  
c) Overhead charges@ 10% on (a+b)       2.15  
  Total (a+b+c) =     Total = 23.6  
  Rate per 1 RM= 23.6 =77.42/RM    
    0.3048        
    Say Rs. 77.40/RM    
17 15cm to 20cm dia sal bullah fitted and fixed
complete per 1R.M.
Data for 0.3048 RM
         
a)  Seasoned sal bullah 0.3048 RM 76.00 23.16  
b) 2% sawing, shapping, fitting & fixing etc.on       0.46  
c) Overhead charges@ 10% on (a+b)       2.36  
  Total (a+b+c) =     Total = 25.99  
  Rate per 1 RM= 25.99 =85.27/RM    
    0.3048        
    Say Rs. 85.30/RM    
18 Sal bullah above 200mm and upto 250mm
mean dia dia upto 2.75m long fitted and fixed
complete  per 1cum
         
a)  Seasoned sal bullah 1 Cum 6503.00 6503.00  
b) 2% sawing, shapping, fitting & fixing etc.on       130.06  
c) Overhead charges@ 10% on (a+b)       663.31  
  Total (a+b+c) =     Total = 7296.37  
  Rate per 1 Cum= 7296.37/Cum      
  Say Rs. 7296.40/Cum      
19 Sal bullah above 200mm and upto 250mm
mean dia above 2.75 m & upto 4.75m long
fitted and fixed complete per 1cum.
         
a)  Seasoned sal wood 1 Cum 7284.00 7284.00  
b) 2% sawing, shapping, fitting & fixing etc. on       145.68  
c) Overhead charges@ 10% on (a+b)       742.97  
  Total (a+b+c) =     Total = 8172.65  
  Rate per 1 Cum= 8172.65 /Cum      
  Say Rs. 8172.60 /Cum        
20 75mm to 100mm mean dia nonsal bullah fitted
and fixed complete per 1R.M. Datafor 0.3048m
         
a)  Non-sal bullah 0.3048 RM (33+41)/2 11.28  
b) 2% sawing, shapping, fitting & fixing etc.on       0.23  
c) Overhead charges@ 10% on (a+b)       1.15  
  Total (a+b+c) =     Total = 12.65  
  Rate per 1 RM= 12.65 =41.51/RM    
    0.3048        
    Say Rs. 41.50/RM    
21 Non-sal bullah 125mm mean dia fitted and
fixed complete per 1R.M. Datafor 0.3048m
         
a)  Non-sal bullah 0.3048 RM 52.00 15.85  
b) 2% sawing, shapping, fitting & fixing etc.on       0.32  
c) Overhead charges@ 10% on (a+b)       1.62  
  Total (a+b+c) =     Total = 17.78  
  Rate per 1 RM= 17.78 =58.34/RM    
    0.3048        
    Say Rs. 58.30/RM    
22 Non-sal bullah 150mm to 200mm mean dia
fitted and fixed complete per 1R.M.
Data for 0.3048 m
         
a)  Non-sal bullah of above size 0.3048 RM 64.00 19.51  
b) 2% sawing, shapping, fitting & fixing etc. on       0.39  
c) Overhead charges@ 10% on (a+b)       1.99  
  Total (a+b+c) =     Total = 21.89  
  Rate per 1 RM= 21.89 =71.81/RM    
    0.3048        
    Say Rs. 71.80/RM    
23 Labour for fitting and fixing expanded metal or
wiremesh for windows etc. including sal wood
beading with cost of nails, screws, beads, etc.
complete, but excluding cost of expanded metal
or wire mesh. Per 1sqm Details for 1.54sqm
         
a)  Material          
  sal wood plank 0.0065 Cum 25698.00 167.04  
  cost of nails & screws       12  
b) Labour          
  carpenter 2nd class 0.33 Nos Each 75.00 24.75  
  skilled mulia 0.25 Nos Each 65.00 16.25  
c) Overhead charges@ 10% on (a+b)       22.00  
  Total (a+b+c) =     Total = 242.04  
  Rate per 1 RM= 242.04 =157.17/RM    
    1.54        
    Say Rs. 157.20/RM    
Note            
  1)  When 1/3 pannelled and 2/3 glazed or vice versa shutter is specified, the proportionate rate of the respective items should be worked out and the rate for the shutter                arrived.
2)  Diameter of bullahs to be measured above 2m high from the bottom.
3)  The standard fittings for Doors and windows should be as per the I.S.I. specification
4)  10 per cent excess on the above rates will be allowed for the work being executed inside jail premises

*****